Forwards Revised Licensing Schedule as Result of Discovery That Incorrect Rev May Have Been Encl W/Util Transmitting Reload Licensing Schedule
ML20149D972
Person / Time
Site: Peach Bottom  
Issue date: 02/05/1988
From: Gallagher J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Butler W
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM), Office of Nuclear Reactor Regulation
References
NUDOCS 8802100135
Download: ML20149D972 (2)


Text

A PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. BOX 8699 PHILADELPHI A. PA,19101 (215) 841 5001 Jou m

  • ,,a y,L^,*H'a February 5, 1988 6...

Docket Nos. 50-277 50-278 Mr. W. R. Butler, Director Project Directorate I-2 Division of Reactor Projects I/II U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

Subject:

Philadelphia Electric Company In-House Reload Licensing

Dear Mr. Butler:

1 By letter dated February 1, 1988 Philadelphia Electric Company transmitted a reload licensing schedule to the NRC.

It was subsequently discovered that the incorrect revision of the schedule may have erroneously been enclosed with the letter.

ife regret this error and any inconvenience it may have caused you.

Enclosed is the correct schedule.

Very truly yours, Attachment cc:

Addressee W. T. Russell, Adminstrator, Region I, NRC T. P. Johnson, NRC Resident Inspector f

h ft

~'

A'*!

i i

>l

REVISED LICENSING SCHEDULE NRC Approva1 of

lPB3C9 Subm ttal PECo Submittal +

i PB3C9 Submittal PB3C9 Reload I

Cycle 9 Design / Licensing Startup L

PECo RSE Methods Report Submittal i

NRC Approvals of all NRC Review of All methods reports Methods Reports J

F M A M J

J A

S O N

D J

F M A M J

J A

S O N

D 1989 1990 1