Forwards Rev 0 to Operating Procedure OP 3263, Unit 3 Duty Officer Requirements After Trip or ESF Actuation, in Response to 850910 Request for Addl Info Re Generic Ltr 83-28, Generic Implications of Salem ATWS Event
ML20141G804
Person / Time
Site: Millstone Dominion icon.png
Issue date: 11/07/1985
From: Opeka J, Sears C
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To: Youngblood B
Office of Nuclear Reactor Regulation
Shared Package
ML20141G809 List:
References
F0871A, F871A, GL-83-28, NUDOCS 8601100416
Download: ML20141G804 (39)


Text

P ,

.i m UTILITIES Genal Omces

, (203) 88 5 s000 November 7,1985 Docket No. 50-423 F0871 A

~

Director of Nuclear Reactor Regulation Mr. B. 3. Youngblood, Chief Licensing Branch No. I Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

References:

(1) W. G. Counsil letter to D. G. Eisenhut, " Millstone Nuclear Power Station, Unit Nos.1, 2 and 3; Response to Generic Letter 83-28; Generic Implications of Salem ATWS Event,"

dated November 8,1983.

(2) B. 3. Youngblood letter to 3. F. Opeka, " Request for Additional Information for Millstone Nuclear Power Station, Unit No. 3," dated September 10,1985.

(3) 3. F. Opeka letter to B. 3. Youngblood, " Millstone Nuclear Power Station, Unit No. 3; Response to Request for Additional Information; Generic Letter 83-28, Post-Trip Review," dated October 8,1985.

(4) T. M. Novak letter to 3. F. Opeka, " Draft License for Millstone Nuclear Power Station, Unit No. 3," dated October 28,1985.

Dear Mr. Youngblood:

Millstone Nucleer Power Station, Unit No. 3 Response to Request for AdditionalInformation Operating Procedure for Post-Trip Review (Generic Letter 83-28)

In Reference (1), Northeast Nuclear Energy Company (NNECO) indicated that an operating procedure regarding the post-trip review program for Millstone Unit No. 3 would be available for NRC Staff review. In Reference (2), you requested that we provide this procedure so that the NRC Staff may complete its review of our prograir..

In Reference (3), we informed you that we were in the process of finalizing this operating procedure for Millstone Unit No. ,3. Attached is the operating procedure for the post-trip review program which should enable your Staff to complete its review of this item. As such, item 2.c(18) can be removed from the Millstone Unit No. 3 draf t license (Reference 4).

~~

B601100416 851107 PDR ADOCK 05000423 ^8 T " " "" 1' '

P PDR gg g 'g?cg^{g",'*l PSB (CAMMILL) asB (BERLINGER)

F08 (BEMAROYA)

.E.,

%.f). .- _,

In Reference (1), we also informed you that personnel who perform the function -

of Duty Officer will hold and maintain a current SRO license on the unit. All Millstone Unit No. 3 Duty Officers have participated in the cold license training

-program, however, due to other priorities,- all were not able to take the SRO exam prior to startup. We consider these non-licensed Duty Officers to have a level of knowledge equivalent to that of a SRO licensed individual by virtue of their. participation in the cold license training program. Additionally, it is our

. intent to have them obtain their SRO license within the next few years.

Should you have_any further concerns regarding this matter, please contact our licensing representative.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY et. al.

BY NORTHEAST NUCLEAR ENERGY COMPANY Their Agent

)

3. F. Opeka D 1 Senior Vice President h

b By: C. F. Sears Vice President STATE OF CONNECTICUT )

) ss. Berlin COUNTY OF HARTFORD )

Then personally appeared before me C. F. Sears, who being duly sworn, did state

'that he is Vice President of Northeast Nuclear Energy Company, an Applicant herein, that he is authorized to execute and file the foregoing information in the name and on behalf of the Applicants herein and that the statements contained in said information are true and correct to the best of his knowledge and belief.