Application for Amends to Licenses DPR-39 & DPR-48,revising Specimen Capsule Withdrawal Schedule Which Reflects Implementation of Low Leakage Loading Patterns & Requirements of 10CFR50,App H.Fee Paid
ML20137E867
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 08/19/1985
From: Leblond P
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20137E871 List:
References
0500K, 500K, NUDOCS 8508260090
Download: ML20137E867 (2)


Text

.

'[ O Commonwrith Edison

f. ) ' one First National Plaza. Chicago, Ithnog C Address Reply to: Post Office Box 767 Chicago, lilenois 60690 August 19, 1985 Mr. Harold R'. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission-Washington, DC 20555

Subject:

Zion Nuclear Power Station Units 1 and 2 Proposed Amendment to Facility Operating License Nos. DPR-39 and DPR-48 Specimen Capsules NRC Docket Nos. 50-295 and 50-304

Reference:

LER 50-304/85-09

Dear Mr. Denton:

. Attachment 1 to this letter is a proposed amendment to Facility Operating License Nos. DPR-39 and DPR-48, Appendix A, Section 4.3.4.D -

Materials Irradiation Surveillance Specimen Inspection. This change provides a revised specimen capsule withdrawal schedule which reflects both the implementation of Low Leakage Loading Patterns and the current requirements of 10 CFR 50, Appendix H.

- Attachment 2 provides a technical description and justification for the proposed change.. Attachment 3 contains Commonwealth Edison Company's demonstration that the proposed amendment does not-involve a significant hazards consideration. This change has also received on-site and off-site review and approval.

The technical basis for the revised fluence estimates was originally published as part of a larger report. The required information is being extracted from the original document and is being published in WCAP 10902, entitled " Reactor Vessel Fluence Evaluations for Zion Units 1 and 2".

This ~ document will be transmitted to you by early September.

The referenced LER described Zion's failure to remove a surveillance capsule as required by the current Technical Specifications.

It also committed to removing capsule X on Unit 2 during the Fall, 1985 refueling outage if this change has not been approved. This removal is currently scheduled for late November. Since the removal of a capsule at

.this time will not provide any additional useful information, Commonwealth Edison requests that approval of this amendment request be granted by December 1, 1985.

L p,we 4e h

~ - - _ , _ .

H. R. Denton August 19, 1985 i

A $150.00 fee remittance is enclosed in accordance with 10 CFR 170.

As provided by 10 CFR 50.91, the State of Illinois is being notified of this amendment request by transmittal of a copy of this letter and the attachments.

If you have any questions regarding this matter, please direct them to this office.

Three (3) signed originals and thirty-seven (37) copies of this transmittal and its attachments are hereby provided for your review.

Very truly yours, fb P. C. LeBlond b

Nuclear Licensing Administrator

! 1m Attachments cc:. Resident Inspector - Zion J. A. Norris - MTR M. C. Parker - State of Ill.

i-SUBSCRIBED AND S N to beforejne this f d day of (fjjeusi' , 1985

}'4 Notarf .Public U finn

/

0500K 1