G1rtid R. Riincy
%ce President Peach Bottorn Atornic Power Station PECO ENERGY reco eee,9< ceen v RD 1, Box 208 Delta. PA 17314-9739 717 456 7014 November 7,1994 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Docket Nos. 50-277 and 50-278 Gentlemen:
Enclosed are twelve copies of the monthly operating report k.r Peach Bottom Units 2 and 3 for the month of October 1994 forwarded pursuant to Technical Specification 6.9.1.d under the guidance of Regulatory Guide 10.1, Revision 4.
Sincerely, Geral R. Rainey Vice President, Peach B$ om Atomic ower Station GR H /TtfN/
jj enclosures cc:
R.A. Burricelli, Public Service Electric & Gas W.P. Dornsife, Commonwealth of Pennsylvania R.I. McLean, State of Maryland T.T. Martin, Administrator, Region I, USNRC W.L. Schmidt, USNRC, Senior Resident inspector H.C. Schwemm, Atlantic Electric A.F. Kirby, Ill, Delmarva Power & Light INPO Records Center
- q;.;+t t
v.
n f
%EM i
ccn 94-14171 9411180187 941031 POR ADDCK 05000277 R
5 1
PEACH BOTTOM ATOMIC POWER STATION NRC MONTHLY OPERATIONS
SUMMARY
OCTOBER 1994 k
UNTT 2 Unit 2 began the month of October shutdown in the middle of the 10th refueling outage. Unit 2 began start-up on October 19th when the mode switch was placed to the " start-up" position. The unit completed the refueling outage on October 22nd at 9:48 A.M. when the generator was placed on the grid. The remainder of October was dedicated to power ascension and rerate start-up testing.
J The unit exceeded 1098 Mwe on October 29th and reached the new rerated 100% nominal power later the same day. Unit 2 operated at that power level for the remainder of October.
UNIT 3 Unit 3 began the month of October at nominal 100% power. The Unit operated at that power level until the 8th when power was reduced to perform a rod pattem adjustment and scram time testing.
The unit was retumed to 100% nominal power later the same day. On October 11th an automatic reactor scram occured due to high reactor water level caused by reactor feed pump control problems which were caused by the loss of power from the static inverter. After repairs the unit was restarted on October 15th and reached 100% nominal power on October 17th. Unit 3 operated at 100% nominal power for the remainder of October.
t, W
P Docket No. 50-277 P
Attachment to Monthly Operating l
Report for October 1994 UNIT 2 REFUEUNG INFORMATION
?'
1.
Name of facility:
Peach Bottom Unit 2 2.
Scheduled date for next refueling shutdown:
Reload 11 scheduled for September 20,1996.
3.
Scheduled date for restart following refueling:
Restart following refueling forecast for November 2,1996.
4.
Will refueling or resumption of operation therefore require a technical specification change or other license amendment?
N/A If answer is yes, what, in general, will these be?
5.
Scheduled date(s) for submitting proposed licensing action and supporting information:
N/A 6.
Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods. significant changes in fuel design.
new operating procedures:
N/A 7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:
i (a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2420 Fuel Assemblies,59 Fuel Rods i
4 Docket No. 50-277 Attachment to Monthly Operating Report for October 1994 Page 2 1
UNIT 2 REFUEUNG INFORMATION (Continued) 8.
The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacrty that has been requested or is planned. in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.
9.
The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
September 2002 without full core offload capability.
September 1998 with full core offload capability, i
Docket No. 50-278 Attachment to Monthly Operating Report for October 1994 UNIT 3 REFUEUNG INFORMATION 1.
Name of facility:
Peach Bottom Unit 3 2.
Scheduled date for next refueling shutdown:
Reload 10 scheduled for September 11,1995 3.
Scheduled date for restart following refueling Restart following refueling scheduled for November 13,1995 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
No if answer is yes. what, in general, will these be?
5.
Scheduled date(s) for submitting proposed licensing action and supporting information:
N/A 6.
Important licensing considerations associated with refueling, e g., new or different fuel design er supplier, unreviewed design or performance analysis methods, significant changes in fuel design.
new operating procedures:
N4 7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:
(a) Core - 764 Fuel Assemboes (b) Fuel Fool - 2201 Fuel Assemblies,6 Fuel Rods 8.
The present licensed spent fuel pool storage capacq and the size of any increase in licensec storage capac:ty that has been recuested or is planned. in number of fuel assemblies:
The scent fuel pool storage capacity has been relicensed for 3819 fuel assemoiies.
P Decket No. 50-278 A"achment to Monthly Operating Report for October 1994 Page 2 UNIT 3 REFUEUNG INFORMATION (Continued) 9.
The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
September 2003 wrthout full core offload capability.
September 1997 with full core offload capability.
AVERAGE DA!LY UNIT POWER LEVEL DOCKET No. 50 - 277 UNIT PEACH BOTTOM UNIT 2 s
DATE kCVEMBER 7,1994 COMPANY PECO ENERGY COMPANY W. J. JEFFREY PERFORMANCE AND RELIABILITY SITE ENGINEERING PEACH BCTTOM ATOMIC POWER STATION TELED40hE (717) 456-7014 EXT. 4027 MONTH CCTCBER 1994 DAY AVERAGE CAILY PC%ER LEVEL OAY AVERAGE DAILY PCWER LEVEL (WE-NET)
(MWE hET) 1 0
17 0
2 0
18 0
3 0
19 0
4 0
20 0
5 0
21 0
6 0
22 104 7
0 23 146 8
0 24 217 9
0 25 304 r
10 0
26 522 11 0
27 960 12 0
28 10-8 13 0
29 1M6 14 0
30 1**!
15 0
31 11*e 16 0
]
a AVERAGE DA!LY UNIT POWER LEVEL l
00CKET No. 50 - 278 UNIT PEACH BOTT34 UNIT 3 i
OATE NOVEMBER 7,1994 I
COMPANY PECO ENERGY COMPANY W. J. JEFFREY PERFORMANCE AND RELIABILITY SITE ENGINEERING PEACH BOTTOM ATOMIC POWER STATION i
TELEPHONE (717) 456-7014 Exi. 4027 MONTH OCTOBER 1994 DAY AVERACE CA!LY POWER LEVEL DAY AVERAGE CA!LY POWER LEVEL (wwE-NET)
(MWE-NET) 1 1049 17 1040 2
1049 18 1060 i
3 1056 19 1055 4
1057 20 1059 5
1064 21 1061 6
1049 22 1058 7
1050 23 1050 J
i 8
1030 24 1064 9
1054 25 1065
'10 1058 26 1056
)
11 500 27 1065 12 0
23 1052 13 0
29 1059 1.
C 30
'05a 15 291 31 1053 16 S73 1
j
+
1 5
OPERATING DATA REPORT DOCKET NO. 50 - 277 DATE NOVEMBER 7,1994 i
i COMPLETED BY PECO ENERGY COMPANY W. J. JEFFREY PERFORMANCE AND RELIABILITY SITE ENGINEERING PEACH BOTTOM ATOMIC POWER STATION TELEPMohE (717) 456-7014 EXT. 4027 OPERATING STATUS
- 1. UNIT NAME: PEACH BOTTOM UNIT 2 l NOTES:
l
- 2. REPORTING PERIOC:
CCTCBEa, 1994 i LICENSED TPERMAL POWER INCREASED FR> l l
- 3. LICENSED THERMAL POWER (MWT):
3458 3293MWT to 3458 MWT. DUE TO POWER
- 4. NAMEPLATE RAT!hG (GROSS M.E):
1152 RERATE DURlkG THE REFUELING OUTAGE
- 5. OES!GN LECTRICAL RATING (hET MWE):
1C65 OTHER RATINGS WILL BE CHAhGED UPON
- 6. MAXIMUM DEPENDABLE CAPACITY (CROSS M ): b98 COMPLETION OF PERFORMANCE TESTING.
- 7. MAXIMUN :EPENDABLE CAPACITi (hET MWE):
kb5k
- 8. IF CHANCES OCCUI IN CAPACITY RAT!h;S (!TEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASchS:
- 9. PUWER LEVEL TO WHICh ;ESTRICTED, IF ANY (NET WE):
- 10. REASCNS FCR RESTRICTIONS, IF ANY:
THl$ MCNTH YR-TO-DATE CUMULATIVE
- 11. HOURS IN REPORTING PERICO 745 7,296 178,176
- 12. NUMBER OF HOURS REACTOR '.AS CR!TICAL hb
$3bbb Ikh,4h9$k
- 13. REACICR RESERVE SnUTDCu C AS bb bb b$b
- 14. MOURS GENERA *CR Ch LlhE 230.0 6,319.0 108,539.2
- 15. UNIT RESE4vE SwuTOC%N HOURS b$b b$b b$b
- 16. GRCSS TeEE"A. ENERGY GE% ERA *E? (u.*)
53*,3'7 i8,792,499 323,281,992
- 17. GRCSS ELECTR; CAL E4ERGf GE%ERATED (w.w) 16c,200 6,041,500 106,193,290
- 18. NET LLECTRICAL EhERGY GENERATED (ww) 157,620 5,813,694 101,804,496 t
PAGE 1 CF 2 I
I
OPERATING DATA REPORT (CONTINUED)
DOCKET h0. 50 - 277 DATE h0VEMBER 7,1994 THIS MONTH YR-TO-DATE CUMULATIVE
- 19. UNIT SERV!CE FACTOR 30.9 86.6 60.9
- 20. UNIT AVAILABILITY FACTOR 30.9 B6.6 60,9
- 21. UNIT CAPACliY FACTCR (US!hG MOC AET) 20.1 75.8 54.4
- 22. UNIT CAPACITY FACTOR (USING OER hET) 19.9 74.8 53.6
- 23. UNIT FORCED OUTAGE RATE 0.0 1.9 13.2
- 24. SHUTDOwk5 SOMEDULED OVER hEXT 6 MONTHS (TYPE, DATE, AMD DURATION OF EACH):
- 25. IF SHUTDOWN AT END CF REPORT PERIDO, ESTIMATED DATE OF STARTUP: N/A
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY 09/16/73 INITIAL ELECTRICITY 02/18/74 CDMMERCIAL CPERATICN 07/05/74 ACE 2 CF 2 1
l 1
OPERATikG DATA REPORT r,
COCKET ko. 50 273 DATE NOVEMBER 7,1994 COMP'.ETED BY PECO ENE90Y COMPANY W. J. JEFFREY PERFORMANCE AND RELIABILITY SITE ENGINEERING PEACH BOTTOM ATOMIC POWER STAT!CN TELEPHONE (717) 456-7014 EXT. 4027 OPERATING STATUS
- l. UNIT NAME: PEACH BCTTOM UNIT 3 jNOTES:
j
- 2. REPORTING PERIOD:
CCTOBE R, 1994 l
l
- 3. LICENSED THERMAL PDWER(MWT):
3293 l
- 4. NAMEPLATE RAi!NG (CROSS MWE):
1152
- 5. DESIGN ELECTRICAL RATING (WET MWE):
1065
- 6. MAXIMUM DEPENDABLE CAPACITY (CROSS MWE): 1098
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 1035
- 8. IF CHANGES CCCUR IN CAPACITY RATINGS (!TEMS NUMBER 3 THROUGH 7) SINCE LAST REPCRT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE):
- 10. REASONS FOR RESTR;CTICNS, 15 ANN THIS MONTH YR-TO-DATE CUMVLATIVE
- 11. HOURS IN REDCRTING PERIDO 745 7,296 174,072
- 13. REACTCR REEERVE S*UTCCWN HOLR$
0.0 0.0 0.0
- 14. HOURS GENERATCR Ch-LINE 65.0 7,12*.0 108,415.2
- 15. UNIT RESERVE S*UTCOWN HOURS 0.0 0.0 0.0
- 16. GdCSS THEa*A. E=ER;Y LEhERA*EC (" n) 2,108,*98 23,003,922 321,777,399
- 18. kET ELECTRICAL ENERGY GENERATED (MWH) 673,103 7,323,311 101,297,318 PACE 1 CF 2 I
I I
l i
=
CPERATING DATA REPORT (CONTlWUED)
DOCKET NO. 50 - 278 DATE NOVEMBER 7,1994 s
THIS MONTH YR-TO-CATE CUMULATIVE
- 19. UNIT SERVICE FACTOR 87.8 97.6 62.3
- 20. UNIT AVAILABILITY FACICR 87.8 97.6 62.3
- 21. UNIT CAPAC;TY FACTCR (US!kG MDL hET) 87.3 97.0 56.2
- 22. UNIT CAPACITY FACTOR (USING DER NET) 84.8 94.2 54.6
- 23. UNIT FORCED OUTAGE RATE 12.2 2.4 11.7
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (T7PE, DATE, AhD DURATICN OF EACH):
- 25. IF SHUTDOWN AT END OF REPORT PERIDO, ESTIMATED DATE OF STARTUP: 11/14/95
- 26. UNITS IN TEST STATUS (PRIO* TO COMMERCI AL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY 08/07/74 INITIAL ELECTRICITY 09/01/74 COMMERCIAL OPERATION 12/23/74 PAGE 2 CF 2
4 4
UNIT $HUTDOWNS AND POWER REDUCTICNS DOCKET No. 50 - 277 UNIT NAME PEACH BOTTOM UNIT 2 CATE NOVENBER 7,1974 REPCRT MONTH OCTCBER, 1994 COMPLETED BY PECO EhERGY COMPANY W. J. JEFFREY PERFORMANCE AND RELI ABILITY SITE E%GINEERING PEACH BOTTOM ATOMIC POWER STAT!CN TELEPHChE (717) 456-7014 EXT. 4C27 l
l l
l NETH00 0F l *!CENSEE l SYSTEM COMPCNENTj CAUSE AND CORRECTIVE l TYPE l DURATION lREASONjsHUTTINGDOW4; EVE 4T CODE COCE l ACTICN TO NO.
DATE l(1)l(HOURS)l (2) j REACTOR (3) j REPORT #
(4) i (5) l PREVENT RECURRENCE i
i i
i 1
27 941001 S
515.0 C l 1
l RC C0h200 [ REFUELING OUTAGE 2R10 l
l l
f
.I l
l I
t i
i i
I i
I l
l l
l l
l s
e i
i i
i l
l
--- l l
l l
l l
l l 515.0 l l
l l
l l
(1)
(2)
(3)
()
- - FCRCEO REASCN METHOD EXHIB!! 3 - INSTRUCT!CAS S - SCHEDULE 0 A - EQUIP"E%T FAILURE (EXPLA!%)
1 - MAhLA.
FCR PRE;ARATION CF DATA 8 - MAINTEhAhCE CR TEST 2 - MAhLAL SCRAW.
ENTRY S*EITS FCR LICENSEE C - REFUEL!%3 3 - AUT0wA!!C SCRAM.
EVENT REDCRT (LER)
D - REGULATORY RESTR!CTICN 4 - OT*Et (EvDLAIN)
FILE (4URE3-C'61)
E CFERATCR TRAIN!*; + LICEwiE ExA=!4ATION F - ACMINIS* RAT!kE (5)
G - OPERATIO%AL ERROR (EXPLA!4)
H - OTHER(EyPLA!N)
EXHIBIT ! - SAME SOURCE I
I
)
I i
4 l
1 l
i
r P
0 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET No. 50 - 278 UNIT NAME PEACH BOTTOM UNIT 3 DATE NOVEMBER 7,1994 REPORT MChin CCTCBER, 1994 COMPLETED BY PECO ENERGY COMEANY W. J. JEFFREY PERFCRWANCE AND RELIABILITY SITE ENGINEERING PEACH BOTTOM ATOMIC PCWER STA*:CN TELEPHCNE (717) 456-7014 IXT. 4C27 j
j l
l NETH00 0F l LICENSEE l SYSTEM l COMPONENT! CAUSE AND CORRECTIVE j
TYPE lDURATIOklREASCNl SHUTTING DChN j E'.'E NT l CODE j CODE l ACTICN TO NO.j DATE (1)l (HOURS)l (2) lREACTCR(3) l REPCRT # j (4)l (5) l PREVENT RECURRENCE 1
i i
I I
I t
i I
t I
i 18 9410C8 i S 11.0 l H l 4
l l RC CONR00 l ROD PATTERN ADJUSTMENT i
i i
i e
i i
4 1
4 i
i i
i e
i i
19 l 941011 l F 91.C '
A l 3
i 3 94-05 CH GENERA l AUTOMATIC SCRAM / HlGH REACTOR WATER LE'.I. OUE l
l j
l l
j TO FEED PUMP CCNTROL PRC6LEMS CAUSED BY. CSS l
l l
l l
l l CF THE STATIC INVERTER i
e i
i i
i
)
i i
i i
i i
4 l
l l ----
l l
l l
l l
l l
l 102.0 l l
l l
l l
(1)
(2)
(3)
(4)
F-FORCED REASCN METHUD EXHIB:7 3 - IkSTRUCTICNE S - SCHEDULED A - EDUIPwENT FA! LURE (EVDLA:N) 1 - MANUAL FCR FRE*ARATION CF CATA B
MAINTEAANCE CR TEST 2 MANLAL SCRA".
ENTRY E-EETS FCR LICENEEE C - REFUELING 3 - AUTCaATIC ! CRAM.
EVENT REoCRT
(.' ER)
D REOULATCRY REE'R CTION 4 - CT-ER (EXP.A:4)
FILE (NURE3 C*d*)
E CPERATOR 'RA:h:%- - L:CEsEE EXA": SAT:CN F - ACMINISTRATIVE (5)
G - CPERAT:Ch*L ERRCE (ExPLA:4) 9 - DTHER(EA:LA!N)