ML20147C878
| ML20147C878 | |
| Person / Time | |
|---|---|
| Site: | 05000580, 05000581 |
| Issue date: | 10/06/1978 |
| From: | Mcwhorter R OHIO EDISON CO. |
| To: | Regan W Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML20147C881 | List: |
| References | |
| NUDOCS 7810130157 | |
| Download: ML20147C878 (1) | |
Text
- _ - - _ - _ _ _ _, _ _ _ - _ _ - - _ _ _ _ _ _ _ _
c 0
OHIO EDISON COMPANY 76 SOUTH MAJN STREET, AKRON, OHIO 44308 e 216 384 5913 Octob'er 6, 1978 ROBERT J. McWHORTER VICE PRESILIENT G+M ~ So-58o Sgt Mr. Wm. H. Regan, Jr.
i f
Chief, Environmental Projects f
Branch 2 Division of Site Safety &
Environmental Analysis 3
I U. S. Nuclear Regulatory Commission l
Washington, D. C.
20555
Subject:
Erie Nuclear Plant, Units 1 & 2 Revised CAPCO Load Forecast
Dear Mr. Regan:
Enclosed for your information is the supplemental testimony, dated l
August 26, 1978, of Mr. Lynn Firestone describing t_.e revised CAPC0 Load l
forecast, as submitted to the Ohio Power Siting Commission, during the recent I
state certification hearings for the Erie Nuclear Plant. This material was l
previously submitted informally to Mr. Singh Bajwa (NRC) at the time it was l
prepared in an effort to keep USNRC advised of energy and load forecast
)
changes in a timely manner as they occur.
If you should have any questions, please advise.
Very truly yours, j
W krfrJ l
RJM/ECB:klp Enclosure 1
l cc: GCharnoff 1
I l
1&toi%s7 goa,]gg%
llI