Advises of 861201 Fuel Load Date & Commencement of Hearings on 860311 Instead of in Feb 1986.Review of Encl Proposed Milestone Schedule to Facilitate Orderly Support of Region II Activities Requested.W/O Encl
ML20140B499
Person / Time
Site: Vogtle 
Issue date: 03/17/1986
From: Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Gibson A, Stohr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8603240209
Download: ML20140B499 (2)


Text

'

opnee cegy MAR 171986 MEMORANDUM FOR:

Albert F. Gibson, Director, Division of Reactor Safety J. Philio Stohr, Director, Division of Radiation Safety and Safeguards FROM:

Roger D. Walker, Director, Division of Reactor Projects (DRP)

SUBJECT:

V0GTLE UNIT 1 MILESTONE SCHEDULE This memorandum will serve to inform Region II staff of the Georgia Power Company (GPC) scheduled fuel load date of December 1,1986, and to provide a proposed milestone schedule for Region II activities to support the fuel load date.

Hearings commenced March 11, 1986, instead of the previou-scheduled February 1986 date. To facilitate an orderly support of Region II activities regarding IE and licensing, it is requested that your staff review the proposed milestone s::hedule and take appropriate actions to support the schedule. If the scheduled fuel load date changes, DRP will inform the Region II staff.

Marvin V. Sinkule, Section Chief, Vogtle Project Section, will serve as the primary contact for Region II project management as well as for the NRR Licensing Project Manager and GDC licensing interface coordination.

Original Signed by Roger D. Walker Roger D. Walker

Enclosure:

Vogtle 1 Milestone Schedule cc w/ encl:

J. N. Grace, RA V. L. Brownlee, DRP M. S. Sinkule, DRP H. H. Livermore, DRP J. F. Rogge, Vogtle Site R. J. Schepens, Vogtie Site W. H. Rankin, DRP Section Chiefs / Branch Chiefs, RII W. M. Hill, IE M. A. Miller, NRR RII RII RII lS$

k h

VPfnp,//86 MSinkule:lb VBrownlee iera 03/jj/86 03/p/86 03/F ptg22gggggt8agp h

t I

EEc/

1.j c

M AR 171986171986~

ENCLOSURE V0GTLE 1 MILESTONE SCHEDULE June 30, 1985 (C)

SER Issued July 31,1985 (I)

Follow up SER Open Item Full ACRS Review Meeting August 8, 1985 (C)

November, 1985 (C)

Inform Licensee of Completion Letter Requirement (10 CFR50.71(1))

February 3, 1986 (I)

Review Status of CDR's, Part 21's, OIL, Allegations February, 1985 (C)

Issue First Readiness for Licensing Letter Prior to Hearing (Inquiry of Inspectors)

March 11, 1986 Start ASLB Hearing March 15, 1985 Review Inspection Program Status (All)

April 30, 1986 Issue Inspection Program Status June 15, 1986 Commence Preparation and Draft 94300 Letter August 1, 1986 Receive Proof and Review Technical Specifications August 31, 1986 SALP Period Ends September 15, 1986 Publish First 94300 Letter September 15, 1986 Issue a Readiness for Licensing Letter Prior tc Regional Review Panel (Staff Inquiry)

September 19, 1986 SALP Inputs Due October 1, 1986 Perform On-Site Procedure Review (Operations Emergency, Surveillance Maintenance)

October 1, 1986 Issue Second 94300 Letter October 14, 1986 SALP Board Meeting October 20, 1986 Perform on-site Technical Specifications Review November 3, 1986 Region II Division Directors Tour Plant November 6, 1986 Convene Regional Review Panel November 14, 1986 Publish Third 94300 Letter November 20, 1986 SALP Meeting with GPC November 28, 1986 Final Module 94300 Letter December 1986 Phone Closeout of Module 94300 Letter List with NRR Project Manager December 1985 Issue Low Power License January 1987 Readiness Review Inspection January 30, 1987 Develop Regional Brief Package _For Commission Brief for Full Power License February 15, 1987 Commission Brief for Full Power (C) Completed (I) In Progress l