Forwards Projected Milestones Remaining for Singer Link Replica Simulator Project,Indicating Delivery by Aug 1986. Initial Simulator Training Lesson Plans Will Be Developed by Delivery Date
ML20137Y728
Person / Time
Site: Crane Constellation icon.png
Issue date: 10/03/1985
From: Hukill H
GENERAL PUBLIC UTILITIES CORP.
To: Stolz J
Office of Nuclear Reactor Regulation
References
5211-85-2159, NUDOCS 8510080078
Download: ML20137Y728 (2)


Text

GPU huclear Corporation NggIgf Post Office Box 480 Route 441 South Middletown, Pennsylvania 17057-0191 717 944 7621 TELEX 84 2386 Writer's Direct Dial Number October 3 1985 5211-85-2159 Office of Nuclear Reactor Regulation Atd : John F. Stolz, Chief Operu'ing Reactors Branch No. 4 U.S Nuclear Regulatory Commission Washington, D. C. 20555

Dear Mr. Stolz:

Three Mile Island Nuclear Station Unit 1 (TMI-1)

Operating Licer.se No. DPR-50 Docket No. 50-289 Replica Simulator Status Update In our special status report of July 19, 1985 GPUN indicated that the Singer Link replica simulator delivery was delayed to the second quarter of 1986.

Enclosed please find a copy of the GPUN projected milestones remaining for this project which indicate that the optimistic schedule for training on the simulator to begin is August 1986.

Please note that GPUN is currently working with Singer Link to minimize or avert, if possible, further schedule delays.

GPUN will have a full complement of staff and will have developed initial simulator training lesson plans by the revised delivery date.

The new building being constructed to house the simulator will be completed in October 1985.

Sincerely, H. D.

1 kill 8510080078Byhg9 PDR ADOCK O PDR

.iDH:gpa p

r 2400f/001 0

Attachment

,0

' I cc: R. Conte J. Thoma Reference a) GPUN Letter (5211-84-2243) dated 10/01/84 GPU Nuc) lear Corporation (is a subsidiary of the Gener/lyublic Utilities Corporation b GPUN Letter 5211-85-2129) dated 07 85 al

3 MILESTONES FOR REPLICA SIMULATOR OPERATION OPTIMISTIC MILESTONE ESTIMATED SCHEDULE Started Integrated Factory Acceptance

  • August 30, 1985 Test (Duration 34 weeks)

Complete Integrated Factory Acceptance April 30, 1986 Test Teardown Pack Ship and Install June 15, 1986 Replica Simulator at TMI-l (Duration 6 weeks)

Start Site Acceptance Test June 15, 1986 (Duration 6 weeks)

Complete Site Acceptance Test July 20, 1986 Ready for Use August 1, 1986

  • This testing program consists of 2 fixed time intervals of approximately 17 weeks which cannot be compressed to recover schedule.