Forwards Info Which Is 780828 Suppl Testimony of L.Firestone Describing the Rev Capco Load Forecast as Submitted to Oh Pwr Siting Comm During State Cert Hearings for Subj Facil. Matl Was Previously Submitted Informally to Singh Bajwa,Nrc
ML20147C878
Person / Time
Site: 05000580, 05000581
Issue date: 10/06/1978
From: Mcwhorter R
OHIO EDISON CO.
To: Regan W
Office of Nuclear Reactor Regulation
Shared Package
ML20147C881 List:
References
NUDOCS 7810130157
Download: ML20147C878 (1)


Text

- _ - - _ - _ _ _ _ , _ _ _ - _ _ - - _ _ _ _ _ _ _ _

  • c 0

ROBERT J. McWHORTER VICE PRESILIENT OHIO EDISON COMPANY 76 SOUTH MAJN STREET, AKRON, OHIO 44308 e 216 384 5913 Octob'er 6, 1978 G+M ~ So-58o i Mr. Wm. H. Regan, Jr.

Sgt f Chief, Environmental Projects f Branch 2 Division of Site Safety &

3 Environmental Analysis I U. S. Nuclear Regulatory Commission l

Washington, D. C. 20555

Subject:

Erie Nuclear Plant, Units 1 & 2 Revised CAPCO Load Forecast

Dear Mr. Regan:

Enclosed for your information is the supplemental testimony, dated l August 26, 1978, of Mr. Lynn Firestone describing t_.e revised CAPC0 Load l forecast, as submitted to the Ohio Power Siting Commission, during the recent I state certification hearings for the Erie Nuclear Plant. This material was l previously submitted informally to Mr. Singh Bajwa (NRC) at the time it was l prepared in an effort to keep USNRC advised of energy and load forecast )

changes in a timely manner as they occur.

If you should have any questions, please advise.

Very truly yours, j krfrJ -