Forwards Response to Sqrt Confirmatory Issue 1 Re Completion of Design Change Packages Which Implement Installation of Hydraulic Control Unit Piping Supports
ML20138J763
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 12/16/1985
From: Corbin McNeil
Public Service Enterprise Group
To: Adensam E
Office of Nuclear Reactor Regulation
References
NUDOCS 8512180026
Download: ML20138J763 (3)


Text

m w-Public Service Electric ar'd Gas Company Corbin A. McNeill, Jr.

Public Service Electric and Gas Company P.O. Box 236, Hancocks Bndge.tlJ 08038 609339-4800 Vice President -

Nuclear December 16, 1985 Director of Nuclear Reactor Regulation United States Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20814 Attention:

Ms. Elinor Adensam, Director Project Directorate 3 Division of BWR Licensing

Dear Ms. Adensam:

RESPONSE TO SQRT CONFIRMATORY ISSUE 1 HOPE CREEK GENERATING STATION DOCKET NO. 50-354 Pursuant to the NRC, PVORT/SQRT audit held at the Hope Creek Generating Station on May 7-10, 1985 and HCGS SER Supplement 3, Section 3.10.1.6, Public Service Electric and Gas Company hereby submits the attached response to SQRT Confirmatory Issue 1 regarding completion of design change packages which implement installation of HCU piping supports.

This submittal completes our responses required for action items identified at the PVORT/SQRT audit regarding Seismic and Dynamic Qualification.

Should you have any questions in this regard, please contact us.

Sincerely, m

i po 85 21 g g $$0 0354 EB (LIAW) l l

P PDR PsB (L. HuLMAn) b

  • EICSB (SRINIVASAN)

' RSB (ACTING)

FOB (VASSALLO)

AD - G. LAINAS (Ltr only)

m Director of Nuclear 2

12-16-85 Reactor Regulation Attachment C

D.II. Wagner USNRC Licensing Project Manager R.W.

Borchardt USNRC Senior Resident Inspector J.

Singh EG&G Idaho, Inc.

+

t -

ATTACHMENT SQRT CONFIRMATORY ISSUE -REGARDING INSTALLATION OF HCU PIPING SUPPORTS Issuance of Design Change Packages'7427 and 7429 through 7432 which implement installation of HCU piping supports was indicated previously in' letter; R.L.-Mittl to W.. Butler,

.-dated August.16, 1985 as Attachment I.

Construction installation per the DCPs-indicated above has.been 100% completed.