ML20138C160

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Sept 1985
ML20138C160
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 09/30/1985
From: Hutchison L, Powers C
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
NUDOCS 8512120486
Download: ML20138C160 (4)


Text

-_

g, .. .

OPERATING DATA REPORT WNP-2 01-Oct-85

1. DOCKET: 50-397

,2, REoORTING PERIOD: Sep-85 OUTAGE +0N-LINE HOURS 720

3. UTILITY CONTACT: LEONARD HUTCHISON (509) 377-2486
4. LICENSED THERMAL POWER (MWt): 3323
5. NAMEPLATE RATING (GROSS MWe): 1200.1
6. DESIGN ELECTRICAL RATING (NET MWe): 1100
7. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe): 1140
8. MAXIMUM DEPENDABLE CAPACITY (NET MWe): 1O95

,7 . IF CHANGES OCCUR ABOVE SINCE LAST REPORT, GIVE REASONS:

c! _ ____ __- - - - - . . - - - __________- _-

- =

. _ _ _ _ _ _ _ - - -____-_ .______-- =-_ =___________

=- = _== _______________ =_ - _ _ -

10. POWER TO WHICH RESTRICTED, IF ANY (NET MWe): _8,00 MWe NET

' .1 1. REASONS FOR RESTRICTIONS, IF ANY: __ "B"_ RRC_PU_MP INOPERABLE ______ _ ___ ___

- - - - __===_ _ _____ .---_- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - - - --

________________- ________==:- -_____

MONTH YEAR CUMULATIVE

12. REPORT PERIOD HOURS 720 6551 6991.2
13. HOURS REACTOR CRITICAL 720.0 4791.0 5207.5
14. RX RESERVE SHTDWN HRS O.0 O. O
  • O. O *
15. HRS GENERATOR ON LINE 720.0 4545.0 4943.4
16. UNIT RESERVE SHUTDOWN HOURS 0.0 0. O
  • O. O *
17. GROSS THERMAL ENERGY (MWH) 1719360 11446903 12660531
10. GROSS ELECTRICAL ENERGY (MWH) 581190 3780790 4207720
19. NET ELECTRICAL ENERGY (MWH) 557204 3623263 4033649
20. UNIT SERVICE FACTOR 100.0% 69.4% 70.7%

2i. UNIT AVAILABILITY FACTOR 100.0% 69.4%* 70.7%*

22. UNIT CAPACITY FACTOR (MDC NET) 70.7% 50.5% 52.7%
23. UNIT CAPACITY FACTOR (DER NET) 70.4% 50.3% 52.5%

24 UNIT FORCED OUTAGE RATE O.0% 12.2% 12.0%

25. FORCED OUTAGE HOURS O.0 630.9 672.6
26. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE,DATE, DURATION):

FAUiTENANCE OUTAGE _10L1_5 FOR 2_ DAYS _____ _____ ___

=- -

. = - - ._______- _ _ _ - _=- -= .- -- _______

27. IF CURRENTLY SHUTDOWN ESTIMATED STARTUP DATE:
  • THE RESERVE SHUTDOWN HOURS WHICH WERE CREDITED TO THE MAY 1985 AND JUNE 1985 REPORTS (1046.9 HRS RX RESERVE SHUTDOWN AND 1029.9 HRS UNIT RESERVE SHUTDOWN)

HAVE BEEN DELETED AND THE TIME CHARGED AS OUTAGE HOURS. }

8512120486 850930 PDR R ADOCK 05000397 g(

PDR

AVERAGE DAILY UNIT POWER LEVEL DOCKET No, 50-397 .

UNIT WNP42 DATE 10/1/85 COMPLETED BY L.B. HUTCHISON TELEPHONE (509)377-2486 SEPTEMBER 1985 MONTri DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE D II,y p PGR LEVEL (MWe-Ner) 17 778 2 775 777 18 3,

774 19 780

~

4 767 777 20 764 5

21 774 771 6 781 22 778 7

23 731 .

s 778 24 775 9 776 25 778 to 776 775 25 11 775

" 27 774 12 775 781 2e 13 771 785 23-14 771 777 20

'S 778 31 16 __ 773 INSTRUCTIONS

'I' n $: s ,$'n e a.: 2 Y u It p wer level ir. Mwe.x,2 for esch hy b dle repor:fng mondi.Ccmpute to :he Tme S ture: v.H be :ed r ma

, e ,', [,n* 'e mum dependable apac;tyis

-e ia e, ),

e at t. e  : p o.- , %so.e ,m.,en, a,.c,, ,,.

we==.eeem;emya,,gegj;je;ese.x;e-d,se ,,

DOCKET t10. _

50-397 U11'T NAl1E WNP-2  : '

DATE in/1/as U1IT SIUTDowf1S / REDUCTIONS C0f.iPLETED BY L.B. HUTCHISON REITRT PERIOD ' SEPT 19 85 TELEPfl0NE (509)377-2486 month, yEr No. IIXTE TYPE TUDIS ItEASON METHW LEll tot 0ER SYS~lLH COMPONEfff CAUSE & CORRECTIVE ACTION TO filEVENT RECURRENG 85-02P 7/1/85' F 0 A 5 -

CB PUMPXX POWER OUTPUT LIMITED TO 73% (APPR0XD1ATELY 800 MWe NET) DUE TO Ifl0PERABILITY OF "B" RRC PUMP t

i I .

l SUfftARY l WNP-2 OPERATED AT A REDUCED POWER LEVEL DURING THE ENTIRE fiONTH WITH NO SfiUTDOWilS. ,

TYPE REASON METil0D SYSTEM & COMP 0fENT F-Forced A-Equip Failure . F-Admin 14fanual Exhibit F & H ,

S-Sched 0-Maint or Test G-Oper Error' 24fanual Scram Instructions for .

. C-Refueling H-Other 3-Auto Scram Preparation'of D-Regulatory Restriction 4-Continued Data Entry Sheet E-Operator Training 5-Reduced Load Licensee Event Report

& License Examination 9-0.ther (LER) File (tUREG-0161)

O Washington Public Power Supply System 3000 George Washington Way P.O. Box 968 Richland, Washington 99352-0968 (509)372-5000 October 4, 1985 Docket No. 50-397 Director Office of Resource Management U.S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Sir:

Subject:

NUCLEAR PLANT NO. 2 MONTHLY OPERATING REPORT Transmitted herewith is the Monthly Operating Report for September 1985 as required by our Technical Specifications 6.9.1.6.

Very truly yours, 8[ft Acws C. M. Powers (M/D 927M)

WNP-2 Plant Manager CMP /lc Enclosure cc: Mr. John B. Martin - NRC, Region V Mr. A. D. Toth -

WNP-2 Site Ms. Dottie Sherman - ANI, Fannington CT l