Supplemental Deficiency Rept CP-86-62 Re Misinterpretation of Polar Crane Load Cases.Initially Reported on 861003.Addl Polar Crane Rail Hold Down Clips for Unit 2 Now Installed
ML20149J054
Person / Time
Site: Comanche Peak  
Issue date: 02/18/1988
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-86-62, TXX-88231, NUDOCS 8802220252
Download: ML20149J054 (1)


Text

MEE log # TXX-63231 2

File # 10110

.r r

903.8

('

illELECTRIC

$$USdE$=

February 18, 1988 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 POLAR CRANE SUPPORT STRUCTURE SDAR:

CP-86-62 (SUPPLEMENTAL REPORT)

Gentlemen:

On October 3, 1986, we notified you by our letter, logged TXX-6011, of a deficiency involving a misinterpretation of the polar crane load cases, which we deemed reportable under the provisions of 10CFR50.55(e). Our most recent report submitted to status the implementation of corrective action was logged TXX-88123 dated January 18, 1988.

The additional polar crane rail hold down clips for Unit 2 are now installed.

This completes our reporting on the subject SDAR.