Comm:nwrith Edison f( O
- C Ons First National Plaza, Chicago, Illinois
. Address Reply to: Post Office Box 767 Chicago, Illinois 60690 October 4, 1978 l
l Mr. Dennis L. Ziemann, Chief Operating Reactors - Branch 2 Division of Operating Reactors U.S. Nuclear Regulatory Commission i
Washington, D.C.
20555
Subject:
Dresden Station Unit 1 Monthly Progress Report as Required by Amendment No. 23 to Facility Operating License No. DPR-2 NRC Docket No. 50-10
Dear Mr. Ziemann:
As required in Amendment No. 23 dated January 6, 1978 to Facility Operating License DPR-2 for Dresden Station Unit 1, we are transmitting the September 1978 monthly report on progress towards completion of our scheduled ECCS, IEEE-279 and fire protection modifications including related activities which could affect these projects such as the decontamination program.
HPCI The HPCI building roof is now complete.
The outer walls of the valve house and penetration structure were poured.
Good progress was also made on the north electrical duct run.
These jobs had been delayed somewhat by a shortage of concrete.
The electrical installation has started and a purchase requisition was issued for the thermal shock reanalysis.
The expected operational date for the HPCI system is 11/1/79.
IEEE-279 The motor control center vendor's prints and pro-l cedures have been reviewed and returned to him with minor comments.
There are no major problems foreseen with approval of the drawings and procedures by early November.
Most of the j
Limitorque valve operators are on the site.
It is expected the j
electrical penetration will be on the site during November.
wfWW7Y g
/9ises//JE l
'/Vo
- -.. L i
C:mmenwanith Edis:n NRC Docket No. 50-10 Mr. Dennis L. Ziemann: October 4, 1978 i
Fire Protection The seismic issue concerning the fire protection contractors hanger turned out to be larger than expected.
The problem has been resclved and design on the fire system piping is proceeding.
The complete design minus the hangers has been received.
The final construction drawings should be re-ceived with the hangers shown during October.
Chemical Cleaning The painting contract is still unawarded.
We anticipate the contract will be awarded in early October.
An additional specification for NDE of the in and out of sphere welds is being prepared by Catalytic.
This specification should be submitted for CECO. review shortly.
An independent testing laboratory will be contracted to perform this work.
Structural steel work is 85% complete and the concrete work is 92% complete.
Foundation work for the service water facility is in progress.
The basemat should be placed the week of 10/2/78 The HVAC contractor has arrived on site and the electrical installation activities have started.
One (1) signed original and thirty-nine (39) copies of this letter are provided for your use.
Very truly yours, v
s M.
S. Turbak Nuclear Licensing Administrator Boiling Water Reactors