Forwards Braidwood Unit 1,Cycle 1 Startup Rept, Per Tech Spec 6.9.1.3 & Covers Initial Criticality
ML20147G211
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 02/29/1988
From: Hunsader S
COMMONWEALTH EDISON CO.
To: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20147G216 List:
References
NUDOCS 8803080162
Download: ML20147G211 (1)


Text

p N

[/h(S

~ 'y

/,.~.-\ - Commonwealth Edloon

) One First Nabonal Plaza, Chicago, IEnois

'~ Address Reply to: Poet Omco Box 767

've Chscago,IEnois 60690 0767 February 29, 1988 I PRIORITYRMIO 1 e 1stmuL sch ,

} ~

Mr. A. Bert Davis ( - -

Regional Administrator g 'ael E1 -

gna Region III E l '"

U. S. Nuclear Regulatory Commission O fik 799 Roosevelt Road ~

Glen Ellyn, IL 60137

SUBJECT:

Braidwood Nuclear Power Station Unit 1 Cycle 1 Startup Report NRC Docket No. 50-456

Dear Mr. Davis:

The enclosed Startup Report for Braidwood Unit 1, Cycle 1 is being submitted to you in accordance with Technical Specification 6.9.1.3 and covers initial criticality. Supplementary reports will be issued covering the balance of Startup Testing in accordance with Technical Specification 6.9.1.3.

Very truly yours, h{.

S. C. Hunsader

-!h Nuclear Licensing Administrator Attechment ec: S. Sands - NRR NRC Document Control Desk l'AR ~2 fggg Encl. Braidwood Unit 1, Cycle 1 Startup Report 7

4296K 8803080162 800229 1!

)

PDR ADOCK 0S000456 P PDR O