Denies Request for Exemption from 10CFR50.71(e)(3)(i) Re Delay for FSAR & as Built Drawing Update.Licensee Should Provide Modified Exemption Request Based on Listed Info
ML20149G449
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 06/26/1984
From: Novak T
Office of Nuclear Reactor Regulation
To: Richard J
MISSISSIPPI POWER & LIGHT CO.
References
NUDOCS 9707230234
Download: ML20149G449 (3)


Text

___

A s-P sMA

' j$0k &N f a

um 6, 1984 Docket No. 50-416 PUBUC DOCUMEM5MBUTION:

Docket No. 50-416 Mr. J. B. Richard

'85 W -5 NW8 6%

Local PDR Senior Vice President, Nuclear TIME PE40EQSystem Mississippi Power & Light Company P.O. Box 23054 L F14 r/f EAdensam Jackson, Mississippi 39205 MD'..can GHouston

Dear Mr. Richard:

LWheeler DMJordan, ISE Attorney, OELD ACRS (16)

Subject:

Delay for FSAR and As-Built Drawing Update JNGrace, I&E By letter dated February 6,1984, you requeste' an exemption from 10 CFR d

50.71(e)(3)(1) which requires you to submit an updated FSAR within two years'of receipt of the operating license for Grand Gulf, Unit 1, specifically by June 1984.

You requested a delay in meeting this requirement to 12 months following 1

the issuance of an operating license to Grand Gulf, Unit 2.

1 However, since the completion schedule for Unit 2 has recently been given as 1990 and has a high degree of uncertainty (currently construction halted), we find the proposed schedule for the FSAR update, based upon Unit 2 completion, unacceptable.

As stated in your letter, you have proposed a comprehensive l

annual amendment to the FSAR in June 1985.

We believe that the timing of this submittal would be more appropriate for the FSAR update for Unit 1.

~

Earlier submittal of amendments would be beneficial in view of the discrepancies being found in the current review of the Technical Specifications versus the FSAR.

Changes to the FSAR for specific. details on Unit 2 will be allowed to continue as long as such changes are well identified as applicable to Unit 2 and do not confuse or obscure the information for Unit 1.

For.the same reasons as stated above regarding the extended delay for the FSAR update, we also find the proposed schedule for updating the as-built drawings, based upon Unit 2 completion, unacceptable.

As discussed in NUREG-0696, the TMI accident revealed a need for complete and up-to-date drawings, schematics 1

and diagrams for the as-built plant to be available for emergency situations.

Thus, a delay in updating the as-built drawings until after 1990 cannot be

) $,,

9707230234 840626 DR ADOCK 050 46

+%e i:

li

L

. i tolerated.

We understand your situation where significant changes have been made to the plant but believe this is all the more reason to allocate additional resources to update the drawings rather than to delay the effort.

drawings, which are current to within 6 months of that submittal, should be Revised included in your FSAR update.

of the FSAR and as-built drawings and find your propose effort to be unacceptable.

denied and Therefore, your requested schedule, as written, is discussion.you should provide a modified exemption request based on the above l

your Project Manager, Dean Houston, (301) 492-8358.If you have any q Sincerely, G. ;c:; ^::vi 2f

.licn:;..l.iicr.k Thomas M. Novak, Assistant Director for Licensing Division of Licensing cc:

See next page i

I oNOTE: SEE PREVIOUS WHITE FOR CONCURRENCE LB#4/DL LB#4/DL LB#4/DL OELD AD:L/DL

  • MDuncan
  • DHouston
  • EAdensam:pob *MEWagner TNovak 6/12/84 6/12/84 6/13/84 6/14/84 6/ /84 l

l

GRAND GULF Mr. J. B. Richard Senior Vice President, Nuclear Mississippi Power & Light Company P.O. Box 23054 Jackson, Mississippi 39205 Robert B. McGehee, Esquire cc:

P.O. Box 651 Wise, Carter, Child, Steen and Caraway Jackson, Mississippi 39205 Nicholas S. Reynolds, Esquire Bishop, Liberman, Cook, Purcell

. and Reynolds 1200 17th Street, N.W.

Washington, D. C.

20036 Mr. Ralph T. Lally Manager of Quality Middle South Energy, Inc.

225 Baronne Street P.O. Box 61000 New Orleans, Louisiana 70161 Mr. Larry Dale, Director Nuclear Licensing and Safety P.O. Box 23054 Mississippi Power & Light Company

~~

Jackson, Mississippi 39205 Mr. R. W. Jackson, Project Engineer Grand Gulf Nuclear Station Bechtel Power Corporation Gaithersburg, Maryland 20760 Mr. Alan G. Wagner Senior Resident Inspector

~

Route 2, Box 399 Port Gibson, Mississippi 39150 U.S. Nuclear Regulatory Comission, James P. O'Reilly, Regional Region II Atlanta, Georgia 101 Marietta Street, N.W., Suite 2900 30323

- - -