Forwards Grand Gulf Nuclear Station Pre-SALP Rept for SALP Period 960225-970906, Which Provides Results of Integrated Review
ML20138A197
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 04/23/1997
From: Hughey W
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20138A201 List:
References
GNRO-97-00033, GNRO-97-33, NUDOCS 9704280016
Download: ML20138A197 (2)


Text

_

O Enti erations, inc.

Port Gibson, MS 39150 Tol 601437-6470 April 23,1997 W.K.Hughey D' rect (y Nuclear Safety & Reg 4 story Affans U.S. Nuclear Regulatory Commission Mail Station P1-137 Washington, D.C. 20555 Attention:

Document Control Desk

SUBJECT:

Grand Gulf Nuclear Station Unit 1 I

Docket No. 50-416 License No. NPF-29 1996-1997 Pre-SALP Assessment GNRO-97/00033 Gentlemen:

The NRC SALP process provides Grand Gulf with a convenient opportunity to perform a retrospective review of overall site performance. While it is Grand Gulf policy to continually conduct self-assessments focused along departmental and functional lines, we have traditionally reserved the period at the end of a SALP cycle to perform an integrated review.

The enclosed report provides the results of just such an integrated review. The information contained within this report provides the basis for the April 24,1997 1

presentation to the Region IV staff. However, it is extremely difficult in a two hour presentation to adequately cover all the initiatives that are either underway or recently completed at Grand Gulf during our current SALP period. Thus, this report i

provides us with an additional opportunity to share with the NRC the many performance' initiatives underway at Grand Gulf.

We believe it is appropriate to provide the NRC with a broader information base than may be available through inspection Reports and other docketed correspondence.

We hope you will find the enclosed useful and informative.

Yours truly, j

G0093 fMO !

2' M ll ll ll I.ll.Il.l11. l.l CAB /TMC attachment:

GGNS Pre-SALP Assessment cc:

(See Next Page) 9704200016 970423 PDR ADOCK 05000416' G

PDR

)

GNRO-97/00033 i

Page 2 of 3 cc:

Ms. K. Weaver (w/a) i Mr. E. W. Merschoff (w/a)

Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive Suite 400 Arlington, TX 76011 Mr. Jack Donohew, Project Manager (w/a)

Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 13H3 Washington, D.C. 20555 l