ML20148B877

From kanterella
Jump to navigation Jump to search
Insp Rept 50-113/88-01 on 880125-26.Violations Noted.Major Areas Inspected:Reactor Operations Program,Radiation Protection Program,Emergency Preparedness Program & Radioactive Matl Shipment & Receipt Program
ML20148B877
Person / Time
Site: 05000113
Issue date: 03/03/1988
From: Cillis M, Yuhas G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20148B863 List:
References
50-113-88-01, 50-113-88-1, GL-86-11, IEIN-87-022, IEIN-87-22, NUDOCS 8803220177
Download: ML20148B877 (10)


See also: IR 05000113/1988001

Text

s.

"

S

'

<p;

,,

,;

-y

s

.

"

..
-

.

,

  • _.f:

-

'

'+

,

~

'

,

,

. . , .

.

U.S. NUCLEAR. REGULATORY COMMISSION

.

REGION V-

.

Report'No.

50-113/88-01

-Docket No.

50-113

' License No.

R-52

Licensee:

University of Arizona

LCollege of Engineering

Tucson, Arizona 85721

Facility Name: University of Arizona Research Reactor, TRIGA Hark I

Inspection at: Tucson, Arizona

Inspection Conducted: January 25-26, 1988

Inspector:

[d

d,NY

L!bf!88 -

M. Cillis, Senior Radiation Specialist

Date Signed

Approved by:

M , A//[ b-

7//f '

3

G. P. Yuhas Chief

Date Signed

Facilities'Radiolo cal Protection Section

Summary:

Inspection on January 25-26, 1988 (Report No. 50-113/88-01)

Areas Inspected:

Routine unannounced inspection by a regionally based

inspector of reactor operations program,- radiation protection program,

emergency preparedness program, radioactive material shipment and receipt

program, followup items, and a tour of.the facility.

Inspection procedures

30703, 39745, 40745, 41745, 42745, 61745, 69745,'82745, 83743, 86740, 92701,

and 92702 were addressed.

i-

Results:

Of the six areas inspected, two violations were identified.

Failure

4

to include all required topic areas in the reactor operator / senior reactor

'

operator annual written examination (see paragraph 2.F) and failure to follow

and maintain the Emergency Plan in effect (see paragraph 4).

The licensee's

performance in remaining areas that were examined appeared to be consistent

with the regulatory requirements.

.

1

8803220177 880303

~

PDR

ADOCK 05000113

O

DCD

'

, _

,_ _ _

.

_ _ . _ . ~ .._ ..

_ , _ . _ , . . _ . _ . .

.

.

.

.

. . . -

.

..

'

f

DETAILS

1.

Fersons Contacted

  • E. T. Smerdon, Dean, College of Engineering and Mines
  • T. Triffet, Associate Dean of Engineering and Research
  • G. W. Nelson, Director, Nuclear Reactor

R. L. Seale, Head, Department of Nuclear and Energy Engineering

  • B. Westerman, Director, Radiation Control Office
  • B. O. Ganapol, Reactor Committee Chairman
  • H. J. Duane, Reactor Supervisor
  • C. Irwin, Radiation Safety Officer

M. C. Young, Assistant Director, Radiation Control Office

B. B. Piner, Chief, Radiation Control Officer

  • Denotes those individuals attending the exit interview on January 29,

1988.

2.

Reactor Operations

A.

General

The inspection disclosed that reactor operations were consistent

with the information provided in the licensee's 1986 and 1987 annual

reports.

The inspection disclosed that the facility continues to provide

support for irradiations and teaching programs.

The inspector witnessed reactor operations that were performed

during the inspection.

No violations or deviations were identified.

B.

Organization

The organizational structure for operation and administration of the

TRIGA Reactor facility remains unchanged from that previously

reported.

The organization was found to be consistent with Section

6.1 of the Technical Specifications (TSs).

No violations or deviations were identified.

C.

Experiments

The licensee's experiment program has not changed since the previous

inspection.

Experiments performed have consisted of activation

analysis in support of various research projects and classroom

laboratory work,

No new experiments had been performed since the

previous inspection.

~

-

-

-

[

'

2

.

No violations or deviations were identified.

D.

Changes

Discussions with the Reactor Supervisor and a review of reactor

operating records for the period January 1986 to the present date

disclosed that no changes were made to the facility or procedures

that would require a safety evaluation pursuant to 10 CFR Part 50.59.

No violations or deviations were identified.

E.

Procedures

,

The inspection disclosed that the licensee maintains in effect

reactor operating procedures es prescribed in TSs, Section 6.3.

The inspector reviewed the licensee's standard operating procedures.

The procedures appeared to provide thorough instructions.

The

inspector noted that the procedures are reviewed on a routine

schedule and whenever changes occur that may require revisions.

No violations or deviations were identified.

F.

Reactor Operator Requalification Program

The implementation of the licensee's approved Reactor Operator (RO)

and Senior Reactor Operator (SRO) requalification program, dated

August 29, 1974, was examined.

Applicable training lesson plans,

quizzes, and annual examinations administered in 1986 and 1987 were

reviewed.

Additionally, discussions related to Information Notice (IN) 87-22, "Operator Licensing Requalification Examination at

Nonpower Reactors," and the recent changes made to 10 CFR Part 55

were held with the licensee's staff.

The inspector also verified

through the review of applicable logs and records that the R0/SRO

requalification program was in compliance with Section 3 of the

approved requalification program.

Section 3 requires each operator

to perform at least ten reactivity control manipulations over the

two year term of his license, at least one reactor checkout, and one

startup per quarter.

The examination disclosed that the licensee had received a copy of

the recent changes made to 10 CFR Part 55 and IN 87-22.

The

Director of the Nuclear Reactor informed the inspector that an

evaluation of the IN had been completed.

He added that actions

have been taken to ensure that the problems identified in the IN is

-

considered during the administration of future R0/SRO annual

examinations.

The licensee was still in the process of evaluating

the recent changes to 10 CFR Part 55 for applicable to activities

performed at the NRL.

The examination disclosed that the 1967 annual examination did not

include an examination in the topic area of "Normal, Abnormal, and

Emergency Operating Procedures" as required by Section 2 of the

.

-

--

- -

-

.

.

-.

.

.

-

_,

.

..

.

i

3-

,_

approved R0/SRO approved requalification program.

The reactor

supervisor was'not-aware that the topic area had not been included

in the examination.

He said it was probably due to an oversight on

his part.

The above observations were brought to the licensee's attention

during the exit interview.

The inspector informed the licensee that

failure to include the topic area of. Normal, Abnormal, and Emergency

i

Operating Procedures in the 1987 annual R0/SR0 annual examination

,

was an apparent violation (88-01-01).

The licensee. acknowledged the inspector's observation.

i

G.

Review and Audit

The inspector verified that the licensee's review and audit program

was consistent with Section 6.2 of the TS.

Reactor Operations

Committee (ROC) meeting minutes for the period of January 1986

through January 1988 were reviewed.

The chairman of the ROC met

with the inspector to discuss methods for improving the

effectiveness of ROC review and audit functions.

The inspection

findings were brought to the attention of the ROC chairman.

No violations or deviations were identified.

H.

Surveillance Program

The inspector verified through the review of 1986 and 1987 reactor

l

operating records, checklists, and logs that the licensee's

.

surveillance program had been in compliance with Sections, 2, 3, and

4 of the TS.

The review dis osed that the surveillances were

performed in accordance wi^h the licensee's Standard Operating

Procedures (SOP) at a frequency that met or exceeded TS

'

requirements,

j

No violations or deviations were identified.

!

3.

Radiation Protection Program

<

A.

Liquid and Solid Waste

A review of records maintained by the licensee's radiation control

office and at the reactor facility disclosed that no liquid or solid

radioactive waste had been generated since the previous inspection.

,

No violations or deviations were identified.

B.

Posting

The inspector verified that the licensee's posting practices were in

compliance with 10 CFR Part 19.11, Posting of Notices to Workers,.

I

No violations or deviations were identified.

J

i

>

,

e,-

- -. - - ,

..-,a

n

-..,_n-n,,.._,

,m

...c--.~,.-..---,__,n,,

,,,,,..--,..n..

w-.-mv_,,,,-.- - , -

-,---,.m

.-

.

'

.

C.

Personnel Monitoring

The licensee's program for assuring compliance with 10 CFR Part 20.202,-"Personnel Monitoring," was examined and was found to be

acceptable.

Personnel monitoring records for the period of December

1985 through November 1987 were reviewed.

No abnormal exposures

were identified.

No violations or deviations were identified.

D.

General Employee Training (GET)

The licensee's GET program for assuring compliance with 10 CFR Part 19.12, "Instructions to Workers," was examined.

Training lesson

plans, examinations, and attendance records were reviewed.

The

inspector concluded that the GET program was consistent with 10 CFR Part 19.12.

No violations or deviations were identified.

E.

Surveys

The licensee's program for assuring compliance with 10 CFR Part 20.201, "Surveys," and 10 CFR Part 20.401, "Records of Surveys," wcs

examined.

Survey records for the period of January 1986 through January 1988

were reviewed.

The following observations were made:

(1) Monthly radiation and wipe measurements (surveys) are conducted

at the reactor facility by the campus radiation control office

staff.

Radiation measurements are normally obtained when the

reactor is shut down.

A radiation measurement had not been

performed while the reactor was at full power since the summer

of 1984.

This observation was brought to the licensee's

attention during the inspection and at the exit interview.

The

licensee informed the inspector that provisions will be

established to perform radiation measurements while the reactor

is at power on a quarterly basis.

The inspector noted that the results of survey data reviewed

were consistent with the levels reported in the licensee's

annual reports.

No abnormal results were identified.

(2) A review of reactor operating records disclosed that irradiated

samples transferred to other campus facilities are not normally

checked for contamination.

This obsurvation was brought to the

attention of the licensee's staff during the inspection.

The

inspector was informed, that future samples will be checked for

contamination prior to transfer from the reactor facility.

(3) A review of radiation measurements made on contact with the

reactors water purification system disclosed that surveys of

the unit, which is located immediately outside the reactor's

-

_ _ - - _ _ _ - - . _.

'

.

. .

'5

.

,

.

north wall, are only performed once each month.

The system is

housed in a locked wire-mesh cage which measures approximately

3' square by 5' high.

The-system had never been posted or

controlled as a radiation area during the history of. reactor

operations at the"licensee's facility.

It was noted that the monthly survey did not necessarily

reflect the worst case condition; for example:

a.

Performing measurements immediately after reactor

shutdown, and-

b.

Performing measurements after operating the reactor at

full . power for one day or longer.

The inspector noted that on one occasion, (1984) radiation

levels of 20 mrem /hr were measured on contact with the

demineralizer housing and 4 mrem /hr at one foot from the unit.

The review further indicated that the reactor was seldom

operated at maximum power or for more than three hours per day

and, as a result, radiation measurements on contact with the

water purification system for the past two years had not

exceeded 2 mrem /hr.

However, it should be noted that the

surveys were performed anywhere from several days and/or longer

periods after the reactor had been shut down.

Therefore, any

short-lived radioactivity would have decayed before the

measurement was taken.

The inspector made a measurement of the system within 10

minutes of reactor operation at 1 Kw on January 26, 1988.

Radiation measurements on the outer surface of the wire mesh

cage were less than 0.2 mrem /hr.

The inspector brought the above observations to the licensee's

attention during the inspection and at the exit interview.

The

licensee's staff concluded that no violations of the regulatory

,

requirements had occurred based on the facilities power history

'

over the past several years.

The inspector concurred with the

licensee's conclusions.

This item will be examined during a

subsequent inspection (88-01-03).

The licensee informed the

inspector that an evaluation of the above observations would be

performed to verify compliance with 10 CFR Part 20

requirements.

F.

Particulate and Gaseous Effluent Releases

Annual releases of Argon-41 are determined by calculation.

The

calculations consider the production of Argon-41 during reactor

operations.

A constant air monitor (CAM) is used to measure

i

concentrations of particulate radioactivity pursuant to Section 4.3

of the TS,

/ rgon-41 releases for the period of July 1986 through June 1987 were

determined to be 3.67 millicuries.

This value is less than 0.6% of

4

. -

- -

- -

-

- -

-

-

-

-

-

- - -

-

-

-

- -

-

-

- -

-

- - -

.

- - -

-

'

-

I

f

4*'

'6

-

,

.

.

.

the allowable Argon-41 releases per 10 CFR Part 20, Appendix B.

Particulate airborne concentration levels for this same-period were

essentially non-detectable.

~

The inspector also verified that the CAM alarm setpoint-and

calibration were accomplished in accordance with TS Section 4.4.

No violations or deviations were identified.

G.

Environmental Monitoring Program

The licensee has established an environmental monitoring program

which includes the analysis of water and soil samples that are

obtained at various locations on the University of Arizona campus.

Dose measurements are also performed using an array of CaSO : Dy

4

Thermoluminescent Dosimeters (TL0s).

Records of water, soil, and TLD measurements were reviewed and were

found to support the licensee's conclusion that there has been no

detectable or abnormal increases of radioactivity in the environment

as a result of reactor operations.

No violations or deviations were identified.

4.

Emergency Plan Implementation

The licensee's capability for responding to emergencies as specified in

their NRC approved Emergency Plan of December 12, 1983, and for

, demonstrating compliance with 10 CFR Part 50.54(q) and 10 CFR Part 50,

Appendix E, were examined.

The examination included a review of licensee's records, emergency plan

implementing procedures (EPIP), emergency response equipment, drill

scenarios and critiques, and discussions with the licensee's staff.

10 CFR Part 50.54(q) requires each licensee who is authorized to possess

and/or operate a research reactor to follow and to maintain in effect

emergency plans (EP) which meet the requirements of Appendix E to 10 CFR Part 50.

Paragraph IV.F of Appendix E requires that emergency plans

include provisions for training of personnel and exercising by periodic

drills to ensure personnel are familiar with their duties. Appendix E

further states that the program should identify specialized initial

training and periodic retraining programs.

Paragraph IV.G of Appendix E

also requires that the program describe the provisions to be employed to

ensure the EP, emergency equipment, and the EPIPs are maintained

up-to-date.

Paragraph 10.4 of the licensee's approved EP states, in part:

"Applicable portions of the plan, agreements, and implementing procedures

shall be distributed to the University Police, Radiation Control Office

and the Arizona Radiation Regulatory Agency.. . . ."

Discussions with the licensee's staff disclosed that the Radiation

Control Office did not have a copy of the EP or the EP implementing

.-

.

7

.

..

procedures.

A copy of the reactor's EP was made from the inspector's

copy of the licensee's EP by the Radiation Control Office staff during

the inspection.

Only one of six members from the Radiation Control

Office was generally aware of the instructions provided in the reactor's

emergency plan.

Several members of the Radiation Control Office had not

read the plan since 1985.

The Radiation Control Office staff were not

aware of requirements prescribed in paragraph 10.5.2 of the EP which

states, in part:

"Pnrtable health physics instruments used in the NRL

and those in the emer gency kit are checked for operability quarterly and

calibrated by the staff of the Radiation Control Office semiannually."

Procedures from the Radiation Control Office require portable instruments

be calibrated annually and require that channel checks be performed

semiannually.

Section 3.1.2 of the EP states that the reactor supervisor is responsible

for training and conducting emergency tests and drills for the operating

staff of the NRL in conjunction with the Radiation Control Office.

Section 10.1 of the EP states, in part:

"NRL operators and staff, and

members of the Radiation Control Office with emergency response

responsibilities will complete an initial training program and an annual

review program... Specific training in protective action decisionmaking

will be included in the initial and periodic training for those

individuals who may serve as Emergency Director during an emergency.

Support groups will receive training commensurate with their degree of

pctential involvement."

No records of any training were maintained except for training provided

to operators; however, the training records for operators did not include

any specific instructions related to protective action decisionmaking

responsibilities for the Emergency Director or his alternates.

Discussions with the Reactor Supervisor and Radiation Control Office

staff revealed that the initial training had not been provided and an

annual review program had not been established and maintained.

Several

members from the Radiation Control Office informed the inspector that

they had not read the EP, had not received any specific training related

to the NRL approved EP plan and had not participated in exercises or

drills associated with a simulated NRL e:nergency.

The staff stated that

they had not been directed to review the plan.

The Director of the

Radiation Control Office stated that his staff had been trained to

respond to the University of Arizona campus EP.

The inspector noted that

the site-wide plan was quite different from the NRL approved EP.

The

reactor supervisor stated that he had not developed any specialized

training program for the Radiation Control Office staff.

Discussions witi, the NRL staff disclosed that a video tape had been

prepared so that the campus security group could train their staff.

The

examination disclosed the NRL staff had not verified whether the campus

security department was utilizing the video tape recording to train their

staff.

The examination disclosed that the annual exercises prescribed in EP

,

Section 10.2 were conducted in 1986 and 1987.

The reactor supervisor

- -

- -

-

-

-

-

-

-

-

.

.

..

8

.

.

.

stated that involved personnel were provided with some training in

preparation for conducting the drills.

Section 10.4 of the EP requires that the EP be reviewed annually by the

Reactor Committee (RC) to ensure that the plan is adequate and

up-to-date.

Section 3.1.2 also assigns the reactor supervisor the

responsibility for reviewing and updating the EP and procedures.

The inspector noted that the only review of the EP is performed by the

reactor supervisor.

The results of the reactor supervisor's review are

then presented to the Reactor Operations Committee for approval.

An

independent review of the EP is not performed by the RC.

The inspector summarized the above findings with the licensee's staff

attending the exit interview.

The inspector informed the licensee that

failure to distribute the EP to the Radiation Control Office, failure to

complete the initial training and annual review program, and failure to

perform quarterly calibrations of the inst ruments semiannually was an

apparent violation (88-01-02).

The licensee staff attending the exit interview acknowledged the

inspector's observations.

The inspector was informed that appropriate

actions would be established and implemented to resolve the observations.

5.

Radioactive Material Shipment and Receipt

A review of radioactive material shipping and receiving records revealed

that activities associated with the transportation and receipt of

radioactive material were consistent with 10 CFR Part 20, 10 CFR Part 61,

i

10 CFR Part 71, and Department of Transportation (00T) 49 CFR Parts

173-178.

Shipments of radioactive material are made through the licensee's State

of Arizona radioactive material license.

No violatiens or deviations were ideatified.

6.

Facility Tour

The inspector toured the licensee's facility to check the general state

of housekeeping and to verify that posting and labeling were in

compliance with 10 CFR Part 20.203 and that radiation monitoring

instrumentation was in current calibration and was operating properly.

Independent radiation measurements were parformed using an NRC Eberline

Model E-520 Geiger Counter, Ser ial Number 1086, that was due for

calibration on February 11, 1988.

All fixed and portable radiation monitoring instruments were in current

calibration and the facility cleanliness was excellent.

No violations or deviations were identified.

L

,

-i _

J.-

'

9

'

.

3

.

P

7.

Followup Items

Information Notices (ins) and Generic Letters (GLs)

The inspector verified'that the licensee's staff were receiving and

evaluating ins and GLs for. applicability to activities performed at the

research reactor.

~

A licensee evaluation of GL 86-11, "Distribution of Products Irradiated

in Research Reactors," revealed that the licensee does not plan to

irradiate any gemstones for commercial use.

Reactor Director stated that

the NRC would be informed of any future decisions to irradiate gemstones

for commercial and/or private use.

No violations or deviations were identified.

8.

Exit Interview

The inspector met with the_ individuals (denoted in paragraph 1) at the

i

conclusion of the inspection on January 26, 1988.

The scope and findings

i

of the inspection were summarized.

The licensee was informed of the

apparent violations identified in paragraphs 2.(f) and 4.

,

The violations and other observations discussed in the inspection report

were acknowledged by the licensee at the exit interview.

>

l

b

,

F

-

.

>

t

h

&-.--

- - - - , - - . , , - - , - - , - - , . . - . , , . _ , , - - . - - , . , ,- ,. ,, ,-

-,,-, - ,~,-