Mr. Neil S. Carns Senior Vice President April 15, 1997 and Chief Nuclear Officer Northeast Nuclear Energy Company c/o Mr. Richard T. Laudenat Director - Regulatory Affairs P. O. Box 128 Waterford, CT 06385
SUBJECT:
MILLSTONE NUCLEAR POWER STATION, UNIT 1 - ISSUANCE OF AMENDMENT ON DELETION OF INTEGRATED IMPLEMENTATION SCHEDULE LICENSE CONDITION (TAC N0. M96607)
Dear Mr. Carns:
The Commission has issued the enclosed Amendment No.100 to Facility Operating License No. DPR-21 for the Millstone Nuclear Power Station, Unit 1, in response to your application dated September 5, 1996.
The amendment deletes License Condition 2.C.(5), " Integrated Implementation Schedule" from the Millstone Unit 1 Operating License.
A copy of the related Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commission's biweekly Federal Reaister notice.
Sincer ly,,.
N
d Stephen Dembek, Project Manager Special Projects Office - Licensing Office of Nuclear Reactor Regulation Docket No. 50-245
Enclosures:
1.
Amendment No.100 to DPR-21 2.
Safety Evaluation cc w/encls:
See next page DISTRIBUTION:
Docket File PUBLIC SP0-L Plant SP0 Reading PMcKee 80' NRg RE CUgm espy ACRS OGC Dl,I GHill (2)
CGrimes JDurr, RI DOCUMENT NAME:
G:\\DEMBEK\\M96607.AMD
- see previous concurrence To ricdve a copy of this document, Indicate in the boa: "C" = Copy without attachtnant/ enclosure "E" = Copy with,attaght ient/ enclosure
- N" = No copy 0FFICE SPO-L:PM_
l SPO-L: LAM'l 6 OGC*
l SPp-MO l
l NAME SDembek//b/R LBerry i(/
MYoung PHLKee DATE 04//c/97 04/0/97 04/10/97 04/it /97 04/ /97 0FFICIAL RECORD COPY 9704170330 970415 PDR ADOCK 05000245 P
PDR c
carg
- }(
1 UNITED STATES s
j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 3066H001 8
%,..... j April 15,1997 Mr. Neil S. Carns Senior Vice President 3
and Chief Nuclear Officer Northeast Nuclear Energy Company a
c/o Mr. Richard T. Laudenat Director - Regulatory Affairs P. O. Box 128 Waterford, CT 06385
SUBJECT:
MILLSTONE NUCLEAR POWER STATION, UNIT 1 - ISSUANCE OF AMENDMENT ON DELETION OF INTEGRATED IMPLEMENTATION SCHEDULE LICENSE CONDITION (TAC NO. M96607)
Dear Mr. Carns:
The Commission has issued the enclosed Amendment No.100 to Facility Operating License No. DPR-21 for the Millstone Nuclear Power Station, Unit 1, in response to your application dated September 5,1996.
The amendment deletes License Condition 2.C.(5), " Integrated Implementation Schedule" from the Millstone Unit 1 Operating License.
A copy of the related Safety Evaluation is also enclosed.
Notice of Issuance will be included in the Commission's biweekly Federal Reaister notice.
Sincerely, l
y Stephen Dembek, Project Manager Special Projects Office - Licensing Office of Nuclear Reactor Regulation Docket No. 50-245
Enclosures:
1.
Amendment No.100 to DPR-21 2.
Safety Evaluation cc w/encis: See next page
\\
Northeast Nuclear Energy Company Millstone Nuclear Power Station,
Unit 1 cc:
i Lillian M. Cuoco, Esquire Mr. Wayne D. Lanning Senior Nuclear Counsel Deputy Director of Inspections Northeast Utilities Service Company Special Projects Office P. O. Box 270 475 Allendale Road Hartford, CT 06141-0270 King of Prussia, PA 19406-1415 Mr. Kevin T. A. McCarthy, Director Mr. F. C. Rothen Monitoring and Radiation Division Vice President - Nuclear Work Department of Environmental Services Protection Northeast Nuclear Energy Company 79 Elm Street P. O. Box 128 Hartford, CT 06106-5127
~Waterford, CT 06385 4
Mr. Allan Johanson, Assistant Ernest C. Hadley, Esquire Director 1040 B Main Street Office of Policy and Management P. O. Box 549 Policy Development and Planning West Wareham, MA 02576 Division 450 Capitol Avenue - MS# 52ERN Mr. John Buckingham P. O. Box 341441 Department of Public Utility Control Hartford, CT 06134-1441 Electric Unit 10 Liberty Square Regional Administrator New Britain, CT 06051 J
Region I U.S. Nuclear Regulatory Commission Mr. J. K. Thayer 475 Allendale Road Recovery Officer - Nuclear i
King of Prussia, PA 19406 Engineering and Support
~
Northeast Nuclear Energy Company First Selectmen P. O. Box 128 Town of Waterford Waterford, CT 06385 i
Hall of Records-200 Boston Post Road Mr. B. D. Kenyon Waterford, CT 06385 President and Chief Executive Officer Mr. D. M. Goebel Northeast Nuclear Energy Company Vice President - Nuclear Oversight P. O. Box 128 Northeast Nuclear Energy Company Waterford, Connecticut 06385 P. O. Box 128 Waterford, CT 06385 Senior Resident Inspector Millstone Nuclear Power Station Mr. J. McElwain c/o U.S. Nuclear Regulatory Millstone Unit No. 1 Nuclear Commission Recovery Officer P.O. Box 513 Northeast Nuclear Energy Company Niantic, CT 06357 P. O. Box 128 Waterford, CT 06385
Northeast Nuclear Energy Company Millstone Nuclear Power Station Unit 1 CC:
The Honorable Terry Concannon Mr. Evan Woolacott Co-Chairs Nuclear Energy Advisory Council Room 4035
. Legislative Office Building
. Capitol Avenue l
Hartford, Connecticut 06106 Citizens Regulatory Commission ATTN: Ms. Susan Perry Luxton 180 Great Neck Road Waterford, Connecticut 06385 Deborah Katz, President Citizens Awareness Network P. O. Box 83 Shelburne Falls, MA 03170 e