Amend 99 to License NPF-57,changing TS Section 3.6.5.3.2, Filtration,Recirculation & Ventilation Sys, to Provide Appropriate LCO & Action Statement That Reflects Design Basis for Filtration,Recirculation & Ventilation Sys
ML20149D861
Person / Time
Site: Hope Creek 
Issue date: 07/09/1997
From: Stolz J
Office of Nuclear Reactor Regulation
To:
Public Service Electric & Gas Co, Atlantic City Electric Co
Shared Package
ML20149D865 List:
References
NPF-57-A-099 NUDOCS 9707180021
Download: ML20149D861 (4)


Text

_

O ct%

p UNITED STATES 4

g j

NUCLEAR REGULATORY COMMISSION t

WASHINGTON D,0. 20665-0001 h.....,$

1 i

PysllC SERVICE ELECTRIC & GAS COMPANY l

ATLANTIC CITY ELECTRIC COMPANY l

DOCKET NO. 50-354 j

HOPE CREEK GENERATING STATION AMENDMENT TO FACILITY OPERATING LICENSE Amendmer.t No. 99 i

License No. NPF-57

)

1.

The Nuclear Regulatory Commission (the Commission or the NRC) has found that:

A.

The application for amendment filed by the Public Service Electric

& Gas Company (PSE&G) dated March 31, 1997, complies with the 4

standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance:

(1) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-57 is hereby amended to read as follows:

9707180021 970709 PDR ADOCK 05000354 P

PDR

l 2-(2) Technical Soecifications and Environmental Protection Plan 4

The Technical Specifications contained in Appendix A, as revised through Amendment No. 99, and the Environmental Protection Plan i

contained in Appendix B, are hereby incorporated into the license.

PSE&G shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3.

The. license amendment is effective as of its date of issuance and to be implemented within 60 days of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION At 4 + [+

s 7

- y JohnF.Stolz,birector Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation i

Attachment:

Changes to the Technical Specifications Date of Issuance: July 9, 1997

j i

ATTACHMENT TO LICENSE AMENDMENT NO. 99 FACILITY OPERATING LICENSE NO. NPF-57 l

DOCKET NO. 50-354 4

j Replace the following pages of the Appendix "A" Technical Specifications with the attached pages. The revised pages are identified by Amendment number and contain vertical lines indicating the area of change.

Remove Insert 3/4 6-52a 3/4 6-52a j

l

CONTAINMENT SYSTEMS 3.6.5.3 FILTRATION, RECIRCULATION AND VENTILATION SYSTEM (FRVS)

FRVS RECIRCULATION SUBSYSTEM LIMITING CONDITION FOR OPERATION

-3.6.5.3.2 Six FRVS recirculation units shall be OPERABLE.

APPLICABILITY: OPERATIONAL CONDITIONS 1, 2,

3 and *.

ACIlQE8 With one or two of the above required FRVS recirculation units a.

inoperable, restore all the inoperable unit (s) to OPERABLE status within 7 days, or:

1.

In OPERATIONAL CONDITION 1, 2, or 3, be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

2.

In Operational Condition *, suspend handling of irradiated fuel in the secondary containment, CORE ALTERATIONS and operations with a potential for draining the reactor vessel.

The provisions of Specification 3.0.3 are not applicable.

b.

With three or more of the above required FRVS recirculation units inoperable in Operational Condition *, suspend handling of irradiated fuel in the secondary containment, CORE ALTERATIONS or operations with a potential for draining the reactor vessel. The provisions of Specification 3.0.3 are not applicable.

c.

With three or more of the above required FRVS recirculation units inoperable in OPERATIONAL CONDITION 1, 2, or 3, be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

SURVEILLANCE REQUIREMENTS 4.6.5.3.2 Each of the six FRVS recirculation units shall be demonstrated OPERABLE:

a.

At least once per 14 days by verifying that the water seal bucket traps have a water. seal and making up any evaporative losses by filling the traps to the overflow, b.

At least once per 31 days by initiating, from the control room, flow through the HEPA filters and charcoal adsorbers and verifying that the subsystem operates for at least 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> with the heaters on in order to reduce the buildup of moisture on the carbon adsorbers and HEPA filters.

HOPE CREEK 3/4 6-52a Amendment No. 99