Text
'
~N) Conuninw:cith Edison
/
I One First National Plaza. Chicago, Illinois
( O '/
,' Address Reply to: Post Office Box 767 Chicago, Illinois 60690 N
l October 3, 1978 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Subject:
Zion Station Units 1 and 2 Schedule for Revised ECCS Evaluation NRC Docket Nos. 50-295 and 50-304 Reference (a):
September 13, 1978 letter from A.
Schwencer to Cordell Reed requesting schedule for submittal of a revised ECCS evaluation for Zion Station
Dear Sir:
Per Reference (a), Commonwealth Edison Company was requested to provide the NRC Staff with a schedule for sub-mittal of a revised analysis of ECCS cooling performance for Zion Station Units 1 and 2.
This analysis is to be calculated in accordance with the revised Westinghouse ECCS evaluation model approved by the NRC Staff in August 1978.
Westinghouse has currently scheduled a revised analysis for the Zion units to begin in late October 1978.
Upon receipt of the results of this analysis Commonwealth Edison l
will prepare, review and approve the appropriate Zion Station Technical Specification changes associated with the revised analysis for submittal to the NRC Staff.
Based on the above, Commonwealth Edison's current
(
schedule for submittal to the NRC Staff of the required revised ECCS analysis and its associated technical specification changes is January 5, 1979.
Very truly yours, g
l
>[
William F. Naughton Nuclear Licensing Administrator Pressurized Water Reactors l
l ge//s