Advises That NRC Restriction of Operations Above 90% Power, Per SER Section 15.4.3,may Be Removed Based on Completion of Dropped Rod Analysis for Cycle 1 Using Methodology in WCAP-10297-PA.Confirmatory Item 42 Complete
ML20140J209
Person / Time
Site: Beaver Valley
Issue date: 04/01/1986
From: Carey J
DUQUESNE LIGHT CO.
To: Harold Denton, Tam P
Office of Nuclear Reactor Regulation
References
2NRC-6-030, 2NRC-6-30, TAC-62928, WCAP-10297-PA, NUDOCS 8604040279
Download: ML20140J209 (1)


Text

'Af 4

a 5 41 E.*zIs)fo k z$s"ote21o N

T*""

n Pittsburgh, PA 15205 April 1, 1986 Mr. Harold R. Denton, Director Office of Nuclear Rector Regulation United States Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

Mr. Peter Tam, Project Manager Division of PWR Licensing - A Of fice of Nuclear Reactor Regulations

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 Dropped Rod Calculations Gentlemen:

Westinghouse has completed the dropped rod analysis for Cycle 1 of Beaver Valley Station, Unit 2 (BVPS-2).

It was performed utilizing the methodology in WCAP-10297-PA, " Dropped Rod Methodology for Negative Flux Rate Trip Plants."

Based upon this analysis, the NRC's restriction of operations above 90% power as described in the BVPS-2 Safety Evaluation Report (SER), Section 15.4.3, may be removed.

This completes confirmatory Item No. 42.

Please note that this is specific for Cycle 1 operation and is valid for the "Lemoniz" fuel, which will be used at BVPS-2.

Detail of the "Lemoniz" fuel will be provided in. Amendment 12 to the Final Safety Analysis Report.

DUQUESNE LIGHT COMPANY By _

J. W. Carey Vice President RWF/jdw NR/NRC/ DROP-R0D cc:

Mr. P. Tam, Project Manager Mr. G. Walton, NRC Resident Inspector INPO Records Center NRC Document Control Desk 9604040279 860401 PDR ADOCK 05000412 k