Supplemental Deficiency Rept CP-86-73 Re Installation of ASME Snubber Attachment Brackets.Initially Reported on 870320.Completion of Unit 1 Supports Rescheduled for 880501 & Unit 2 Supports Will Be Completed Prior to Fuel Load
ML20148B736
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/15/1988
From: Counsil W, Woodlan D
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-86-73, TXX-88323, NUDOCS 8803220100
Download: ML20148B736 (1)


Text

.-.

- -- usam.

EE Lo

  1. TXX-88323 L

=

Fi e # 10110

=

=

903.9

"' # '* " " * ('b TUELECTRIC March 15, 1988 wnu.. c.co.mu Execme Vke President

'U S. Nuclear Regulatory Commission Attn:

Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 ASME SNUBBER ATTACHMENT BRACKETS SDAR: CP-86-73 (SUPPLEMENTALREPORT)

Gentlemen:

By letter logged TXX-6315, dated March 20, 1987, we notified you of a deficiency involving the installation of ASME snubber attachment brackets, which we determined to be reportable under the provisions of 10CFR50.55(e).

In our last report, logged TXX-88149 (January 26,1988), we' stated that the remaining supports requiring rework would be completed by March 15, 1988.

Due to scheduling constraints we will not be able to meet this date.

We have rescheduled the completion of Unit 1 supports for May 1,1988.

Unit 2 supports will be completed prior to Unit 2 fuel load.

Supporting documentation for Unit I will be available onsite for your Inspector's review after May 1, 1988.

Very truly yours, (M. (p. M W. G. Counsil By:

E R. Woodlan Docket Licensing Manager BSD/grr c-Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) 8803220100 880315 PDR ADOCK 05000445 S