ML20141F897
| ML20141F897 | |
| Person / Time | |
|---|---|
| Issue date: | 04/22/1986 |
| From: | Capra R NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO) |
| To: | Committee To Review Generic Requirements |
| References | |
| NUDOCS 8604230218 | |
| Download: ML20141F897 (3) | |
Text
_ _ _ _ _ _ - _ - _
s.
APR 2 21996 NOTE T0: CRGR MEMBERS MONTHLY REPORT Enclosed is a copy of the summary of CRGR activities for the period February 1 through March 31, 1986. The summary will be included in the ED0's Weekly Report to the Commission for the week ending April 18, 1986.
Robert Capra
Enclosure:
As stated Distribution:
JHSniezek W3chwink DEDROGR cf ROGR staff Central File PDR (NRG/CRGR)
RE
/,
I 0FC :ROGR
- ROGR
...__:._____t_____:...__q,,g,__:____________:-___________:..______ ___:____________:___________
NAME:BGaf__,t l
- RCapra DATE :4/21/86
- 4/t1/86
i DEPUTY EXECUTIVE DIRECTOR FOR REGIONAL OPERATIONS AND GENERIC REQUIREMENTS (DEDROGR)
Week Ending April 18, 1986 CRGR Attached is a summary of the CRGR activities for the period February I through March 31, 1986. Background material on topics reviewed by the Committee and the minutes of CRGR meetings are sent to the Commission. Copies are provided to the Public Document Room after the NRC has considered (in a public forum) or decided the matter addressed by the documents. Questions concerning this monthly report should be referred to Walt Schwink (492-8639).
r-
-y
,e_-,m-r---
Paga 1 of 1 Dat2: April 18, 1986
SUMMARY
OF CRGR ACTIVITIES (February 1 through March 31, 1986)
Meeting No.
Meeting Date (Announcement CRGR CRGR Recommendation Date)
Agenda Status to EDO EDO Action i
87 Review, Final Rulemaking Complete CRGR recomended that the NRR revised package l
3/19/86 Package to Revise the proposal, as modified, be according to CRGR Regulations for Operator approved by the EDO.
recommendations.
Licensing, 10 CFR 55, Package currently in E00 Conforming Amendments and office for approval.
l Three Associated RGs
-Sponsoring Office - NRR l
-Category 2 Item l
-Issue #125 l
l 86 Review, Final Rulemaking Pending No CRGR recommendation at this No action necessary at 2/26/86 Package to Revise the time. This review was continued this time because Regulations for Operator at Meeting No. 87 on March 19.
review of this item is Licensing, 10 CFR Part 55, incomplete.
Conforming Amendments and Three Associated RGs
-Sponsoring Office - NRR
-Category 2 Item
-Issue #125 85 Review, Proposed Broad Complete The CRGR recomended that the Resolve differences 2/5/86 Scope Rule to Modify General proposed broad-scope rule package between CRGR and Design Criterion 4 of 10 be sent forward for consideration sponsoring office CFR Part 50 by the Comission, subject to the indicated in RES memos modifications recommended by CRGR dtd 4/7/86 and 4/9/86
-Sponsoring Office - RES
-Category 2 Item
-Issue #135