Final Deficiency Rept CP-87-48 Re Cable Tray Transverse Clamps.Initially Reported on 870821.Completion of Unit 1 Corrective Actions Will Be Commensurate W/Schedule for post- Const Hardware Validation Program
ML20147C261
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/26/1988
From: Walker R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-87-48, TXX-88261, NUDOCS 8803030038
Download: ML20147C261 (1)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ - _ _ _ - _ _ _ _ _ - _ _

P-EE Log

  1. TXX-88261 Fi1e # 10110

_r-r 903.9 U'

'}

illELECTRIC February 26, 1988 w ou=,c. coumu cmws er, er,*,,,

U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 CABLE TRAY TRA?$ VERSE CLA!M SDAR:

CP-87-48 (FINAL REPORT)

Gentlemen:

On August 21, 1987, we notified you by our letter, logged Txx-6658, of a deficiency involving cable tray transverse clamps which we deemed reportable under the provisions of 10CF,750.55(e). Our latest re3 ort on this issue, logged TXX-6760, was submitted September 21, 1987.

Tiis report is submitted to provide the schedule for corrective action completion.

The completion of the Unit 1 corrective actions will be c$mmensurate with the schedule for the Post Construction Hardware Validation Program (PCHVP).

The completion of the corresponding Unit 2 corrective actions will be completed prior to Unit 2 fuel ioading.

Very truly yours.

W. G. Counsil By:

1 R. D. Ralker Manager, Nuclear Licensing DAR/grr c-Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) 8803030038 880226 PDR ADOCK 05000445 S