m n
7590-01 UNITED STATES NUCLEAR REGULATORY COMMISSION NEBRASXA PUBLIC POWER DISTRICT DOCKET NO. 50-298 NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE AND PROPOSED NO SIGNIF'ICANT HAZARDS CONSIDERATION DETERMINATION AND OPPORTUNITY FOR HEARING The U.S. Nuclear Regulatory Comission (the Comission) is considering issuance of an amendment to Facility Operating License No. OPR-46,. issued to the Nebraska Public Power District (the licensee), for operation of the Cooper Nuclear Station located in Nemaha County, Nebrasks.
The amendment would revise the frequency for surveillance testing of main steamisolationvalves(MSIV's).
The facility Technical Specifications presently require that MSIV's be slow-speed / partial-stroke tested weekly and full-speed / full-stroke tested quarterly.
Since issuance of the Cooper Technical Specifications the staff position has been revised to reflect increased experience with MSIY testing.
The current staff position, which is consistent with ASME Section XI Inservice Testing requirements, is that stroke testing can be conducted quarterly, partial stroke only, if full stroke testing cannot be perfonned at power.
Cooper presently has an inoperable slow-speed test solenoid valve in one of its MSIV control circuits. This precludes the capability to partially stroke that valve. Because the MSIV cannot be slow-speed / partial-stroke tested weekly, it must be full-speed / full-stroke tested weekly in order to comply with the Technical Specifications. The M 1-speed / full-stroke test requires that power be reduced in order to prevent a high pressure scram.
8807150174 880708 PliR ADOCK 05000298 P
PDC c
The amendment would eliminate the weekly test. By expediting the amendment, the weekly power reductions, with the concurrent increased possibility of scram, with the attendent increased challenges to Safety 1 Relief valves can sooner be eliminated.
Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act)andtheCommission'sregulations.
The Commission has made a proposed determination that the amendment request involves no significant hazards conside,atiens. Under the Conmission's regulations in 10 CFR 50.90, this means that operation of the facility in accordance withtheproposedamendmentwouldnot(1)involveasignificantincreaseinthe probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety.
The proposed Technical Specification change is judged to involve no significant hazards based on the following:
1.
Does the proposed license amendment involve a significant increase in the probability or consequences of an accident previously evaluated?
Evaluation:
This proposed change deletes the weekly exercise of the MSIV's. The j
weekly surveillance involves partial closure of each individual valve to j
the 90% open position and reopening to the full open position.
The safety function of the MS!Y is to isolate the main steam 11ne in case of a steamline break or major fuel failure, to limit the loss of i
u 9 reactor coolant and to limit the release of radioactive materials. The MSIV's do not affect the probability of any accident occurring. Also, the test which is being deleted does not test the safety function of the MSIV's. The safety function is tested during the quarterly full stroke fast closure trip test. Since deleting the weekly partial closure test is not considered to have any affect on the reliability of the MSIV's to perform their safety function, there is no increase in the consequences of any postulated acc; dents.
P.
Does the proposed license amendment create the possibility for a new or different kind of accident from any accident previously evaluated?
Evaluation:
The safety function of the MSIV's is to mitigate the consequences of accidents by isolating the main steamline to limit the release of reactor coolant and radioactive materials. The MSIV's do not prevent the occurrence of any accident.
Failure of the MSIV'c to isolate could increase the consequences of several ace'!ents previously esaluated in Chapter 14 of the Updated Safety Evaluath- 'eport, but would not create any new or different kind of accident since they perform only a mitigation function. The elimination of the weikly exercising of the MSIV's by partial closure does not test the safety function of the valves, and therefore, canrot increase the consequences of an accident.
Since the MSIV's perform a mitigating safety function, and the quarterly test adequately tests the safety function, elimination of the weekly test cannot create any new or different kind of accident.
3.
Does the proposed license amendment involve a significant reduction in a margin of safety?
Evaluation:
The deletion of the weekly partial closure test of the MSIV's does reduce the frequency of testing the MSIV's. This could be considered to reduce the margin of safety for the MSIV's, however, the test to be deleted does not test the safety function of the valves, and therefore, does very little to test any function or capability of the valve.
The weekly partial closure test uses a test solenoid valve to change the position of the three way pilot valve, which slowly exhausts the air pressure that holds open the MSIV. As the air pressure is reduced, the springs in the MSIV start to close the valve. At the 90% open position, a limit switch is tripped and the test solenoid vaive is de-energized by the operator, allowing the MSIV to return to its full open position. The normal MSIV isolation does not rely upon the test solenoid valve for full closure. The only purpose that this test fulfills is a weekly check to verify that the MSIV is not binding. The MSIV's are tested quarterly, and this test adequately verifies that the MSIV's are not binding and that the valves will perform their safety function.
The quarterly full stroke fast closure trip test is considered to be adequate, since this is the only test required by the ASME Boiler and Pressure Vessel Code and the Standard Technical Specifications (STS).
Also, a quarterly test is all that is required of the other power operated primary containment isolation valves.
. Based upon the discussion above, the weekly partial closure test does not test the safety function of the MSIV's, the quarterly full stroke fast closure test is clearly a better test and deletion of the partial closure test would m t significantly reduce any margin of safety.
Accordingly, tne Comission proposes to determine that this change does not involve significant hazards considerations.
The Comission is seeking public coments on this proposed determination.
Any coments received within 15 days after the date of publication of this notice will be considered in making any final determination. The Comission will not normally make a final determination unless it receives a request for a hearing.
Written comments may be submitted by mail to the Rules and Procedures Branch, Division of Rules and Records, Office of Administration and Resources Management, U. S. Nuclear Regulatory Comission, Washington, D.C. 20555, and should cite the publication date and page number of the FEDERAL REGISTER notice.
Written comnents may also be delivered to Room 4000, Maryland National Bank Building, 7735 Old Georgetown Road, Bethesda, Maryland from 8:15 a.m. to 5:00 p.m.
Copies of written coments received may be examined at the NRC Public Document Room, 1717 H Street, NW, Washington, D.C.
The filing of requests for hearing and petitions for leave to intervene is discussed below.
By July 29, 1988
. the licensee may file a request for a i
hearing with respect to issuance of the amendment to the subject facility operating license and any person whose interest may be affected by this proceed-ing and who wishes to participate as a party in the proceeding must file a
written request for hearing and a petition for leave to intervene. Requests for a hearing and petitions for leave to intervene shall be filed in accordance with th'e Connission's "Rule of Practice for Domestic Licensing Proceedings" in 10 CFR Part 2.
If a request for a hearing or petition for leave to intervene 1
is filed by the above date, the Comission or an Atomic Safety and Licensing l
Board, designated by the Comission or by the Chairman of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the designated Atomic Safety and Licensing Board will issue a notice of hearing or an appropriate order.
As required by 10 CFR 2.714, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding. The petition shouid specifically explain the reasons why intervention should be perriitted with particular reference to the following factors:
(1) the nature of the petitioner's right under the Act to be made a party to the proceeding; (2) the nature and l-2xtent of the petitioner's property, financial, or other interest in the proceeding; and (3) the possible effect of any order which may be entered in the I
proceeding on the petitioner's interest. The petition should also identify the specificaspect(s)ofthesubjectmatteroftheproceedingastowhich petitioner wishes to intervene. Any person who has filed a petition for leave to intervene or who has been admitted as a party may amend the petition without requesting leave of the Board up to fifteen (15) days prior to the first pre-hearing conference scheduled in the proceeding, but such an amended petition must satisfy the specificity requirements described above.
Not later than fifteen (15) days prior to the first prehearing conference scheduled in the proceeding, a petitioner shall file a supplement to the petition to intervene, which must include a list of the contentions that are sought to be litigated in the matter, and the bases for each contention set forth with reason-able specificity. Contentions shall be limited to matters within the scope of the amendment under consideration. A petitioner who fails to file such a supple-ment which satisfies these requirements with respect to at least one contention will not be permitted to participate as a party.
These pemitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing, including the opportunity to present evidence and cross-examine witnesses.
If the amendment is issued before the cxpiration of 30-days, the Comission will make a final determination on the issue of no significant ha7ards consider-ations.
If a hearing is requested, the final determination will serve to decide when the hearing is held.
If the final detemination is that the amendment request involves no significant hazards considerations, the Commission may issue the amendment and make it effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment.
If the final determination is that the amendment request involves signifi-cant hazards considerations, any hearing held would take place before the issuance of any amendment.
Nomally, the Comission will not issue the amendment until the expiration of the 15-day notice period. However, should circumstances change during the i
l
8-notice period, such that failure to act in a timely way would result, for example, in derating or shutdown of the facility, the Comission may issue the license amendment before the expiration of the 15-day notice period, provided that its final determination is that the amendment involves no significant hazards considerations. The final detemination will consider all public and State coments received.
Should the Comission take this action, it will publish a notice of issuance. The Comission expects that the need to take this action will occur very infrequently.
A request for a hearing or a petition for leave to intervene must be filed with the Secretary of the Comission, U.S. Nuclear Regulatory Comission, Washington, D.C.
20555, Attention: Docketing and Service Branch, or may be delivered to the Comission's Public Document Room,1717 H Street, N.W.
Washington, D.C., by the above date. Where petitions are filed during the last ten (10) days of the notice period, it is requested that the petitioner promptly so inform the Comission by a toll-free telephone call to Western Union at1-(800)325-6000(inMissouri 1-(800)342-6700). The Western Union operator should be given Datagram Identification Number 3737 and the following message addressed to Herbert N. Berkow:
petitioner's name and telephone number; date petition was mailed; plant name; and publication date and page number of this FEDERAL REGISTER notice. A copy of the petition should also be sent to the l
Office of the General Counsel, U.S. Nuclear Regulatory Comission, Washington, D.C, 20555, and to Mr. G. D. Watson, Nebraska Public Power District, Post Office Box 499, Columbus, Nebraska 68601, attorney for the licensee.
Nontimely filings of petitions for leave to intervene, amended petitions, supplemental petitions and/or requests for hearing will not be entertained absent 1
i
.g.
a determination by the Comission, the presiding officer or the presiding Atomic Safety and Licensing Board that the petition and/or request should be granted baseduponabalancingofthefactorsspecifiedin10CFR2.714(a)(1)(i)-(v) and 2.714(d).
For further details with respect to this action, see the application for amendment dated July 5, 1988, which is available for public inspection at the Comission's Public Document Room,1717 H Street, N.W., Washington, D. C.
20555, and at the Local Public Dact.. tent Room, Auburn Public Library,11815th Street, Auburn, Nebraska 68305.
Dated at Rockville, Maryland, this 8th day of July 1988.
FOR THE NUCLEAR REGULATORY COMMISSION William O. Long, Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation