Advises That Rev 1 to App R Compliance Assessment Rept, Will Be Submitted Prior to 860506,per 851210 Commitment.Addl Internal & Independent External Reviews Will Be Completed for Rev 1,per 860324 Discussion
ML20140F601
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/27/1986
From: Williams J
TOLEDO EDISON CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
1262, NUDOCS 8604010103
Download: ML20140F601 (1)


Text

.

TOLEDO h EDISON Docket No. 50-346 JOE WwAMs. JR Serenr We 6%essert - Nur seer (4191249 ?XO License No. NFP-3 ta'S!m W Serial No. 1262 March 27, 1986 Mr. John F. Stelz, Director PWR Project Directorate No. 6 Division of PWR Licensing-B United States Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Stolz:

In our letter dated December 10, 1985 (Serial No. 1210), the Toledo Edison Company committed to submit for your review and approval Revision 1 of the Davis-Besse Nuclear Power Station Unit No. 1 Appendix R Compliance Assessment Report (CAR). As discussed with Mr. A. DeAgazio on March 24, 1986, although the CAR was essentially completed as committed to, Toledo Edison mrtagement has commissioned additional reviews for completion prior to submitting the CAR. These reviews consist of several internal reviews as well as an independent external review of the CAR. The objectives of these reviews are to ensure that the commitments identified in the two-volume CAR are accurate, clearly defined, adequately planned, and that statements made within the CAR accurately reflect plant and analysis conditions.

Toledo Edison is committed to ensuring adequate action is implemented to address the Appendix R issues as well as those actions necessary to upgrade the Fire Protection Program. As such, the additional reviews which are currently underway will provide Toledo Edison with further assurance that the CAR has been adequately prepared and reviewed. Toledo Edison will complete these reviews for Revision 1 of the CAR and submit the document to your office prior to May 6, 1986.

Very truly yours, d

hh JW:TJB:dem cc: DB-1 NRC Resident Inspector h

0 J. Ulfe - Region III 0

1<0 k

0604010103 60327 gDR ADOCK O p 346 THE TOLEDO ED! SON COMPANY EDISON PLAZA 300 MAOtGON AVENUE TOLEDO. OH!O 43652