Text
..-
. ~
s 3
Pubhc Service i
4 Electnc and Gas Company Cerbin A. McNeill, Jr.
Public Se wce Electnc and Gas Company P.O. Box 236.Hancocks Bridge,NJ 08038 609 339 4800 Vice President -
Nuctear
{
January 15, 1986 i
1 i
l Director of Nuclear Reactor Regulation
}
United States Nuclear Regulatory Commission 7920 Norfolk Avenue i
Bethesda, Maryland 20814 Attention:
Ms. Elinor Adensam, Director Project Directorate 3 Division of BWR Licensing
Dear Ms. Adensam:
STATUS OF FUEL LOAD AND LOW POWER /
POWER ASCENSION TESTING HOPE CREEK GENERATING STATION l
DOCKET NO. 50-354 In a letter dated November 29, 1985, Public Service Electric and Gas Company provided the NRC a draft listing of systems that were projected not to be completed at the time of fuel loading.
PSE&G hereby submits an updated status of the draft listing (Attachments I and II).
Attachment I identifies those systems that are removed from the proposed list of deferral
]
systems as presented in our letter of November 29, 1985.
l These systems will be complete in support of fuel load.
Attachment i
II identifies those systems that are scheduled for completion i
after fuel load.
A finalized list of-systems which will l
not be completed by fuel load will be submitted to the NRC l
at least 30 days prior to the. anticipated fuel load date.
In support of the system deferral effort, a safety evaluation for each deferred system has been performed.
Each safety evaluation has been reviewed by both the Station Operations Review Committee (SORC) and the Offsite Safety Review Group (OSR).
The results of these reviews demonstrate that post fuel load completion of the systems identified in Attachment II pose no undue risk to the health and safety of the public.
i 6
/
86012701g0 860115 kDR ADOCM 05000354 i
1 PDR e
1
,-_,.v.g.
,,....,,,.,..,, _. ~,,,. _, -...,,,., _.. ~.., _,...,,
,,,,,,-,-w.,,,
,m.,,._,w,~,
.,cy,
,7
-,,,,-,,-,.,,,,,,y
,,yg..__ -..
.,--.-,,--ye 3
,,y,w,,__-
J s
=
1 i
4 Director of-Nuclear 1-15-86 Reactor Regulation
+
t
-All items required to be complete in order to load fuel have been summarized in a Master Punchlist.
Corrective actions as a result of 10CFR50.55(e) reportable deficiencies and inspection report open items are identified on the Master Punchlist.
These items are being resolved directly with Region I.
The current assessment of the remaining activities required to be completed prior to issuance of a low-power license for j
HCGS indicate the plant will be ready to load fuel March 7, 1986.
j Please advise PSE&G if any additional information is required
{
to allow the NRC to plan its resources to support timely issuance j
of a low power license for the Hope Creek Generating Station.
Sincerely, 4
i
%~
i i
j Attachment i
C D.
H. Wagner USNRC Licensing Project Manager R. W.
Borchardt l
USNRC Senior Resident Inspector t
i i
I 4
i i
f i
?
- 1..
ATTACHMENT I The follcwing systems, which were identified as post-fuel load completion items in our November 29, 1985 letter will be completed prior to fuel load.
Each item identified below is correlated to its respective identifier as presented in Attachment I to our November 29, 1985 submittal.
G.
Main Turbine Control (EHC) System H.
Radwaste Building and Turbine Building.
Fire Protection Water Systems (Automatic Suppression Systems) and Early Warning Smoke Detection Systems J.
Containment Pre-purge Clean-up System (CPCS) e e
ATTACHMENT 1:
The following systems are scheduled for completion after fuel lcad as detailed in the November 29, 1985 letter.
Each iter identified below is correlated to its respective identifier as presented in Attachment I to our November 29, 1985 submittal.
A.
Radwaste HVAC Systems B.
Reactor Building Filtration Recirculation and Ver.tilation System (FRVS)
C.
Liquid Radwaste System D.
Solid Radsaste System E.
Radiation Monitoring System, Area / Process F.
Transverse In-Core Probe Monitoring 1.
Gaseous Radwaste O