e APPENDIX A NOTICE OF DEVIATION Arkansas Power & Light Company Dockets: 50-313 Arkansas Nuclear One 50-368 Operating Licenses: DPR-51 NPF-6 Based on the results of an NRC inspection conducted December 1,1987, through January -19,1988, a deviation of your comitments made to the NRC was identified. The deviation consisted of the failure to issue supplements to licensee event reports (LERs).
In accordance with the "General Statement of Polic and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1988, the deviation is listed below:
When LERs 85-001-00 and 86-001-00 for Unit 1 and 84-022-00, 85-002-00, 85-007-00, 86-012-00, and 86-014-00 for Unit 2 were issued by the licensee, the licensee stated in each listed LER that supplemental reports would be issued to provide the NRC with updated information on the event addressed by the LER.
In deviation from the above, the licensee failed to provide supplemental reports to the NRC.
(313/87-39-01,368/8739-01)
Arkansas Power & Light Company is hereby required to submit a written statement or explanation to this Office within 30 days of the date of the letter transmitting this Notice. This reply, should include for each deviation:
(1) the reason for the deviation if admitted, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further deviations, and (4) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time.
Dated at Arlingtor,, Texas, this 4th day of March 1988.
pBR 9Ba!R Bi88)}p G