'Af Duquesne Udit 2N,Rggg9 8h Nuclear Construction Division y
Robinson Plaza, Building 2. Suite 210 Pittsburgh, PA 15205 August 19, 19S5 United States Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, PA 19406 ATTENTION:
Mr. Richard W. Starostecki Division of Project and Resident Programs
SUBJECT:
Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 USNRC IE Inspection Report No. 50-412/85-13
REFERENCE:
NRC Inspection 50-412/85-13, dated July 18, 1985 Centlemen:
This is in res pons e to the Not ice of Violation cited in Inspection No. 50-412/85-13 and listed in A ppe ndix A (Notice of Violation) attached to your letter to Mr. J. J. Carey, dated July 18, 1985.
Notice of Violation 85-13-02:
"QC Accepted Pipe Support Dimensional Error-Location" As a result of the inspect ion conducted on May 2 3-June 28, 1985, and in accordance with the NRC Enforcement Policy (10CFR2, Appendix C), published in the Federal Register on March 8, 1984 (49FR8583), the following viola-tion was identified:
10CFR50, A ppe ndix B,
Criterion V, requires that ac t ivit ies af fect ing quality shall be prescribed by procedures and shall be accomplished in accordance with these procedures.
Drawing 12241-BZ-19A-48-0C defines the dimens ions, associcted to le r-ances, and other necessary details to properly install pipe suppo rt 2SWS-PSST 625.
Contrary to the above, and even though the installed support was " final ins pe ct ed," the relative piping / support centerline dime ns ion of pipe on Drawing s uppo rt 2SWS-PSST 625 did not conform to that spe c i f ied 12241-BZ-19A-48-0C.
This is a Severity Level IV Violation (Supplement II).
8508270124 850819 PDR ADOCK 05000412 O
PDR flO
United States Nuclear Regulatory Commission Mr. Richard W. Starostecki USNRC IE Inspection Report No. 50-412/85-13 Page 2
Response
The ou t-o f-to le rance pipe location and pipe strut 2SWS-PSST 625 have been evaluated to have resulted during replacement of valve, VGW-060-A-2, during May 1984 following SQC final inspection acceptance of this strut on April 12, 1984.
This condition occurred because neither the cons t ruc t ion personnel replacing the valve or the SQC inspector inspecting the replaced valve welds recopilzed that tha aljacent strut angular orientation from the local ve rt ical had exceeded the maximum I 5* allowed by spe c i f ica-tion 2BVS-920 and 1.P. 7.3.1 by 1.7*.
Upon notification and verification of the stated condition, N&D act ion was initiated.
The condition has been reviewed by Engineering and found not to be reportable under 10CFR50.55(e).
Our applicable piping mdification procedure FCP-504, Revisions to Schneider Power Corporation Control Drawings, has been reviewed and will be revised to strengthen our control of this type of work.
The main control for piping mdifications is the Construction Revision Notice (CRN) des.:ribed in FCP-504.
The application of the CRN will include the process f e, r identifying and controlling ef fects on associated pipe suppo r t s.
In addi t ion, the inspection Plan 7.2 controlling pipe welding will also be revised to include SQC verification of the condition of the associated pipe supports.
The implementation of the revised program will commence on or before Sep t ewbe r 10, 1985.
The revised de ta iled procedures will be made available to NRC Senior Resident inspector upon completion.
We advi se that although the out-of-tolerance condition had not been identified at the time of piping rework, further verification inspections are scheduled.
These act iv it ies are related to the final configuration verification for stress reconciliation and the associated ASME N5 certifi-cation process.
DUQUESNE LIGHT COMPANY SUBSCRIBED AND SW RN TO BEFORE ME THIS
/k DAY OF Mud 1985.
A By Notary Public Q/',y'. Careyv' ANITA ELAINE REITER, NOTARY PUBLIC Vice Fresident ROBINSON TOWNSHIP, ALLEGHENY COUNTY LtY CC'TiSS:0N EXPlRES OCTOBER 70.1996 SDH/wjs cc:
Mr. J. M. Taylor, Director (3)
Mr. B. K. Singh, Project Manager Mr. G. Walton, NRC Resident inspector INPO Records Center NRC Document Control Desk
~.
United States Nuclear Regulatory Commission l
Mr. Richard W. Starostecki USNRC IE Inspection Report No. 50-412/85-13 Pa*ge 3 COMMONWEALTH OF PENNSYLVANIA
)
)
SS:
COUNTY 0F ALLEGHENY
)
On this //,4I day of
_4w
/((I, before me, a Notary Public in and fo r said Com wealth and County, pe rso nally appe ared J. J. ' Carey, who being duly sworn, deposed and said. that (1) he is Vice Pres ident of Duquesne Light, (2) he is duly authorized to execute and file the foregoing Submittal on behalf of said Company, and (3) the statements set forth in the Submittal are true and correct to the best of his knowledge.