I Public Service f

Company of Co orado P.O. Box 840 2420 W. 26th Avenue, Suite 1000, Denver, Colorado 80211 Denver. co 80201- 0840 (303)571 -7511 December 24, 1985 Fort St. Vrain Unit No. 1 P-85491 Direttor of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attn: kr. F. N. Berkow, Project Director M.uncardization and Special 5'i Projects Directorate Docket No. 50-267

SUBJECT:

Technical Specification Upgrade Program Schedule

REFERENCE:

1)NRCLetter, Butcher to Lee, dated 11/19/85 (G-85466)

2) NRC Letter, Martin to Lee, dated 7/19/85 (G-85288)
3) PSC Letter, Lee to Berkow, dated 11/27/85 (P-85448)

Dear Mr. Berkow:

This letter provides PSC comments on the proposed schedule for completion of the Fort St. Vrain (FSV) Technical Specification Upgrade Program, provided in Reference 1.

The following comments are based on receipt of the NRC mark-up of the Final Draft by January 30, 1986, as indicated in Reference 1.

Any delays in receiving NRC comments will produce similar delays in the rest of the schedule.

oyogg $$e' f,,I EEE a

w m.r=,

i

i l

I 4.

1.

PSC considers that a TSRG reviewer visit on February 11-15, o

1966, would not allow adequate time for PSC review of NRC

(

comments.

PSC proposes that this meeting be held February i

24-28, 1986, at which time the list of action items will be defined.

2.

In order to obtain comments from FSV operations personnel, PSC proposes that six weeks be allowed to resolve action l

ttems.

Several two-or three-day meetings with the NRC l

should also be considered during this comment resolution period.

PSC proposes that all action items and other major l

differences be resolved by April 11, 1986, t

i 3.

PSC considers that the requirement in Reference 2 to submit j

a Itcense amendment within 90 days after NRC comments, i

represents the time required to resolve minor differences, and to obtain approvals of PSC's Plant Operating Review Committee (PORC) and Nuclear facility Safety Committee p

(NFSC). Ninety days is not an adequate time period to resolve new problems or major differences.

PSC considers that this 90 day period would begin April 11, and that an appitcation to amend the Specifications would then be l

submitted by July 10, 1986.

4.

PSC proposes that the NRC issue a license amendment by August 15, 1986.

5.

As identified in Attachment 6 to Reference 3, PSC proposes that the upgraded Technical Specifications be implemented at the startup following the fourth refueling, to a110w for training, procedure development, and data base revisions.

The fourth refueling date for FSV is uncertain, but is currently planned for April 1, 1987.

.--.---._.-__-,---_-_._-,--.,---__--__.-----,,---..-.-,----c---

~

. PSC considers that the above schedule is consistent with the commitments identified in Reference 2.

If you have any questions regarding the above comments, please contact Mr. M. H. Holmes, (303) 480-6960.

Very truly yours, J%M%A e

H. L. Brey, Manager Nuclear Licensing and Fuels Division HLB /SWC/ paw