ML20138L022

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Repts 50-282/85-15 & 50-306/85-12.Corrective Actions:Program of Steam Generator Snubber Insp & Testing Underway,Ler Procedures Implemented & Westinghouse Reviewing Specs
ML20138L022
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 10/18/1985
From: Larsen C
NORTHERN STATES POWER CO.
To: Harrison J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 8510310137
Download: ML20138L022 (2)


Text

,

2 o

Northem States Power Company 414 Nicollet MaH Minneapohs Minnesota 55401 Telephone (612) 330-5500 October 18, 1985 J J Harrison, Chief Engineering Branch U S Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 In response to your letter of September 20, 1985, concerning Inspection Reports No. 50-282/85015 (DRS) and 50-306/85012 (DRS), the following information is offered related to the two noncompliance items cited in the report.

Violation 10 CFR 50, Appendix B, Criterion XVI, as implemented by Northern States Power Company Corporate Nuclear Administrative Control Directives, Section 10, requires conditions adverse to quality such as deficiencies, defective materials, and deviations be corrected.

In the case of a significant adverse condition, the cause of the condition shall be determinec and corrective action taken to preclude repetition.

Contrary to the above, after identifying a seal leak and fluid contamination in a steam generator snubber (SGS), the licensee did not investigate the cause of seal deterioration and fluid contamination.

In addition, the licensee did not perform tests on the other SGSs to assure operability and to identify the possible worst case condition.

This is a Severity level IV violation (Supplement II).

Response

A program of steam generator snubber inspection and testing is underway as described in our letters of September 16, 1985 and October 16, 1985.

This program is intended to fully resolve all potential conditions adverse to quality related to these components.

All 16 of the steam generator snubbers of this design are or will be tested.

Eight of the 16 are installed in Unit No. 2 and were tested during the current refueling outage.

No conditions adverse to quality, such as defective materials, were found in these snubbers. Analysis of snubber seal material and hydraulic fluid is not complete, however.

The eight snubber in Unit No. I will be tested during the spring 1986 refueling outage, gjo3 37 G51018 g

a x o500o2o2 r00T211985 @

pon M 8M/

J.J Harriecn, NRC, R III

- 18, 1985

'

  • October

'Page 2 Violation

=10 CFR'50.73 requires the licensee to submit a Licensee Event Report (LER)~within 30 days after discovery of condition that resulted in the nuclear power ~ plant being seriously degrade'd, or that resulted in the nuclear power plant being in an unanalyzed-condition that significantly compromised plant safety, or in a condition that was outside the design basis of the plant.

Contrary to the above, the licensee failed to submit LERs documenting (1) the identified seal leak and fluid contamination problem, (2)

that.the SGS. control valves were replaced to avoid possible piping overstress, and (3) that a Westinghouse calculation indicated a SGS load significantly greater than the original design value (282/85015-02A, B, and C; 306/85012-02A, B, and C).

Response

Procedures are now in place which require Licensee Event Reports to be made in accordance with.the requirements of 10 CFR Part 50, Section 50.73.

Westinghouse is reviewing the snubber design specifications and design load calculations. We believe these actions fully address the concern

identified in the violation. A followup report will be made when this work is completed.

As noted above, portions of our investigation are continuing. This work is expected to be completed by December 31, 1985.

'A supplemental response will be provided to you at that time.

Please contact us if you have any questions related to the information we have provided or our schedule for providing a supplemental response.

m C E Larson Vice President Nuclear Generation c: Regional Administrator-III, NRC NRC Resident. Inspector G Charnoff 1

O b