OCT 2 41335 Docket No.: 50-423 MEMORANDUM FOR:
B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing FROM:
Elizabeth L. Doolittle, Project Manager Licensing Branch No. 1 Division of Licensing
SUBJECT:
FORTHCOMING MEETING WITH NORTHEAST NUCLEAR ENERGY COMPANY TO DISCUSS OPERATIONAL READINESS OF MILLSTONE NUCLEAR POWER STATION, UNIT 3 DATE & TIME:
Monday, October 28, 1985; 6:30 p.m. - 7:45 p.m. and Tuesday, October 29, 1985; 9:00 a.m. - 4:00 p.m.
LOCATION:
Millstone Nuclear Power Station, Unit 3 PURPOSE:
To permit NRC management to assess the operational readiness of Millstone 3.
(See enclosed agenda)
PARTICIPANTS:
NRC NNECO H. Thompson J. Opeka and other J. Taylor representatives of the applicant W. Russell J. Knight L. Rubenstein A. Thadan1 B. J. Youngblood V. S. Noonan E. L. Doolittle S. Black Elizabeth L. Doolittle, Project Manager Licensing Branch No. 1 Division of Licensing
Enclosure:
As stated cc: See next page
/,L)le/mac LBh LB EDo 1tt BJY q ood l0/23/85 g g /85 g511010065851024 R
A ADOCK 05000423 PDR
EHCLOSURE PROPOSED AGENDA MANAGEMENT SITE VISIT MILLSTONE NUCLEAR POWER STATION, UNIT 3 Monday, October 28, 1985 6:30 p.m.
NNEC0/NRC Management Introduction 6:45 p.m.
Begin Simulator Exercise 7:45 p.m.
Complete Simulator Exercise Tuesday, October 29, 1985 9:00 a.m.
Plant tour and discussions with operating and maintenance personnel 12:00 p.m.
Lunch 1:00 p.m.
Discussion Organization and staffing - NNEC0 Operational experience / personnel qualifications - NNEC0 Training - NNEC0 Operational Readiness - NNECO Selected Technical Issues Engineering Assurance Program Quality Assurance Operation Program Implementation Technical Specifications Employee Information Program Probabilistic Safety Study 3:30 p.m.
Concluding remarks by NNECO and NRC 4:00 p.m.
Meeting adjourned
Pr. J. F. Opeka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. 3 cc:
Gerald Garfield, Esq.
Ms. Jane Spector Day, Berry & Howard Federal Energy Regulatory Commission City Place 825 N. Capf_to1* Street, NE Hartford, Connecticut 06103-3499 Room 8608C Washington, D.C.
P0426 Mr. Maurice R. Scully, Executive Director Connecticut Municipal Electric Energy Cooperative 268 Thomas Road Groton, Connecticut 06340 Robert W. Bishop, Esq.
Corporate Secretary Northeast Utilities Post Office Box 270 Hartford, Connecticut 06141 Mr. T. Rebelowski Senior Resident Inspector Office U. S. Nuclear Regulatory Commission Millstone III P. O. Box 615 Waterford, Connecticut 06385 Mr. Michael L. Jones, Manager Project Management Departnent Massachusetts Municipal Wholesale Electric Company Post Office Box 426 Ludlow, Massachusetts 01056 Regional Administrator U. S. NRC, Region I 651 Park Avenue King of Prussia, Pennsylvania 19406 Mr. Karl Abraham Public Affairs Office, Region I U. S. Nuclear Regulatory Commission, King of Prussia, Pennsylvania 19406 l
MEETING NOTICE DISTRIBUTION OCT 3 41985 fDock'tFile.
NRC Participants e
NRC POR L PDR H. Thomoson NSIC J. TAvlor PRC System
!1. Russell LB!1 Reading File J. Kniaht M. Rushbrook L. Pubenstein E
L. Doolittle Project Managcr A. Thadani H. Denton/D. Eisenhut B. J. Younablood H. Thompson /F. Miraglia E. L. Doolittle T. Novak V. S. Noonan W. Butler S. Black G. Knighton E. Adensam C. Thomas M. Virgilio J. Zwolinski C. Grimes G. Holahan G. Lainas S. Varga D. Vassallo E. Butcher, Actir.g bec: Applicant & Service List J. Stolz T. Speis F. Schroeder F. Rowsome Acting Director /DE J. P. Knight W. Johnston R. Bernero W. Houston L. Rubenstein D. Muller Acting Director /DHFS W. Russell J. Partlow B. Grimes E. Jordan F. Ingram ACRS (16)
Attorney, OELD Receptionist (If mtg is held in Bethesda) i
--