Issue date: 11/29/1985
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20137Q521 List:
References
PY-CEI-NRR-0409, PY-CEI-NRR-409, NUDOCS 8512050292
Download: ML20137Q517 (1)


Text

b t THE CLEVELAND ELECTR P.o. box 5000 - CLEVELAND, oHlo 44101 - TELEPHONE (216) 622-9800 - ILLUMINATING BLDG. - 55 PUBLICSoVARE Serving The Best Location in the Nation MURRAY R. EDELMAN VICE PRESIDENT NUCLEAR November 29, 1985 PY-CEI/NRR-0409 L Mr. Harold R. Denton Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Request for Extension of Construction Permit No.CPPR-148

Dear Mr. Denton:

Enclosed herewith is an application for amendment of construction permit number CPPR-148 to extend the construction completion date for the Perry Nuclear Power Plant, Unit 1.

In accordance with the schedule of facility fees set forth in 10 CFR Section 170.21, a check for $150.00 is being transmitted by separate cover.

Very truly ours, Murray R. Edelman Vice President Nuclear Group MP2:nj c Enclosure cc: Jay Silberg, Esq.

John Stefano (2)

J. Grobe 8512050292 851129 g

PDR ADOCK 05000440 h"o A

PDR o