May 15, 1997 Mr. Michael B. Sellman President l
Maine Yankee Atomic Power Company l
329 Bath Road Brunswick, Maine 04011
SUBJECT:
PLANT PERFORMANCE REVIEW (PPR)- MAINE YANKEE I
On March 271997, the NRC staff completed the semiannual Plant Performance Review (PPR) of Maine Yankee. The staff conducts these reviews for all operating nuclear power.
l plants to develop an integrated understanding of safety performance. The results are used by NRC management to facilitate planning and allocation of inspection resources. The PPR for Maine Yankee involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period January 1,1996, through March,1997. PPRs provide NRC management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and senior management meeting (SMM) reviews.
This letter advises you of our planned inspection effort resulting from the Maine Yankee PPR review. It is provided to minimize the resource impact on your staff and to allow for i
scheduling conflicts and personnel availability to be resolved in advance of inspector arrival l
onsite. The enclosure details our inspection plan for the next 8 months. Additionally, the l
NRC will provide you with our Restart Plan, which will detail the issues that we willinspect i
prior to restart of the facility. Resident inspections are not listed due to their ongoing and j
continuous nature.
We willinform you of any changes to the inspection plan. If you have any questions, please contact Curtis J. Cowgill at (610) 337-5233.
l Sincerely, Original Signed By:
Curtis J. Cowgill, Chief Reactor Projects Branch 5 Docket 'Nos. 50-309 I
l
[
i
Enclosure:
Inspection Plan fD 200002 b
5.E555,lQg 1
l 9705200096 970515 i
PDR ADOCK 05000309 l
0 PDR
3
-.- ~
l l
\\'
Mr. Michael B. Sellman 2
~
cc w/ encl:
G. Leitch, Vice President, Operations M. Meisner, Vice President, Licensing and Regulatory Compliance B. Hinkley, Acting Vice President, Engineering J. M. Block, Attorney at Law P. L. Anderson, Project Manager (Yankee Atomic Electric Company)
R. Blackmore, Plant Manager L. Diehl, Manager of Public and Governmental Affairs J. A. Ritsher, Attorney (Ropes and Gray)
P. Dostie, State Nuclear Safety inspector P. Brann, Assistant Attorney General U. Vanags, State Nuclear Safety Advisor C. Brinkman, Combustion Engineering, Inc.
W. D. Meinert, Nuclear Engineer First Selectmen of Wiscasset Maine State Planning Officer - Nuclear Safety Advisor State of Maine, SLO Designee l
State Planning Officer - Executive Department Friends of the Coast 1
4 l
l
7 j
-e l
Mr Michael B. Sellman 3
Qistribution w/ encl:
Region ! Docket Room (with concurrences) l Nuclear Safety information Center (NSIC) l PUBLIC l
NRC Resident inspector DRS Director, Region I DRS Deputy Director, Region i DRS Branch Chiefs, Region I DRP Director, Region I DRP Deputy Director, Region i DRP Branch Chiefs. Region I E. Conner, DRP M. Oprendek, DRP D. Bearde, DRP Distribution w/enci (VIA E-MAIL):
W. Dean, OEDO S. Varga, NRR D. Dorman, PM, NRR M. Callahan, OCA R. Correia, NRR D. Taylor, NRR D. Screnci, PAO Inspection Program Branch, NRR (IPAS) 4~
DOCUMENT NAME: G:\\ BRANCH 5\\PPR\\MYPPRLTR.597 To receive a copy of this document, indicate in the box:
C" = Copy without attachment / enclosure "E" = Copy with attachment / enclosure "N" = No copy OFFICE Rl/DRP j
Rl/DRP//V NAME EConner CCowgill DATE S/1/07 5/pf/97
^
l OFFICIAL RECORD COPY l
l w
Enclssura MAINE YANKEE SPECIAL INSPECTION PLAN INSPECTION TITLE / PROGRAM AREA D TES 92903 Followup - Engineering Star Date 92902 Followup - Maintenance Star Date 92901 Followup - Operations Star Date 42700 Plant Procedures 5/16/97 60705 Preparations for refueling 5/19/97 71707 Plant Operations 5/19/97 Service Water System Operational Performance 6/2/97 Tl 2515/118 Inspection (SWSOPI) 6/20/97 IP 92903 Followup - Engineering 6/20/97 IP 83729 Occupational Exposure During Extended Outages 6/16/97 Radioactive Waste Treatment, and Effluent and IP 84750 6/30/97 Environmental Monitoring 92903 Followup - Engineering 7/1/97 IP 62706 Maintenance Rule inspection Procedure 7/7/97 IP 81020 Management Effectiveness - Security Program 8/11/97 IP 82205 Shift Staffing and Augmentation 8/18/97 Triennial Postfire Safe Shutdown Capability IP 64150 10/1/97 Revenfication IP 64704 Fire Protection Program 10/1/97 Inspection Requirements for Generic Letter 89-10, Tl 2515/109 Safety-related Motor-operated Valve Testing and 10/6/97 Surveillance Notes:
IP Inspection Procedure Tl Temporary instruction Core Minimum NRC Inspection Program (mandatory for all plants)