TENNESSEE VALLEY AUTHORITY CH ATTANOOG A. TENNESSEE 374o1 5N 157B Lookout Place i
JAN 211988 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C.
20555 Gentlemen:
In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 SEQUOYAH NUCLEAR PLANT (SQN) - REVISED COMMITMENT REGARDING HEAT TRACE PROCEDURE CHANGE In a letter dated November 10. 1987, responding to NRC Report Mos. 50-327/87-52
=
and 50-328/87-52 TVA committed to revise Sequoya; Itandard Practice SQN-2 to proceduralize the requirements for working essential raw cooling water pumping station heat trace by December 15, 1987. Additional time was required to complete this revision, and an extension was made to NRC by telephone on December 15, 1987.
A procedure revision to SQM-2 was issued on December 22, 1987 meeting the requirements of this commitment.
Very truly yours.
TENNESSEE EY AUTHORITY
'/
R. Gridley, D ector Nuclear Licen ing and Regulatory Affairs
(
I cc: See page i i
P An Equal Opportunity Employer
.1 r.
. U.S. Nuclear Regulatory Commission as N 211988 cc:
Mr. K. P. Barr, Acting Assistant Director for Inspection Programs TVA Projects Division Office of Special Projects U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Mr. G. G. Zech, Assistant Director for Projects Mail Stop 7E23 TVA Projects Division Office of Special Projects U.S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20814 Sequoyah Resident Inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road Soddy Daisy Tennessee 37379