Forwards LER 97-015-00 Re Event or Condition That Resulted in Manual or Automatic Actuation of Esf.Commitments Made by Ltr,Submitted
Date released: 06/03/2020 Download: ML20141A218


:on 970418,electrical Penetration Assembly Failed Due to Aging & Deterioration of Undervoltage Release Coil Causing Loss of Power to Reactor Protection Bus 1B. Caused by EPA Breaker Failure.Epa Breakers Replaced
ML20141A251
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 05/08/1997
From: Peterson C
COMMONWEALTH EDISON CO.
To:
References
Download: ML20141A251 (4)
Forwards LER 97-015-00 Re Event or Condition That Resulted in Manual or Automatic Actuation of Esf.Commitments Made by Ltr,Submitted
ML20141A216
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 05/08/1997
From: Pearce L
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
Download: ML20141A216 (1)