ML20149K184

From kanterella
Jump to navigation Jump to search
Final Deficiency Rept CP-87-85 Re Degradation of Class 1E Circuits.Initially Reported on 870903.Corrective Actions for Unit 1 Currently Scheduled for Completion Prior to Heatup
ML20149K184
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/17/1988
From: Counsil W, John Marshall
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-87-85, TXX-88236, NUDOCS 8802230400
Download: ML20149K184 (1)


Text

,

F. -

FE Log # TXX-88236 C

File # 10110

.r

=

907

" * (')

1UELECTRIC wmi.m c. co.n.n February 17, 1988 Executive Vke President V. S. Nuclear Regulatory Commissian Attn:

Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION DOCKET N05. 50-445 AND 50-446 DEGRADATION OF CLASS 1E CIRCVITS SDAR:

CP-87-85 (FINAL REPORT)

Gentlemen:

On September 3, 1987, we verbally notified your Mr. H. S. Phillips of a deficiency involving the degradation of Class 1E circuits. Our latest report was logged TXX-7124, dated December 23, 1987.

This report is submitted to provide the corrective action completion schedule for this issue.

Corrective actions for Unit 1 are currently scheduled for completion prior to Unit 1 heatup.

Unit 2 corrective actions will be implemented prior to Unit 2 hot functional testing.

Very truly yours,

((} u h, 0s u n Sc b W. G. Counsil By:

J. S. Marshall Supervisor, Generic Licensing VIP /grr c-Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) 8002230400 ggoy37 gDR ADOCK 05000445 PDR g