Forwards Second Quarter Update to Fire Protection/App R Program Milestones,In Response to NRC .Safe Shutdown Safety Sequence Diagrams in Final Form & Estimated Completion Date Changed from 920815 to 0915
ML20141M271
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 08/04/1992
From: Cross J, Walt T
PORTLAND GENERAL ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9208110003
Download: ML20141M271 (5)


Text

__ _ _ _ - _ - _ _ _ _ - _ _ _ _ _ _

9 N

M

~

G NT, Portland General Electric Company James E. Cross Vice President and Chief Nuclear Officer August 4, 1992 Trojan Nuclear Plant Docket 50-344 License NPF-1 U.S. Nuclear Regulatory Conrnission Attn:

Document Control Desk Washington DC 20555 Dear Sir Elte_EIDLettion/Apprudix

'R' PIngr.atLMiltalonca_Ilpdate In response to your letter of January 22, 1992 and as a follow-u}

o our February 21, 1992 letter (VPN-066-92) transmittinF the Fire Prote. ion /

Appendix

'R' Program milestones, attached is the second quarter update to the milestone activities. Changes to milestone daten are annotated by revision bars.

Sincerely.

T. D. Walt At taclunen t for J. E. Cross c:

Mr. John B. Martin Regional Admin!strator, Region V U.S. Nuclear Regulatory Commission Mr. David Stewart-Smith State of Oregon Department of Energy Mr. R. C. Barr NRC Resident Inspector Trojan Nuclear Plant y

kho O

4 0

F 121 SW Salmon Street, Portland, OR 97204 k

i 503/464-6897

  • Trojan Nuclear Plant Document Control Desk l

' Docket 50-344 August 4, 1992 License NPF-1 Page 1 of 4 FIRE PROTECTION / APPENDIX 'R' PROGRAM MILESTONES UPDATE - SECONILQL%RIER 1992 D scr.iplion

_DaC Insk A

1.

Establish Administrative Goals for Fire Protection.

Complete

. Consolidate the Fire Protection Program.

Interfaces and responsibilities.

. Develop procedure for Fire Protection Program.

The Fire Protection activities within the engineering department have been consolidated under the control of one group. The Nuclear Plant Engineering (NPE) Fire Protection Group '.as a dedicated supervisor who reports to the General Maaager, NPE via the Assistant General Manager, NPE.

T'ojan Plant Procedure (TPP) 13-7, Fire Protection Program Responsibilities, was issued to define organizational interfaces and responsibilities for implementing Trojan's Fire Protection Program.

TPP 24-1, Equipment Control Guidelines for Appendix

'R' to 10 CFR 50 Safe Shutdown Equipment, was issued to clarify administrativo requirements for Appendix

'R' safe shutdown equipment.

2.

Revise Portland General Electric Company (PCE)-1011, Complete Fire Protection Plan Program Description.-

The completion date for this task w;A changed to July 30, 1992 by our letter (VPN-118-92; dated-May 6,1992 to accommodate an extensive internal review of PGE-1012 Amendment 12.

3..

Document Program Goals and Standards.:

Complete

. Use of Title 10 to the Code of Federal Regulations, Part 50.59 (10 CFR 50.59) evaluations and exemption requests under Generic: Letter 86-10.

. Establish performance standards for the Fire Protection Program.

A review of the use of 10 CFR 50.59 evaluations and exemption requests under-the guidelines of Generic letter 86-10 was performed and clarifying guidance was issued.

I Trojan Nuclear Plant Document Control Desk Docket 50-344 August 4, 1992 License NPF-1 Page 2 of 4 Iask Description

__Date_

An NPE operating plan for Appendix

'R' and Fire Pro-tection was created to establish goals, objectives, and define activities for the Fire Protection Program upgrade effort. Nuclear Engineering Manual Procedure (NEMP) 18.18.1, Upgraded Fire Protection Program Document dierarchy, was issued to provide an overview of the documents which describe and implement the upgrade program.

4.

Issue Fire Protection Program Procedures.

Complete

. Procedures to include a review of design basis and analysis assumptions when making changes to the safe shutdown analysis or its implementing procedures.

This task was completed with the issuance of TPP 13-7, NEMP 18.18.1, and NEMP 18.18.2, Instructions for Conducting and Implementing 10 CFR 50 Appendix R Analysis Upgrade.

5.

Complete Safety Sequence Diagram.

09/15/92

. Reevaluate present approach to Appendix 'R' safe shutdown.

The safe shutdown safety sequence diagrams are in final draft. Because receipt of the diagrams is not expected from the engineering vendor until mid-August 1992 and an internal review and approval of the diagrams will be performed, the estimated completion date for this task has been changed from August 15, 1992 to September 15, 1992.

6.

Complete Electrical Circuit Analysis.

11/01/92

. Emergency Fire Procedure (EFP) background documents will be updated to be consistent with EFPs and modified spurious operation analysis.

Procedures, assumptions, and methodology supporting the electrical circuit analysis have been completed.

The cable and subcomponent selection for the circuit analysis has begwi.

Updating of the EFP background documents to ensure their consistency with the EFPs and the modified spurious operations analysis is on schedule.

x

Trojan Nuclear Plant Document Control Desk

' Docket 50-344 August 4, 1992 License NPF-1

-Page 3 of 4 Iank Dageriptlop

.._Dain___

1 7.

reriodie Update of PGE-1012.

Complete PGE-1012 will be revised as required by 10 CFR 50.71(e) to reflect the completion of milestones which impact the Fire Protection Program Plan.

8.

Complete Cable Separation Analysis.

06/15/93

. " cr!.nu walkdown of fire areas to identify spurious i

++pe ation components in support of spurious operation-uesociated circu't reanalySim,

. Perform more det., led spurious operation evaluation coraidering. circuit analysis, time constrait.ts, operator actions, ant available indications /

parameters.

j Validate Calculation TNP 84-17 for transit time to or through fire areas to p3rform manual act30as.

Reassess shutdown methodology, including station 1

blackout.

Address prensurizer power-operated relici valve (PORV) circuitry HI/LO interface requirements of Generic Letter 86-10.

Incorporate circuit analysis of communicstions equipment into' safe shutdown analysis, i

Inform the Nuclear Regulatory Commission (NRC) if station blackout is the preferred methodology for achieving safe shutdown.

The comp 13 tion of this task and the associated cubtaaks remain on schedule. A revised-sp<rious operations-anelysis was completed and documented as Calculation TF-006, Spurious Operation Evaluation.

p Calculation TF-011, High~Pricrity Operator Actions and Transit in Effected Fire Area,ifas issued to supersede TNF 89-17 and identifies fire areas.in which access is needed to perform time-critical-actions or transit through the area.

9.

Complete Design Basis Document (UBD)-System 13 07/01/93 Validation.

Plant walkdowns are being performed and-are on schedule to' meet the task completion date.

1

]

~

Trojan Nucleas Plant Document Control Desk

' Do-6et 50-364 August 4, 1992 L c nse NPF-1

? age 4 of 4 5

1 Inak Description

__Date__

10.

Complete Fire Damper Modifications.

12/31/93 i

Fire damper modifications are in progress and on

~,

schedule to meet the task completion date.

11.

Complete Foamed Fire Seal Replacement.

12/31/93 Formed seal replacements are in progress and on i

schedule to meet the task completion date.

12.

National Fire Protection Association (NFPA) Code 05/12/94 Resolutions.

. Verify syster aesign and identify NFPA/

Underwriters Laboratories, Inc. (UL) Code deviations.

. Develop inspection / maintenance criteria for fire protection features not presently covered by existing Pisnt procedures.

NFPA Code deviation issues are being addressed.

4 13.

Implement Revised Methodology - Modifications.

06/15/94

. Protect pressurizer PORVs from effects of multiple hot shorts.

Work associated with this tack has not been initiated, I

i l

l 1