{{#Wiki_filter:- ~. l Limstick GanIrating Station A _y PECO NUCLEAR eeco ree,2vcomneev Po Box 2300 A UNIT Or PECO ENtucy Sanatoga. PA 19464-o020 T.S.6.9.1.6 j 1 s April 9,1997 l Docket Nos. 50-352 50-353 License Nos. NPF-39 NPF-85 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Subject; Limerick Generating Station Monthly Operating Report For Units 1 and 2 0 Enclosed are the monthly operating reports for Limerick Units 1 and 2 for the month of March 1997 forwarded pursuant to Technical Specification 6.9.1.6. s Very truly yours, j h[ 4 Edward F. Sproat, III Director - Site Engineering bec Enclosures I cc: H. J. Miller, Administrator, Region I, USNRC N. S. Perry, USNRC Senior Resident Inspector LGS h 'g + W. G MacFarland, Vice President, LGS 9704160102 970331 .g PDR ADOCK 05000352 ~ ] p PDR @,E5EU.N.E.ISE
. _.. _. ~. _. Dock 1t No. 50-352 1 Attichmant to Monthly Operating Report for March 1997 Limerick Generating Station Unit 1 March 1 through March 31,1997 4 ' l. Narrative Summary of Operatina Experiences Unit i began the month of March 1997 at a nominal 100% of rated thermal power (RTP). i On March 1,1997 at 0303 hours, power was reduced to 98% of RTP for main turbine valve testing. Power was restored to 100% RTP at 0351 hours. 4 On March 7,1997 at 2210 hours, power was reduced to 98% of RTP for main turbine l valve testing. Power was restored to 100% RTP at 2318 hours. t On March 14,1997 at 2300 hours, power was reduced to 98% of RTP for main turbine j - valve testing. Powerwas restored to 100% RTP at 2318 hours. .\\ l On March 21,1997 at 2300 hours, power was reduced to 92% of RTP for main turbine valta testing. Power was restored to 100% RTP on March 22,1997 at 0110 hours. t On March 28,1997 at 2200 hours, power was reduced to 98% of RTP for main turbine ) valve testing. Power was restored to 100% RTP on March 28 at 2300 hours. Unit 1 ended this month operating at 100% RTP. i t li. Challenoes to Main Steam Safety Relief Valves } There were no challenges to the Main Steam Safety Relief Valves during the month of March. V
.m AVERAGE DAILY POWER LEVEL DOCKET NO. 50-352 UNIT LIMERICKUNIT1 DATE APRIL 9,1997 3 COMPANY PECO ENERGY COMPANY BRUCE E. CANFIELD f REPORTS Ei4GINEER SITE ENGINEERING LIMERICK GENERATING STATION TELEPHONE (610)718-3794 L10 NTH MARCH,1997 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-NET) (MWE-NET) 1 1115 17 1119 2 1110 18 1115 3 1119 19 1115 4 1119 20 1115 5 1119 21 1107 r 6 1115 22 1103 1 7 1123 23 1116 8 1115 24 1120 1 9 1119 25 1112 10 1119 26 1103 i l 11 1119 27 1102 12 1123 28 1090 y 13 1119 29 1095 5 14 1119 30 1096 6 15 1118 31 1101 16 1123 s I i
OPERATING DATA REPORT DOCKET NO. 50- 352 DATE APRIL 9,1997 COMPLETED BY PECO ENERGY COMPANY BRUCE E. CANFIELD REPORTS ENGINEER SITE ENGINEERING ~ LIMERICK GENERATING STATION i TELEPHONE (610)718 3794 i OPERATING STATUS
- 1. UNIT NAME:
L. I.M..ER.I.C..K UN.._IT 1..
- 2. REPORTING PER!OD:
MA,R_CH,1997_ GREATER THAN 20% THIS MONTH.
- 3. LICENSED THERMAL POWER (MWT):-
3456
- 4. NAMEPLATE RATING (GROSS MWE):
1100
- 5. DESIGN ELECTRICAL RATING (NET MWE):
1105
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):
1145
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):
1105
- 8. IF CHANGES OCCUR IN CAPAChY RATINGS (ITEMS 3 THROUGH 7 ) SINCE LAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED,:F ANY(NET MWE):
- 10. REASONS FOR RESTRICTIONS,IF ANY:
[ THIS MONTH YR-TO-DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 744 2.160 97,848
- 12. NUMBER OF HOURS REACTOR WAS CRillCAL 744.0 2,160.0 82,287.4
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 14. HOURS GENERATOR ON-LINE 744.0 2,160.0 80,920.0
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 2,570,899 7,462,708 253,216,871
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 854,300 2,488,800 82,560,380
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 828,168 2,409.513 79,342,610 s
PAGE 10F 2 =
OPERATING DATA REPORT (CONTINUED) DOCKET NO. 50 -352 .DATE. APRIL 9,1997 THIS MONTH YR-TO-DATE CUMULATIVE
- 19. UNIT SERVICE FACTOR 100.0 %
100.0 % 82,7 %
- 20. UNIT AVAILABILITY FACTOR '
100.0 % 100.0 % 82.7 %
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 100.7 %
101.0 % 76.4 %
- 22. UNIT CAPACITY FACTOR (USING DER NET) 100.7 %
101.0 % 76.4 % .0% .0 % 4.1 %
- 23. UNIT FORCED OUTAGE RATE
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
PLANNED MAINT OUTAGE,4/11/97, SCHEDULED 2 DAY DURATION
- 25. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):
FORECAST ACHIEVED INITIAL CRITICALITY 12/19/84 12/22/84 INITIAL ELECTRICITY mfd APRIL 85 04/13/85 COMMERCIAL OPERATION 1ST QTR 86 0201/86 i t PAGE 2 OF 2
UNIT SHUTDOWNS AND POWER REDUCTIONS i DOCKET NO. 50-352 l UNITNAME UMERICKUNIT1 DATE APRIL 9.1997 - r COMPLETED BY PECO ENERGY COMPANY BRUCE E. CANFIELD REPORTS ENGINEER SITE ENGINEERING L UMERICK GENERATING STATION [ REPORT MONTH MARCH,1997 TELEPHONE (610)718-3794 i METHOD OF UCENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN EVENT CODE CODE ACTION TO NO. DATE (1) (HOURS) (2) REACTOR (3) REPORT # (4) (5) PREVENT RECURRENCE 181 970301 S 1.0 8 4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 98% DUE TO MAIN TURBINE VALVE TESTING. 182-970307 S 1.0 B 4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 90% DUE TO MAIN TURBINE VALVE TESTING. j 183 970314 S 1.0 B 4 N/A HA VALVEX . REACTOR POWER WAS REDUCED TO 98% DUE TO MAIN TURBINE VALVE TESTING. 184 970321 S 2.0 B 4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 92% DUE TO f MAIN TURBlNE VALVE TESTING 185 970329 S 1.0 B 4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 98% DUE TO MAIN TURBINE VALVE TESTING TOTAL HOURS 6.0 ( t i 'f f (1) (2) (3) (4) f F-FORCED REASON METHOD EXHIBIT G-INSTRUCTIONS S-SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST 2.MANUALSCRAM ENTRY SHEETS FOR LICENSEE C-REFUELING 3-AUTOMATIC SCRAM EVENT REPORT (LER) l D-REGULATORY RESTRICTION 4-OTHER (EXPLAIN) FILE (NUREG-0161) E - OPERATOR TRAINING + LICENSE EXAMINATION 1 F-ADMINISTRATIVE (5) G-OPERATIONAL ERROR (EXPLAIN) EXHIBIT 1-SAME SOURCE H - OTHER (EXPLAIN)
'l Dock:t No. 50-353 Attichmint to Monthly Operating Report for j March 1997 4 j Limerick Generating Station L Unit 2 March 1 through March 28,1997 i - 1. Narrative Summary of Operatina Experiences i 1 i Unit 2 began the month of March 1997 at 25% rated thermal power (RTP) in power ascension from a refueling outage. On March 3,1997 Power was restored to 100% RTP at 1509 hours. On March 4,1997 at 2025 hours, power was reduced to 65% of RTP due to a feedwater heat exchangerleak. Powerwas restored to 100% RTP on March 7,1997 at 0044 hours. On March 8,1997 at 2214 hours, power was reduced to 88% of RTP for main turbine valve testing. Power was restored to 100% RTP on March 9, at 0059 hours. t i On March 15,1997 at 1345 hours, power was reduced to 98% of RTP for main turbine valve j testing. Power was restored to 100% RTP at 1428 hours. 3 On March 23,1997 at 0740 hours, power was reduced to 85% of RTP due to a main transformer high combustible gas reading. Powerwas restored to 100% RTP on March 24, at 0120 hours. l On March 27,1997 at 1436 hours, power was reduced to 86% of RTP due to tuibine generator i excitor alterex in contact with its bearing. Unit 2 ended this operating penod at 22% of RTP. 3 II. Challenaes to Main Steam Safety Relief Valves There were no challenges to the Main Steam Safety Relief Valves during the month of March. (
.-. ~ AVERAGE DAILY POWER LEVEL. DOCKET NO, 50-353 ' UNIT LIMERICK UNIT 2 - DATE APRIL 9,1997 ~ COMPANY PECO ENERGYCOMPANY BRUCE E. CANFIELD - REPORTS ENGINEER SITE ENGINEERING LIMERICK GENERATING STATION TELEPHONE (610)718-3794 -( MONTH MARCH,1997 - t DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-NET) (MWE-NET) 1 309 17 1130 2 686 18 1'30 3 1075 19 1134 4 1044 20 1125 5 901 21 1120 ~ 6 961 22 935 7 1140 23 1021 8 1123 24 1131 9 1135 25 1131 i 10 1135 26 1110 11 1130 27 1004 L 12 1138 28 775 .i 13 1138 29 792 ~ i 14 1129 30 771 t 15 1132 31 0 i 16 1138 l b ...w w .. -.- n a e -
~. OPERATING DATA REPORT DOCKET NO. 50 -3S3 DATE APR!L 9,1997 COMPLETED BY PEC 3 ENERGY CCMPANY i"!UCE E. CANFIELD REPORTS ENGINEER SITE ENGINEERING LIMERICK GENERATING STATION TELEPHONE (610)718-3794 OPERATING STATUS
- 1. UNIT NAME-LIMERICK UNIT 2 NOTES: THERE WERE 2 LOAD DROPS
- 2. REPORTING PERIOD:
MA.RCH,1997 GREATER THAN 20% THIS MONTH
- 3. LICENSED THERMAL POWER (MWT):
_ _3458 DUE TO RECIRC PUMP 4 NAMEPLATE RATING (GROSS MWE): ..._.1163 VIBRATIONSB FEEDWATER HTR
- 5. DESIGN ELECTRICAL RATING (NET MWE):
1115 LEAK AND TURB GEN ALTEREX
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): __
11_55 BEARING
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):
1115
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
IN CONTACT WITH ITS
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE):
'c. REASON 5 FOR RESTRICTIONS,IF ANY: i THIS MONTH YR-TO-DATE CUMULATIVE
- 91. HOURS IN REPORTING PERIOD 744 2,160 63,360
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 1,519.8 57,547.0
- 13. REACTOR RESER'E SHUTDOWN HOURS OO O.0 0.0
- 14. HOURS GENERATOR ON-LINE 720.0 1,447.6 56,386.7
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 2.256,453 4,240,593 180,665,337
- 17. GROSS SLECTRICAL ENERGY GENERATED (HWH) 759,700 1,400,500 59,790,780
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 734,774 1,347,220 57,651,951 PAGE 1 OF 2
OPERATING DA FA REPORT (CONTINUED) DOCKET NO. 50-353 DATE APRIL 9.1997 THIS MONTH YR-TO-DATE CUMULATIVE
- 19. UNIT SERVICE FACTOR 96.8 %
67.0 % 89.0 %
- 20. UNIT AVAILABILITY FACTOR 96.8 %
67.0 % 89.0 %
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 88.6 %
55.9 % 84.8 %
- 22. UNIT CAPACITY FACTOR (USING DER NET) 88.6 %
55.9 % 84.8 %
- 23. UNIT FORCED OUTAGE RATE
.0 % .0 % 3.5 %
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
PLANNED MAINT OUTAGE. 3/31/97 SCHEDULED 4 DAY DURATION
- 25. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
403/97
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):
FORECAST ACHIEVED INITIAL CRITICALITY 08/12/89 08/12/89 INITIAL ELECTRICITY 09/01/89 09/01/89 COMMERCIAL OPERATION 02/01/90 01 M 90 PAGE 2 OF 2
UNIT SHUTDOWNS AND POWER REDUCTIONS { DOCKET NO. 50-353 UNIT NAME LIMERICK UNIT 2 i DATE APRIL 9,1997 COMPLETED BY PECO ENERGY COMPANY I BRUCE E. CANFIELD REPORTS ENGINEER SITE ENGINEERING [ LIMERICK GENERATING STATION t REPORT MONTH MARCH,1997 TELEPHONE (610)718-3794 METHOD OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN EVENT CODE CODE ACTION TO i NO DATE (1) (HOURS) (2) REACTOR (3) REPORT # (4) (5) PREVENT RECURRENCE 167 970304 F 28.0 A 4 N/A CH HTEXCH REACTOR POWER WAS REDUCED TO 65% DUE TO FEEDWATER HEAT EXCHANGER LEAK. 168 970308 S 2.0 B 4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 88% DUE TO MAIN TI)RBINE VALVE TESTING. L 189 970315 S 1.0 8 4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 98% DUE TO MAIN TURBINE VALVE TESTING. i 170 970323 F 17.0 A 4 N/A EG TRANSF REACTOR POWER WAS REDUCED TO 85% DUE TO l MAIN TRANSFORMER HIGH COMBUSTIBLE GAS READING. 171 970327 F 105.0 A 4 N/A HA TURBiN REACTOR POWER WAS REDUCED TO 86% DUE TO TURBINE GENERATOR EXCITOR ALTEREX IN CONTACT WITH ITS BEARING. TOTAL HOURS 153 0 i (1) (2) (3) (4) F-FORCED REASON METHOD EXHIBIT C -INSTRUCTIONS S - SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST 2-MANUAL SCRAM ENTRY SHEETS FOR UCENSEE i C - REFUELING 3-AUTOMATIC SCRAM EVENT REPORT (LER) D - REGULATORY RESTRICTION 4-OTHER (EXPLAIN) FILE (NUREG4161) E - OPERATOR TRAINING + LICENSE EXAMINATION r F - ADMINISTRATIVE (5) G - OPERATIONAL ERROR (EXPLAIN) EXHIBIT I-SAME SOURCE H - OTHER (EXPLAIN) =}}