_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _,
4 s
GPU Nuclear Corporation a Nuclear
- s
- , o,e,,
201-316 7000 TELEX 136-482 Wnter's Direct Dial Number:
C311 2034 April 5, 1988 U.S. Nuclear Regulatory Comission Attn: Document Control Desk Washington, D.C.
20555 Gentlemen:
Three Mile Island Nuclear Station, Unit 1 Operating License No. DDR-50 Docket No. 50-289 Response to SALP Report 86-98 On February 11, 1988, tne NRC issued the Systematic Assessment of Licensee Performance (SALP) report for Three Mile Island Unit 1.
A meeting to discuss this report was held in the GPUN corporate offices on March 3,1988.
The attachment to this letter provides the GPUN written coments on the SA'.P report.
As indicated in the March 3,1988 meeting, we are addressing the areas ider.tified in the SALP as needing improvement.
We appectate the opportunity to review with you the SALP report and provide our comments. We continue to believe that this dialogue is the most meaningful portion of the SALP process.
Si ncerely, P. R. Clark President HDH/DVH/feg :
cc:
W. Russell R. Hernan R. Conte Attachment 8804120356 080405 PDrt ADOCK 05000209 0
PDR 6618f/0167f GPU N aclear Corporat.on is a subs >dary cf General Pubic Utites Corpora!on
s ATTACMENT 1 RESPONSE TO SALP REPORT 86-99 A.
Plant Operations In general, we are pleased that the NRC noticed and acknowledged improvements made in Operations. We consider we had a good, safe operational period and that the record supports this.
Our goal is to continue to improve and strive for excellance.
Specifically we offer the following comments:
1.
Personnel Errors - Procedural Compliance We recognize that closer attention to procedural compliance is requi red.
Guidance in this area will be reinforced to all levels of supervision.
In addition action will be taken to strengthen the procedure preparation and review process especially in the maintenance area.
2.
Schedular Pressure - Haste - Pace of Activities Much attention has been directed, particularly since April 1987, to the need for proper planning and a safe conservative approach to all evolutions.
We consider that we have been successful in getting this message to our people, as demonstrated during the letdown cooler replacement and the recent 3 day stator cleaning outages. These outdges ' vere controlled and conducted in a safe, well planned, and coordinated manner.
We intend to continue to apply the principles used in these short outages and the lessons learned from them.
3.
Self Evaluation of Less Significant Problems We acknowledge that more attention to and evaluation of day-to-day unusual events in the plant are needed.
We use the formal Plant Incident Report (PIR) for a thorough evaluation of the more significant events.
This is the proper use of the PIR system.
However, we understand and agree events of lesser significance need more visibility at all levels of management so that lessons learned can be comunicated and that unfavorable trends can be identifled and appropriate action taken. We are currently working to detennine the best way to implement such a program with minimal adninistrative impact.
We expect to have a program in place by July 1,1988.
6618f/0167f _
s a
B.
Radiological Controls We are in general agreement with the analysis as presented.
The facts as we know them regarding the letdown filter cubicle (page 17, first full paragraph, and page 18, last sentence) do not indicate management inattentiveness. This is a complex job and we have properly perfonned seventeen filter changes subsequent to the incident demonstrating that sufficient attention has been provided to resolve the problems.
C.
Maintenance We are pleased that the NRC views the Maintenance Department as a positive influence on overall plant perfomance.
The recently established Materiel Department, we believe, will provide us with even better long term plant reliability which will enhance safety. We offer the following specific comments:
1.
Final Closeout of Job Tickets We acknowledge that in some cases there has been excessive J91ay in closing out job tickets.
Steps have already been taken to correct this area.
2.
Vendor Comunications/Inte-face Problems with the Major Emergency Iflesel Generator Maintenance '
i We consider this to be an isolated incident that was probably exacerbated by schedular pressures. We clearly understand our responsibilities for control of contractor work and verification of accuracy of infonnation supplied by contractors.
This will be emphasized to all on site managers prior to the 7R outage-D.
Surveillance Testing No coment.
l E.
Fire Protection The Fire Protection area is one which has had a great deal of attention over the past years.
There was a large amount of work done in support of Appendix R requirements. While we acknowledge specific deficiencies, we do not agree with the suggestion that there is a similarity in problems I
with the Environmental Qualification (EQ) area.
The prob 1 cms noted in the SALP were more isolated and in our view should not bc compared with the EQ area.
6618f/0167f F.
Emergency Preparedness We have taken action to correct the items cited. We have a Tech. Support Center (TSC) calculation handbook being developed and selected members of the TSC staff will visit other utilities' facilities to observe good practices that could benefit our TSC.
We now have two primary methods to activate the Parsippany Technical Functions Center as well as a backup method which should eliminate any delay in having that center activated, 1
although it should be noted that the activation times in the plan have always been achieved.
G.
Security and Safeauards No c Mment.
H.
Outages We believe our outages during the last year; 6R, letdown Cooler and Stator Cooling, were well planned and conducted properly. The 7R outage has better planning and preparations are more extensive which should result in an even better outage.
Our test program is an integral part of our modification process.
At times this test program will uncover problem areas.
However, we will continue to emphasize to our people the importance of proper reviews of modifications to find and resolve potential problems prior to installation and testing.
Outage work packages have previously remained open too long.
Emphasis is being placed on close out of Maintenance job tickets and a new modification package process has been developed to assure a more timely close out of modification packages consistent with the completion of the i
outage.
I.
Licensing Activities We have three detailed coments to the SALP in this area:
1.
Although the methods to meet Appendix R requirements are still being reviewed, GPUN considers that we have satisfied the Appendix R requi rements, 2.
The time NRC had to approve the pressure-temperature amendment i
appears inaccurate.
GPUN submitted the request July 24, 1987 and the amendment wet issued November 18, 1987.
This is 17 weeks as compared to the stated 10-11 weeks (2-1/2 months).
Perhaps there is a problem j
with the receipt of mail.
GPUN will follow-up on critical license submittals to assure they have been received.
I 6618f/0167 f A
3.
On the Chlorine Technical Specifications, GPUN has never comitted to meeting Reg. Guide 1.95 requirements.
Therefore, our submittal would not have provided the justification looked for by the NRC.
J.
Engineering Support Consistent with the previouc SALP, we have been perfoming a self assessment of the engineering support area.
Phase I consisted of a f
structured survey of the engineering staff and the "user community." The sumary of results is completed and the final phase, including conclusions and action plan is to be complete by May. We look forward to reviewing the results of this assessment with your staff.
We are addressing the NRC coments in five areas (1) Engineering Staff Accountability; (2) Vendor Control (both suppliers of engineered equipment and Architect / Engineers); (3) Schedule Insensitivity related to backlog, NRC issues, and modification engineering; (4) Comunications between design organizations with other functional groups, and (5)
Technical Reviews.
We have been working to improve these areas by the following actions:
(actions already implemented)
Modi fications Implemented program changes to:
Stop splitting design responsibility between Architect Engineers / Contractors on individual modifications.
Move to use only one A/E per plant for design work not perfomed by GPUN.
Enhanced design reviews with stronger and earlier operations /
maintenance input.
Enforce Plant walkdowns by design organization.
Establish schedules to ensure earlier release (target of 6 months) i prior to an outage.
Continually implement corrective actions based upon analysis of quality trends.
Backlog Focus resources to further reduce engineering action items.
6618f/0167 f Configuration Control
- Design Document Data Base (CARIRS) improved to further address user issues.
- Vendor Manuals - Essential manuals have been reviewed and controlled.
- Completed Equipment Level Quality Classification List and Engineering Data Base. Approximately 25,000 components have been entered into the Engineering Data Base.
Owners Group Increase focus on Owners Group and taking leadership role in them.
Management will continue to emphasize the need for thorough and timely responses to technical issues by including:
1.
Prompt implementation of action plans developed as a result of the self assessment.
2.
Emphasizing the need for Operations and Maintenance input on plant modifications by adherence to procedural requirement for design revi ews, 3.
Strengthen technical and safety reviewer training.
4.
Continue the focus on timely reduction of backlog.
5.
Extend the sound technical support provided by the Startup and Test organization to shop testing of engineered vendor hardware.
We do have some specific coments regarding specific issues identified in the SALP report.
The last paragraph on page 40 stites in parts:
l "These deficiencies led to licensee having to perfom additional testing of quality materials as a result of an NRC evaluation l
perfomed during the period."
GPUN is unaware of the instance (s) cited.
There were no instances l
where GPUN perfomed additional testing.
There was one instance l
where GPUN had to perfom further evaluation of a part in a component. We assume this is the instance being cited in the THI-1 SALP.
6618f/0167f i
r The first paragraph on page 40 of the SALP makes reference to the reactor water level design having problems.
THI-1 was required to complete NUREG 0737 item II.F.2 prior to restart from Outage 6R.
During an October 2,1986 meeting, the NRC 1
identified disagreement with the GPUN approach in that RCITS water 1evel input signals to the plant computer enter a single multiplexer and are displayed through two computers.
The NRC disagreed with this j
configuration on the basis that it did not satisfy the single failure criterion.
GPUN maintained that this configuration meets the i
requirements of NUREG 0737 item II.F.2 and that RCITS does not constitute accident monitoring instrumentation, and therefore, the single failure criterion does not apply. GPUN continues to believe the design as described is adequate.
To date the NRC has not documented a finding that the RCITS design as installed is unacceptable.
In addition, GPUN does not believe that a correlation exists between the design of the reactor coolant inventory trending system and perceived difficulties with the safety review process.
K.
Training and Qualification Effectiveness In response to the NRC recomendation for the licensed operator requalification examinations, a requirement has been established, as documented in the licensed operator requalification training program description, that examinations should emphasize the operational application of theoretical concepts and the application of facility administrative limits, Technical Specifications, etc., rather than memorized lists of numbers and facts.
Further, steps are being taken to upgrade learning objectives and test items.
L.
Assurance of Quality l
We are in general agreement with the analysis portrayed although we l
believe the management attitude problem portrayed is an isolated one and i
one in which the company is actively working to resolve. W3 do not believe this problem is manifested in the upper levels of site management.
The safety review program is an area where dialogue has been continuing with the NRC.
At this time we do not offer any coments other than this area has had and will continue to have a great amount of management i
l attention.