Ack Receipt of 850515 Comments on Fes for Facilities. Complaints Re Noise Along High Voltage Transmission Line & Actions Taken Re Complaints Should Be Reported to NRC
ML20137V692
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/25/1985
From: Adensam E
Office of Nuclear Reactor Regulation
To: Scott Moore
ENVIRONMENTAL PROTECTION AGENCY
References
NUDOCS 8510040105
Download: ML20137V692 (1)


Text

-- . _ _ - ~.

September 25, 1985 Docket Nos: 50-424 . DISTRIBUTION:

and 50-425 . Docket File NRC POR Mr. Sheppard N. Moore, Chief Local PDR NEPA Review Staff PRC System Environmental Assessment Branch NSIC U.S. Environmental Protection Agency LB#4 r/f Region IV MDuncan 345 Courtland Street MMiller Atlanta, Georgia 30365 OELD, Attorney ACRS (16)

Dear Mr. Moore:

JPartlow

, BGrimes EJordan j Thank you for your letter of May 15 commenting on the FES for the Vogtle Electric Generating Plant. The FES constitutes the NRC " Record of Decision."

Since the environmental impact is not an issue before the Licensing Board, no further environmental pronouncement will be forthcoming. Therefore, I would like to respond to your comments.

During NRC's environmental review process, the Ebenezer Creek crossing has received the attention of several Federal and state agencies. As a result of input from these agencies, Georgia Power Company has redesigned the segment of i the transmission line in the vicinity of the Creek and has committed to employ construction practices which will minimize potential harm to the area. Although I believe they have considered the alternatives you provided in your May 15 letter, I am forwarding a copy of your letter to them to further emphasize the value niaced on these natural resources.

We also appreciate the spirit in which the noise comments are offered. In assessing the impact of noise, guidance documents developed by EPA were considered by the NRC staff. The assessment indicated that noise at the

predicted level will not cause physical damage, but may constitute an annoyance.

Therefore, we are requiring that Georgia Power Company report actual complaints regarding noise along the high voltage transmission line as well as the action

, it took in response to each complaint. Any additional staff requirements would l then be assessed as necessary.

4 Your interest in this project has been helpful.

Sincerely, I

24 Elinor Adensam, Chief 85100goh05e 0 DR Licensing Branch No. 4 PDR Division of Licensing D Offi of Nuclear Reactor Regulation J [4 LA:DLhlB#4 DL':LB #4 ff F er/ah MDUMan EAdensam /ksa/EHEB mworth j 5 /85 9/A/85 9/.74/85 9////85 DESICrf.23 CI?ICIr/l, j Certifial py

/

,.