Monthly Operating Rept for Sept 1978
ML20150A994
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 10/11/1978
From: Shively C
ARKANSAS POWER & LIGHT CO.
To:
Shared Package
ML20150A989 List:
References
NUDOCS 7810200070
Download: ML20150A994 (8)


Text

..

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-313 UNIT 1

D ATE 10-11-78 COMPLETED f;y C. N. Shively TELEPfl0NE 501/968-2519 MONTil SeP_t emb er DAY AVERAGE DAILY POWER LEVEL DAY AVER AGE DAILY POWER LEVEL (MWe Net)

(MWe Net) 3 811 17 661 2

All 18 769 3

813 39 777 4

R12 20 816 21 810 5

R10 6

809 22 816 7

810 23 R?n 8

ROR 24 821 9

807 25 820 10 An7 26 822 11

_ &O8 27 821 12 811 28 821 13 812 29 821 14 R19 30 R96 15 Al?

31 NA 16

_451 INSTRUCTIONS On thh format, hst the average daily unit power inel in MWe-Net for each day lii the ieporting inonth. Coiripute to the nearest whole nwgawatt.

(9 /77 )

7&o 2.oo,7o

4 s

OPERATING DATA RLPORT DOCKET NO.

50-313 DATE in_11_7g COMPLETED BY c'. M. shively TELEPHONE 501/968-2519 OPERATING STATUS

  • UI'*
1. Unit Name:

Arknn m Nuc1onv Ono

2. Reporting Period: Sentember 1 - September 30, 1978
3. Licensed Thermal Pow er (M% t p

?s6R

4. Nameplate Rating (Gross Mbe):

902.74

5. Design Electrical Rating (Net MWe): 850
6. Maximum Dependable Capacity (Gross MWe): 883
7. Maximum Dependable Capacity (Net MWe):

836

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:

Nnno

9. Power Lesel To Which Restricted. lf Any (Net MWe):

None

10. Reasons For Restrictions. lf Any:

NA This Month Yr..to.Date Cumulative

11. Hours in Reporting Period 720.0 6551.0 33162.0'
12. Number Of Hours Reactor was Critical 711.6 4603.0 23532.0
13. Reactor Reserve Shutdown Hours 0.0 647.6 1966.3
14. Hours Generator On.Line 709.0 4509.3 23044.7
15. Unit Resene Shutdown Hours 0.0 113.7 205.2
16. Gross Thermal Energy Generated (MWH) 1796653.

10931362.

55373888.

17 Grow Electrical Energy Generated (MWH) 547670 _,,,

3653430.

18399341.

18. Net Electrical Energy Generated (MWH) s71sR6-1484814.

17550564.

19. Unit Service Factor 98.5 68.8 69.5
20. Unit Availability Factor 98.5 70.6 70.1
21. Unit Capacity Factor (Using MDC Net) 95.0 63.7 63.3
22. Unit Capacity Factor (Using DER Net) 93.4 62.7 62.3
23. Unit Forced Outage Rate 1.5 13.0 11.7
24. Shutdowns Scheduled Oser Next 6 Months (Type. Date, and Duration of Eacht:
25. If Shut Down At End Of Report Period. Estimated Date of Startup:
26. Units in Test Status (Prior io Commercial Operation):

Forecast Achieved INITI A L CRITICALITY INITIAL ELECTRICITY COMMERCI AL OPER ATION (9/77 )

j

UNIT SEIUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-313 UNIT NAME ANO-Unit I DATE 10/2/78 REPORT MONTil Sept.,1978 COMPLETED BY

_C.N.

Shively TELEPfl0NE 501-968-2519

~.

=

-a $

E

,s?

Licensec f

.=E e_

t has been submitted i

for Cveles 2 and 3

[I I

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

11-1-78 c

6.

Important licensing considerations associated with refueling, e.g.,

new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures.

t Will reload 64 f resh fuel assemblies and operate for appro xima tel y 16 months

}

]

4 m.

7.

The number of fuel assemblics (a) in the core and (b) in the spent fuel storage pool, a) 177 b) 112 4

8.

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblics.

r present 590 increase size by 0

9.

The projected date of the last refueling that can be Oischarged to the spent fuel pool assuming the present licensed capacity.

1 DATE: March 1988 e

l-f

[

E CORRECTION N

~

OPER ATING DATA' REPORT DOCKET NO.

__50-313-DATE

_7-11-78 COMPLETED BY c _ C. N. Shively-TELEPHONE. 50) /968-2519 OPERATING STATUS -

1. Unit Name: - Arkansas Nuclear One-Unit 1 N l'5
2. Reporting Period: - June 1, 1978 - June 30, 1978
3. Licensed Thennal Power (MWt U 2568
4. Nameplate Rating (Gross MWe):

902.74 5,' Design Electrical Rating (Net MWe):

850

6. Maximum Dependable Capacity (Gross MWe):

803

7. Maximum Dependable Capacity (Net MWe)!

836

8. If Changes Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report.Give Reasons:

Nnne i

4

9. Power Level To Which Restricted. If Any (Net MWe):

None

10. Reasons For Restrictions,if Any; NA This Month Yr..to Date Cumulative :
11. Ilours In Reporting Period 72 0, 0___

4343.0 30954.0

12. Number Of llours Reactor Was Critical 717.8 2419.4 21 M.4
13. Reactor Reserve Shutdown flours 0.0 647.6 1966.3
14. Hours Generator On Line 712.2 2333.2 20868.6
15. Unit Reserve Shutdown flours 0.0 113.7 205.2-
16. Gross Thermal Energy Generated (MWil) 1812874.0 5399444.0 49841970.0
17. Gross Electrical Energy Generated (MWH) 611452.0 1816562.0 16562473.0
18. Net Electrical Energy Generated (MWil) 585542.0 1733105.0 15793855.0 l
19. Unit Service Factor 98.9 53.7 6 7. 4. -
20. Unit Availability Factor 98.9 56.3 68.1-
21. Unit Capacity Factor (Using MDC Net) 97.3~

47.7 61.0

22. Unit Capacity Factor (Using ()ER Net!

95.7 46.9 60.0

23. Unit Forced Outage Rate 1.1 21.6 12.6
24. Shutdowns Scheduled Over Next 6 Months (Type. Date, and Duration of Each p NA
25. If Shut Down At End Of Report Period, Estimated Date of Startup:

NA

26. Units In Test Status (Prior to Commercial Operationp Forecast Achieved INITIA L CRITICA LITY INITIAL ELECTRICITY COMMERCIAL OPERATION i

(9/77)

x.<

>. CORRECTION 4 l

OPERATING DATA REPOR T '

DOCKET NO 50-313 DATE Y3W COMPLETED BY C. N. Shively TELEPHONE. 501/968-2519 OPERATING STATUS

1. Unit Name:

Arkansas Nuclear One Notes

2. Reporting Period: July 1 - July 31. 1978
3. Licensed Thennal Power (MWI):

2568 902.74

4. Nameplate Rating (Gross MWe):

850-

5. Design Electrical Rating (Net MWe):
6. Maximum Dependable Capacity (Gross MWe):

883 836

7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

None

9. Power Lesel To Which Restricted. lf Any (Net MWe):

None-

10. Reasons For Restrictions.lf Any:

NA This Month Yr..t o-Date Cumulative i1. Hours in Reporting Periad 744.0 5087.0 31698.0

12. Number Of Hours Reactor Was Critical 744.0 3163.4 22092.4
13. Reactor Reserve Shutdown Hours 0.0 647.6 1966.3 14, Hours Generator On Line 744.0 3077.2 21612.6
15. Unit Reserve Shutdown Hours 0.0 113.7 205.2
16. Gross Thermal Energy Generated (MWH) 1904845.

7304289.

51746815.

17 Gross Electrical Energy Generved (MWH) 033403*

245005C 17195966, i6. Net Electrical Energy Generated (MWH) 6060 W._.

2339185.

16399935.

19. Unit Service factor 100.0 60.5 68.2 5
20. Unit Asailability Factor 100.0 62.7-68.B ~

l

21. Unit Capacity Factor IUsing MDC Net) 97.4' 55.0 61.9
22. Unit Capacity Factor (Using DER Net) 95.8 54.1 60.9
23. Unit Forced Outage Rate 0.0 17.3 12.2
24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Eacht:

NA

25. If Shut Down At End Of Report Period. Estimated Date of Startup: -- N A
26. Unitt in Test Sietus (Prior Io Commercial Operation):

Forecast Achieved

(

INITIAL CRITICA LITY f'

INITI A L ELECTRICITY COMMERCI AL OPER ATION (4/77)

+

s e.s

-m-m.

,2

7

> CORRECTION ' <

s OPERATING DATA REPORT DOCKET NO.

50-313~

pc-9/17tTI8 tb b'

g OPERATING ST ATUS Arkarisas Nuclear One Notes J. Unit Name:

2. Reporting Period:- August 1, 1978-August 31, 1978.

2NO 3.1.ieensed Thermal Power (Mh t):

902.74

4. Nameplate Rating (Grou MWe):

850

5. Design Electrical Rating (Net MWe):

883

6. Maximum Dependable Capacity (Gross MWe):
7. Maximum Dependable Capacity (Net MWe):
h. If(.hanges Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report.Ghe Reasons:

NONE

9. Power LesciTo Which Restricted,1f Any(Net MWe):

NONE

10. Reasons For Restrictions,if Any:

NA This Month Yr. to Date Cumulative 744.0 5831.0 32442.0 i1. ifours in Reporting Period

12. Number Of flours Reactor Was Critical 728.0 3891.4 22820.4
13. Reactor Reserve Shutdown flours 0.0 W.6 1966.3
14. Ilours Generator On Line 723.1 3800.3 22335.7
15. Unit Reserve Shutdown flours 0.0 113.7 205.2
16. Gross Thermal Energy Generated (MWil) 1830420.

9134709.

53577235.

17 Gross Electrical Energy Generated (MWil) 605743 3055810.

17801721.

18. Net Electrical Energy Generated (MWH) 579031.

2918228.

16978978.

19. Unit Service f actor 97.2 65.2 68.8
20. Unit Availability Factor 97.2 67.I 69.5 21'. Unit Capacity factor (Using MDC Net) 93.1 59.9 62.6
22. Unit Capacity Factor (Using DER Net) 91.6 58.9 61.6 23, Unit Forced Outage Rate 2.8 14.9 12.0
24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Each):

NA

25. If Shut Down At End Of Report Period, Estimated Date of Startup: EA 26, Units In Test Staius (Prior to Commercial Operation)!

Forecast Achieved INITIA L CRITICA LITY INITIAL ELECTRICITY COMNil:RCI A L OPER ATION (9/77)