Monthly Operating Repts for Oct 1985
ML20136G736
Person / Time
Site: Surry  
Issue date: 10/31/1985
From: Jones V, Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Beebe M
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
85-795, NUDOCS 8601080454
Download: ML20136G736 (35)


Text

9 8

f Q d VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT NO. 85-10 STATION MANAGER 8601080454 851031 DR ADOCK OS 80 IpV

'] '

s r

i Section Page Operating Data Report - Unit #1 I

Operating Data Report - Unit #2 -

2 Unit Shutdowns and power Reductions - Unit #1 3

Unit Shutdowns and Power Reductions - Unit #2 4&5 Load Reductions Due to Environmental Restrictions - Unit #1 6

Load Reductions Due to Environmental Restrictions - Unit #2 7

Average Daily Unit Power Level-Unit #1 8

Average Daily Unit Power Level-Unit #2 8

Summary of Operating Experience 9 & 10 Amendments to Facility License or Technical Specifications 11 Facility Changes Requiring NRC Approval

,12 Facility Changes 1 hat Did Not Require NRC Approval

.12 Tests and Experiments Requiring NRC Approval 13 Tests and Experiments That Did Not Require NRC Approval 13 Other Changes, Tests and Experiments -

14 Chemistry Report 15 Description of AllInstances Where Thermal Discharge 16 Limits Were Exceeded Fuel Handling Procedure Revisions That Changed the Operating Mode 19 Described in the FSAR Description of Periodic Tests Which Were Not Completed Within the Time Limits Specified in Technical Specifications 20

e il Section Page Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #1 - Mechanical Maintenance 21 - 24 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #1 - Electrical Maintenance 21 - 24 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #1 - Instrument Maintenance 21 - 24 Maintenance of Safety Related Systems During Outage or ~

Reduced Power Periods - Unit #2 - Mechanical Maintenance 25 - 31

' Maintenance of-Safety Related Systems During Outage or Reduced Power Periods - Unit #2 - Electrical Maintenance 25 - 31 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #2 - Instrument Maintenance 25 - 31 9

0 t

ADM-4C Page1 ATTACIF.ENT S Page 1 of 3

~

OPEPATING DATA PJ. PORT FEB C 2 N DOCl'ET NO. 50-280 DATE 11-7-85 l COMPLETED BY V.Tnaas 7 " HONE 357-3184 O?EEATING STATUS 1.

Unit Name:

Surry Unit #1 Notes 2.

Reporting Period:

10-01-85 to 10-31-85 3.

Licensed Thermal Power (MWt):

2441 4.

Nameplate Rating (Gross MWe):

847.s 5.

Design Electrical Rating (Net MWe): 788 6.

Maximum Dependable Capacity (Gross MWe):

820 7..

Marinnm Dependable Capacity (Net MWe):

781 8.

If Changes Occur in Capacity Ratings (Items Eumber 3 Through 7) Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Rastricted, If Any (Net MWe):

10. Reasons For Restrictions, If Any:

This Month Tr.-to-Date Cummulative

11. Hours in Reporting Period 745.0 7296.0 112729.n 12.

Number of Hours Reactor Was Critical 745.0 6471.4 70848,1

13. Reactor Reserve Shutdown Hours o

n 3774.s 14.

Hours Generator On-Line 745.0 61cs 4 sot 7a c

15. Unit Reserve Shutdown Hours 0

0 1716 3 16.

Gross Thermal Energy Generated (MWE) 1,660,525.0 14467608.7 160481785.8

17. Gross Electrical Energy Generated (MWE) 549180.0 4791480.0 51643443.0 18.

Net Electrical Energy Generated (MWE)

'519513.0 4546673.0 48958517.0 19.

Unit Service Factor 100.0 %

87.2 %

61.5 %

20. Unit Available Factor 100.0 %

87.2 %

64.9%

.21.

Unit Capacity Factor (Using MDC Net) 89.3 %.

79.8 %

55.6 %

22.

Unit Capacity Factor (Using DER Net) 88.5%

79.1%

55.1 %

23. Unit Forced Rate 0

2.5%

19.0 %

24.

Shutdowns Scheduled Over Next 6 Months (Type Date, and Duration of Each):

25.

If Shut Down At End Of Report Period Estimated Date of Startup:

26.

Units In Test Status (Prior to Commercial Operation):

Forecast Achieved IEITIAL CRITICALITY INITIAL ELECTRICITY l

COMMERCIAL OPERATION

(

G/FM

_ _ - =

ADM-49 page 2 A C ACEMENT 5 Page 1 of 3 OPEEATING DATA PIPORT FEB C 2 1984 DOCKET NO. 50-281 DATE 11-7-85 COMPLETED BY V Toaes F " HONE 357-3184 OPERATING STATUS j

1.

Unit Name:

Surry Unit #2 Notes 3

2.

Reporting Period:

10-01-85 to 10-31-85 3.

Licensed Thermal Power (MWt):

2441 4.

Nameplate Rating (Gross MWe):

847.5 5.

Design Electrical Rating (Net MWe):

788 6.

Maximum Dependable Capacity (Gross MWe):

811

.i 7.

Mar 4mt= Dependable Capacity (Not MWe):

775

  • 8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

N/A i

9.

Power Level To Which Restricted, If Any (Net MWe):

l

10. Reasons For Restrictions, If Any:

I i

This Month Tr.-to-Date Cummulative

11. Hours in Reporting Period 745.0 7296.0 109608.0 12.

Number of Bours Reactor Was Critical 433.7 4616.6 70622.8

13. Reactor Reserve Shutdown Bours 0

0 328.1 14.

Hours Generater On-Line 433.3 4543.8 69451.4 4

15. Unit Reserve Shutdown Bours 0

0 0

16.

Gross Thermal Energy Generated l

(MWE) 1,050,510.1 10228190.2 162226595.5 i

17.

Gross Electrical Energy Generated (MWE) 342435.0 3282450.0 52572924.0

18. Net Electrical Energy 1

Generated (MWE)

'325174.0 3108011.0 49824453.0 i

19.

Unit Service Factor 58.2 %

62.3%

63.4%

20.

Unit Available factor 58.2%

62.3%

6 3.4 W

, 21. Unit Capacity Factor (Using MDC Net) 56.3 %

55.0 %

58.7%

22. Unit Capacity Tactor (Using DER Net) 55.4 %

54.1 %

57.7 %

23. Unit Forced Rate O'

.3%

13.7 %

24.

Shutdowns Scheduled Over Next 6 Months (Type. Date, and Duration of Each):

25.

If Shut Down At End Of Report Period Estinated Date of Startup:

26.

Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION (907)

~

UNIT 561U1DOWf45 AND POWER REDUC 110NS F

M y,

i

<HA1E 11-f17 R5 REPORT MUNIH OctoW L'OMPl.ETEle RV V Innm 1ELErlMfME (R04) 357-11Ra 1

]

.l l

b 3

4 2

1%

o g

$ I l "j l } g[$

f-l3 U

$ k,,,e,

g4 Cease A Cmieceive i

Ac'h"' 1**

N,,,

pese E.

Evens -

.E. v g '!t p

u g, Re,s r.e.e meca.ieme i

2 q

l 85-15 10-30-85 F

0.0 H

I Unit was reduced to 59% (460 MW's) due to secondary chemistry.

85-16 10-09-85 F

0,0 H

I Unit was reduced to' 30% (180 MW's) due to secondary chemistry. The cause was i

i

~

determined to be resin actting into hotwell from the S/G blowdown 1 x 's. The correct-l tve action was to replace the tailed retentia j

elements.

1 i

i j

i l

l i

l l

1 3

4 F: Fenceil Reason:

Methmi:

Eehible G. Insesucolims i

S: Scleeduled A Esquipment Feilme(Emplain) 1 Menwel im roepereihm of D=

3-Meineenence of Tesi 2 Mannel Sesem.

Entry Sheese few I.icensee C.Refwling 3-Amemnacle Screm.

Event Repal(LER) file INURLG-y l

D Reguisemy Resseicoke 4-Oelsee (Esplein) 0161) g E-Opeeeem Tosining & Ucense Examineshwi e

F-Admihilseteelve 3

w i

G-Opessehmal Eeew (Esplein)

Esisible I.Some Smuce r8177)

Il-Oehee (Emplain) 1

_ _ _. ~

~

Corrected Copy L3filTSlllllDOWNS AND ROWER RE17t!C110NS 180CKET No.

50-281 43NII NAME.

Unit 2 4

.HA1E 10-10-85 CtStrLETEID RV. V. II_ innne REPORTMONsle Sept.

1ELErtlONE (804) 357-3184 l

i g

"h I

~{ -

l_kensee

[*

Cause & Cosseceive t{-

f;IE, gg Repent #

wi e>

heveest Recuseence

}

Evesse -

gi Acehm to W.,

lhee 4

i l

=

t i

RS-7 09-01-85 S

0.0 11 1

Power was reduced to 62%,500 MW's I

]

for load following.

85-8 09-19-85 S

0.0 II I

Power was reduced to 79%,650 MW's for load following.

85-9 09-26-85 S

0.0 Il 1

Power was reduced to 30%,210 MW's due to hurricane threat.

~

j a

l 85-10 09-30-85 S

0.0 11 1

Power was reduced to 82%,653 MW's l

for load following.

l 2

)

i i

I 2

J 4

1 F: Fmced Messem:

Meehail:

Enhalill G - Insieucelims 4

S: SdicJuicJ A-E.gutenwne Ealinse(Emplain) 1-Mannel foe reepsesehm ed D3es R.Maineeseence of Test 2.Manoel Sceans.

Entry Sheces fa licenne j

C.Refeeling 3 Ameommele Screws.

Event Repwe (f.ER)Ille INUltIE T

D Reguleemy Restelcohne 44hbee (Empletal 0161)

E Oresasoe Tsainhag & IJcense Emaniineelun F-AJneinhesselve 5

A i

G Opersehmal Eveise (Emplain)

Eihlble I - Sapie Source j

r8/7F) ll Delwe (Espisleil i

l

-~--

i 50-28]

UNIT 5490Ti>0WNS AND POWER REDUC 190NS I)DCKET NO.

IINIT NAME Surry 2 I

.DATE I I-07-R S IUN REPORT MONIll Octnhor 1El.ErlH7NE (804) 357-3184 i

'~s.

u o

g-

.!I

'g

}* {g e$

U (Aenice g,

conse A cmeecil,e

  1. (-

[

ek jg Repal #

    • O Feevent Recweence Evene gi l

No.

Date Acehm in i

}

85-11 10-19-85 S

311.7 B

1 Unit was shutdown for scheduled snubber

]

outage.

l l

4 g

l I

i I

i 1

2 3

4 F: Fusced Reesem:

Metleml:

Enliible G. insesucshwis t

5: Scheduled A Eiguipnient Fellwe(Emplain) 1-Menwel fue reeposeek m of pais j

3 Malesenence of Test -

2-Manuel 5ceem.

Entey $heets for I.leenice a

C. Refueling 3 Ansosinesic screen.

Evens Repwe(LER)FileINURLG-m j

D-Regulatoey Reseelcthne 4-Otlece (Esplein) 0161)

E Opeessor Teslaing & IJcense Eneminelloes o

i i

F Adadalseteelve m

i G-Opeesehmal Feeve (Emplain)

Eihlble 1 5snee Simes e 1e/77) 11Ohes (Emplaini 4

- - _ -. ~

e.

r Page 6 J

J LOAD REDUCTIONS DUE TO ENVIRONMENTAL RESTRICTIONS l

UNIT NO. I MONTH: October 4

r i

i DATE' TIl!E HOURS LOAD, W REDUCTIONS, !M WH REASON 4

r None Dt ring This Reporting Period a

i I

1, e

l i

i k

r J

I e

i i

I 1

k I

i i

i i

i i

i t

i l

i It 4

t 4

4 1

y I

MONTHLY TOTAL I

4..

. ~

Page 7 LOAD REDUCTIONS DUE TO ENVIRONMENTAL RESTRICTIONS UNIT NO.

2 MONTH: October DATE TI'E HOURS LOAD, L' REDUCTIONS,IN INH REASON None Dtring This Reporting Feriod MONTHLY TOTAL t

U t l*LO AvfwebF DAILY tifet! Filw g gg yr g goggy poggy STAIlON PHOLHAM NO$l?6Mt 15/P1/H5 10.54,18 e

RkPO9 TING MONTH =

DC IllH E P 1995 DOC AF f Ni l. 57-2dn DOCRFI NO. 50-191 DAIF NOvfM)FM 01. l 'M %

COMPtETED Hf W.

Juraf 5 0N I I ON F UN l I i W O Awfhebi DAILf POWLR LEVil avFRabF Daltf POW [p L(wtt 9Av

-MwL-NET-

-MwE-NST-1 165.0 Fo6.9 2

715 1 76n.4

)

in i.6 F58.8 57).2 759.5 5

ill.9 75M.5 o

770 2 756 4 i

776.*

764.6 1

7 7 T. I 763.1 9

  • 4J.5 756.)

IJ 169.0 154.7 11 163.4 75n.0 12 3/ F.o 740.0 11 090 1 7*2.n

!=

Thi./

760.6

!)

166 2 756.3 to 7Ft.h F52.1 17 772.H Fib.6 to F i l. 9 693.3 l '*

148.5 4.5 JJ 173.5 n.n

/t 7F7.0 0.0 22 7F6.6 e.D 29 176.7 n."

?.

IF5.6 A.n

? '-

174. 1 n n o

Ta '

775.5 n.n Il d* T.0 0.n 2d 770.s 09

?8 77b.0 e.n 94 164.o 4.*

St FSS.4 0.*

  • t) m tQ (D

CD

SUMMARY

OF OI:ERATING EXPERIENCE MONTH / YEAR OCTOBER - 1985 Listed below in chronological sequence by unit is a summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.

UNIT ONE 10-01-85 0000 This reporting period begins with the unit at 100% power,805 MW's 10-02-85 1002 Commenced load reduction due to high polishing building aP at 150 MW's/hr 1140 Holding power at 90% (705 MW's) 10-03-85 0448 Commenced power increase at 3%/hr 0637 Holding power at 94% (735 MW/s) 1055 Commenced power increase at 3%/hr 1256 Unit at 100% power (810 MW's) 1930 Commenced load reduction due to secondary chemistry at 150 MW's/hr 10-04-85 0201 Holding power at 59% (460 MW's) 0440 Commenced oower increase at 3%/hr 0650 Commenced station emergency drill (VOPEX DRILL) 0735 Holding power at 69% (540 MW's) 1229 Commenced power increase at 3%/hr 1549 Completed station emergency drill l

2240 Unit at 100% power (810 MW's) 10-09-85 0815 Commenced power reduction at 150 MW's/hr due to secondary chemistry 1010 Holding power at 80% (640 MW's).

1245 Commenced power reduction at 150 MW's/hr due to secondary chemistry 1538 Holding power at 30% (180 MW's) 10-12-85 0712 Commenced power increase at 3%/hr 10-13-85 1631 Unit at 100% power (815 MW's) 10-31-85 2400 This reporting period ends with the unit at 100% power (815 MW's) r

,e

f l

Page 10

SUMMARY

OF OPERATING EXPERIENCE MONTH / YEAR OCTOBER - 1985 Listed below in chronological sequence by unit is a summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.

UNIT TWC 2 10-01-85 0000 This reporting period begins with the~ unit at 100% power (800 MW's).

10-18-85 1926 Commenced unit rampdown at 150 MW's/hr for Planned Outage.

10-19-85 0117 Generator breakers opened, unit off the line.

0140 sReactor shutdown.

1359 Unit < 3500 / 450 psig on RHR.

10-20-85

- 0230 Unit < 2000F.

0623 RCS is degassed.

10-21-85 1447 RCS at mid-nozzle.

10-25-85 0314 Commenced filling RCS.

1200 RCS is soud.

10-28-85 1845 Depressurizing RCS due to pressurizer flange leak.

10-29-85 2034 RCS re-pressurized.

10-30-85 0420 Bubble in pressurizer.

1048 RCS > 2000F, 1840 RCS > 3500F / 450 psig.

10-31-85 0321 Performing RCS overpressure test.

2100 Commenced RCS cooldown to repair MOV-RH-2720B.

2400 This reporting period ends with unit being cooled down to allow repair of MOV-RH-2720B.

.)

7/

p 1

7 y

...m_.m.

4.

Page 11 AMENDMENTS TO FACILITY LICENSE OR TECHNICAL SPECIFICATIONS MONTH / YEAR October - 1985 None During This Reportino Period.

O e

Page 12 FACILITY CHANGES REQUIRING NRC APPROVAL MONTH / YEAR October - 1985 None during this reporting period.

FACILITY CHANGES THAT DID NOT REQUIRE NRC APPROVAL None during this reporting period.

7 i

l l

l l

l

i Page 13 TESTS AND EXPERIMENTS REQUIRING NRC APPROVAL MONTH / YEAR October - 1985 None during this reporting period.

TESTS AND EXPERIMENTS THAT DID NOT REQUIR3 NRC APPROVAL None during this reporting period.

t I

Page 14 OTHER CHANGES, TESTS AND EXPERIMENTS

+

MONTH / YEAR October - 1985 PROC.NO.

TITLE UNIT ST-182 Boric Acid Transfer Pumps Operability Test 1

ST-182C Boric Acid Transfer Pump (1-CH-P-2C) 2 i

Operability Test 4

i l

i

.--.- em

._m-,

  1. -.~.-.--

.,---r---

,v._,,,

PG:25-06 Page 15 VIRGI C PG:IR S:.7RRi' PGu'~r', STATIQ' CEDiIS'"RY REPOr OCwBER 19 85 PgM NE g !T NO. 1 G;IT NO. 2 4 ALYSIS GXDIN MDDIE AVERA'IE

!%XDIN MINDLE AVER 72 3ross Radioact., uCi/ml 1.19E+0 4.36E-1 8.60E.1 6.14E-1 3.20E-2 1.53E-1 Suseerried Solids, run 0.00 0.00 0.00 0.00 0.00 0.00 3ross Tritiun, uCi/ml 7.72E-2 5.88E-2 6.44E-2 2.40E-1 1.71E-1 2.06E-1 Iodine '31, uCi/:nl 1.22E-1 1.29E-2 2.99E-2 2.87E-4 3.59E-5 1.32E-4 I

/I 0.54 0.19 0.27 0.31 0.08 0.16 Hvdrx en, cc/kg 34.1 27.7 30.7 28.8 4.2 16.7 Mthiu, :Un 1.17 0.67 0.83 1.74 1.25 1.39 Boron-10, run*

116.6 68.8 81.1 2181 711 1269 Oxveen, (D.O. ), run 0.005 0.005 0.005 1.500 0.005

0. ! n Chloride, cau 0.01 0.01 0.01 0.050 0.010 0.014 oH @ 25'C 6.89 6.44 6.69 8.90 6.32 8.61
  • Boron-10 = Total Boron x 0.196 7

l RDS.RKS: th,it le cat hul was nlarwl in service on the followine date-for LiOH raiuval, l

I l

10-28-85. Lim was added on the following dates: 10-4-85, 10-10-85, 10-11-85, 10-11-85 for a total of 1030 ams. Started raming-unit down for condensate problerns on 10-3-85.

Ranced down to 59% by 10-4-85.

Started ramping back up on 10-4-85.

Unit was back at i

100% on 10-5-85.

Started ranping unit down 10-9-85 for condensate problems (resin in 1

. SG); rapped down to a 30% hold.. Unit back to 100%on 10-13-85. Unit 2: Cat bed was placed in service on the' following date for LiOH reoval; 10-3-85.

LiOH was added to the unit on the following dates: 10-18-85, 10-28-85 for a total of 2250 gms. Unit started ranp down on 10-18-85 for a snubber outage. At 10-19-85 unit was off line. Unit is still shutdown as of the end of this month.

l l

m

-,.. -. _. - - _ ~ -

Page 16 DESCRIPTION OF ALLINSTANCES WHERE THERMAL DISCHARGE LIMITS WERE EXCEEDED MONTH / YEAR OCTOBER - 1985 None During This Reporting Period.

4 k

i

---.,,..,_m.

I Page 17 i

FUEL HANDLING

)

UNIT 4 1

MONTH / YEAR OCTOBER 10R4 DATF.

NO. OF ANSI NO.

NEW OR SPENT. FUEL SIPPED / RECEIVED ASSEMBLIES PER SHIPMENT INITIAL ENRICHMENT SHIPPING CASK ACTIVITY LEVEL None During This Reporting PeMod.

et

Page }8 FUEL HANDLING UNIT 4 2

October - 1985 HIPPE /R CEIVED ASSEMBLIES P SHIPMENT INITI N CHMENT SHIPPI CASK AC IVIT LEVIL None During rhis Reporting Period.

M S

.= __

Page 19 PROCEDURE REVISIONS THAT CHANGED THE OPERATING MODE DESCRIBED IN THE FSAR MONTH / YEAR OCTOBER - 1985 None.During This Reporting Period.

j l

l 4

i 1

4 l

l I

s m __, _

_,.,__.-.--,__.y_,_..

r., __ _ _,.~,,-., -,,.w y,

Page 20 DESCRIPTION OF PERIODIC TESTS WHICH WERE NOT COMPLETED WITHIN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS -

MONTH / YEAR OCTOBER,1985 PROC.NO.

TITLE UNIT 14.4 Decay Heat Non-Return Valves 1

38.8

~ Chemistry Sampling - Chemical Additon Tank 1

Chemistry Sampling Station Discharges 38.17A Discharge No. 008, Reported as 008 Monthly 1

38.21 Health Physics Sampling - Sub/ Surface Drains 1

38.22 Health Physics Sampling - Piping Tunnel Drains-1 38.27 Full Face Respirators and self contained breathing Apparatus Monthly Inspection 38.37 Component Cooling Service Water Sampling 1

47.B Emergency DC Lighting Self Contain Battery test -

(Service Building) 1 47C Emergency DC Lighting Self Contain Battery test-(Turbine Room - Mezzanine Floor) 1 56.1 Leak Test of Main and Bypass feedwater valve 1

57.7 Reactor Trip Test - Semi-Amually 1

Page 21 MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. I MONTH / YEAR OCTOBER - 1985 The below listed codes denotes the following departments:

0228 or R03 Mechanical i

0229 or R04

- Electrical 0237 or T22. - Instruments l

l

~- 22 C.TCT'TI C ;CIr5 M c.a Fj T' YSM.' Pt !W

"'A' DOHRTr.EC iREF.AH13TO?S60 11/04'95 11::8 PA3E 22 FR:, 11/:;/25 T&J 10/P/d

'.E

  • T 01
9. fir F:ETUT:!II. 72 c:

OT S~Tc!r

.-f;1 c.TG ter.n2 90 Tit!E HIST 04 SUM MRY

. C.T! 10/P/0F. --? 4-02:..?.'t E-m St** to eJ"ST-:NT L:77 FE 0vED 0.D FACKING-rf(ML WEAR. In STALLED tE., FACKIN:: TE5TED. INPGAR D F.:.CNING S+IL. OIUTECARD PACK!tG G_A C GOT HOT.

CC 10/21/G' Cl-FU

-C 0.;iv47 'mE LE6 9 (PW IaF CHEM MVE WS FEEN SHOT WITH F'S:1 ANITE ALL THE WAY AROLPG TrfE BCDY T 0 BC4 RET FLA4E HAS BEEN PINGED, CH ECK TWE DOLTS THERT ARE TIGHT. ON B G SIDE CF R VE 0220 13/21/05 01-P0 t.il -1C72 01e.110 be?.1"G GLo*C STUS DETERI?ATEORE:iACG bTUD3 WITW S/S STd!$ & ADJ REPLACE U37 &t(NIN.3 E vTT0" 0F G M E TIC 97E'EL PETCOCK LEAN STCFfED r20 10/25/25 (1-EE C -1E3 02.J.to t!1 5 NUT O I

i 007 10/27/05 01-C'. 4

-it 62:A t5 Wok H-3fER Dib'C?eECTED MOTOR EATEP HA E BEEN LISC0rNECTED H ATERS NOT USED.

229 10/20 05 01-EF'.-CN' -2 M 0.5312 LO 90L*4ct-WWILE OPEFATING TV-C+' 111P VITAL BU

/

S 1-2 CKT NO 30 TRIPS. THIS IS AS FAR A3 WE GOT. THIS IS ON A 30 LAY CLOCK TECH SSEC.

2 37 10/20/E5 01-SJ f:I -130-2 025350 EQUIPnENT FAILt.FE ACCESSED F/D. HON. FOUND. CHECED S O'5:CE TO EE FROBLEM. ACTIVATED CHEC K SO'J<CE AND CLEAR MEMORY OF EQUIPM EuT FAILVC.E. MOW OP SAT.

' 0237 10/20/85 014:C -FC -425 024?61 5'EET rp co.wAoATOR CA4'T BE RE:tACED AND CALIPPATED FL-1-425 OP ADJUSTED INTO SPEC.

CHECK SAT

237 10/20/95 01-RC 4.1

-G 3 024793 !ROI G-3 >12 STEP? MISALIGNED CHECt3 AWS ROD POSITION INDICAT OR FOR ITS 0,20 tWD 200 STEPS MONIT ORED INDICATI0H WITH SIGNAL SUPPLIE D NO IAIFTING ALSO NONITORED INDICA TION WITH THE TEST SWITCH IIN TIE S237 10/20/S5 31-TC -F? -D32 0247?$ D-12 IRPI IoIFTING LO4 C4EA F C E CKED ANALOG R02 POSITION INDICAT THAN 12 STEPS FROM BANK AVERAGE. OR FOR ITS 0 20, AND 200 STOPS.

MONITORED INDICATION WITH A SIGNAL SiSFLIED NO DRIFTING ALSO MONITORED IWuICATION V:TH THE TEST SWITCH IN r37 10/20/95. 014:C 4P

-F-12 024865 I&I F12 DC:ICTI% LOW CHECED /NALOG ROD POSITION i.iDICAT OR FOR IT'S ZERO. 20 &200 STOPS. MO NITOR INDICATION WITH A SIGNAL SUPP LIED NO IAIFTING ALSO MONITORED IN*

ICATICN WITH TE SWITCH IN THE IN

' 0207 10/20/C5 014,0 45 -F-12 020901 1Wi C-12 ONLY MOVEIt 6 STEPS CHECbED ANALOG ROD POSITION INDICAT DE: FCF ITS ZER. 20 & 200 STOP. MONI TOFID INDICATION WITH A SIGNAL SUPP LIED NO I6IFTING ALSO MONITORED IND ICATION WITH TEST SWITCH IN THE 02?? 10/20/E5 01-RC.CCri -100B 02b045 DISktAYERCATICATTf'O PEEFCfrID PT AFTER TURNING OFF MONITOR i

H 01 SPLAYS T*S ALL THE WAY CHECKING CONTACTS ON COpMECTORS TURMNG OSS S N EN ON AND RESETTING OF MONITOR CH SAT

E3 3?.TE Y RCLATE? ICItC F.OJCED PON': i'FTED it ';s ^.9 DMTENT 5:G W a W T00?60 11/04/85 11:23 FAGE 23 FR*.~.

10,'19/E5 THRJ 10/21/ n LHIT 01 SJF5.Y FITURNED TO wu

EPT SER'.* ICE ttC NJaLFR traa.tER WO IITLE HI5T".AY S*ftAF.Y 2237 10/20/Et 014i f.R -175 0 4.2 N Fil9. FECC*!fE CAN !#EL) READ FiftACEDINKPAD5Ct[ SAT.

l I:37 10/20/E5 01-Ff!-

-:!10 02wb4 Sy! H-10 *ETER I"."1 CATION.

rulACED ST.CKING IN2ICATOR WITH AN DROPPED TO O w!TH NO CAUSE OT9 F?I INDICATOR FEFJ0 FED NECE5 SMY IMP-C-FFI-32 & 1-FT-5.2 MONITO R INDICATION NO ACFAFENT DRIFTS OR STICKING 023' 10r'4/Et 0140 -DCT -215 02600*. COL *F EP4 lt'SICATION MCWITORID N31 I M IR FOR SEVERAL -

ERRATIC DE0AYS DAY 5. WE $EEN NO SIGN Or EFPATIC INDICATION. NO FURTHER 10RK IEEMED NECESSARY.

237 10/03/25 01-CC -PI -300A.024347 NEED TO INSTALL THIS PRE 55iAE INSTALLED A NEW CAL GAGE l

GAUGE FOR THE PUMP TEST

' 0-100 FSIG STOCK #1410977 3237 10/22/25 01-CC M -3001' 021343 TEEP TO I'SitLL THIG PFE55!AE INSTALLED A NEW CALIFRATED GAGE STOCK #1410977 0237 10/20/05.01-CC -PI -301A 0243G REED 10 IWTALL THIS Pct:50RE INSTALLED NEW CALIICATED GAGE j

STOCK t 1410975 OT 10/20/25 01-00 -FI -3015 02u0J fIED TO IWTfA.L THIS F5:E55UFI INSTALLED A NEW CAL CE E STOCK #1410c75

227 10/29/05 01-00 -R
-100 c.:557 7 ?!W M0t41TC* WIrp 00LTAr,E FAILE) FIFAIRED BROKE *! LEAD FOR REMOTE METER ON THE BACK Or TE PROCESS n0NITOR i

'0237 10/31/35 01-CH -P! -NA 01275b GFME FM ^9tST IterCATTON RFA]VED &iD DISCARDED OLD DErECTIVE ERRATIC C40G. INSTALLED NEW CALIBRATED ~GA UGE 0-04 1/4' BACK MOUNT i

1 i

i r

i i

l

~.--,-_. _.

~

o

..r-m e.yy*, p**..*

? v

  • T.s.?

.f T e.* r i g. p..f.g.

L. :.es. T' 6--.L y (4!.' f.a = :', [:.* 7;,f. JQ*,

f T. *,.",; Ap

' '* 7\\, ? C O'."J

  • { / %.4/Cr.

..*N

c. * -.

4a(

ws w.

.t.,

.s

..s w - -. *...

e n

w Msr r u-

....u..r.e.

r..r..

...,.t,c....

Lw!' el dAt

e.. i m,L-,..-

L.J

>c.

i

.?T CEr".' ICE w r/Jx h.MICR ror.itA WO T:"LE HI3TOEY 9f tVI.Y Z 10. ' N. '03

0. E: -

-33 0;c33 EM. lev @ )f ' 54C G C 0*.Y CLEsD ECAIC ACID CU 07 M'E

@) 5D PLAT 5. VALVE HAS FU" DER

-DJ.CTbENT T m i C M EE M@E

."o 10 '14/?? 0;-5; '

- "O c.52v > LIDSSE FOOtti SDMIW FECG SEWING TECi CISCHAFSE EEE55 04U.E. TCOG LIVE FLUG3EL AT FUN TGY. B_EW 00T LINE TO GAUGE.

EEN*.D SENSIN3 LIE TO S'JCTION CM 70(.bD NO Lt0CNAGE Z3 10.'14/05 01-5'. -:-

-101 0.1430 CLEM ST~ AlvA t.'T ADM5T IM EEm00ED LID R0m CANISTEFS. REMOVE FILTD. ELEMENT 3.FOUND VERY LITTLE TF45H. CLE#G WT LITTLE TERE W45 C3.ma*E NEW GASKET 3. INSTALLE D ELEnENT LID 5. ADJUSTED IMFELLEP

.'22? 10/10/05 01-OH -H U -2M-9 v t2h 'EC % C 3G CIPCUIT railed TO EEMCED OLL TAKE, EEFLA*ED WITH NEW MEET ACOEPTANCE CRITERIA IME

2N 10/

.E" 01 ~J: I@ :;4 023219 !@! CATI 0' CLC FC.ST10n TOO EEricy_D FLUG AND SFt!CEIi CABLE ON B HIGH GTH SIIE

'." ? 10/10/.5 0149 +1SC-m 0.'.,23 0

.@f.9 F. FF;t<E IOOR LIMI 5 nED TO bCE MICR0 SWITCH 10/11/95 W ALARM KEEPS COMING IN MUST LENT ARn ON SWITCH TO hANE UP TO TAPE DOOR SHUT EkQ DOCS ALAEji NOT A FRGBLEM AT THIS TIME 10/12/85

Page 25 1

i MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 MONTH / YEAR OCTOBER - 1985 The below listed codes denotes the following departments:

0228 cr R03 Mechanical 0229 or R04 Electrical ~

0237 or T22 Instruments i

i i

e i

a l

I

_ =.. _ -. _

- _ ~ - -. _ _ _

=

DC2 E/C.Y F.ELt.D rer.!*:3 TIW.49 PJB: S$1ED FY '28tr MD 95.,RTrBit PF00:Am U;T00560 11/04 'B5 11:25 Ft.0E 26 FK0:i 10 '19/E5 !Hku 10/31/95 UNIT 02 :iLS3 i

FSTurdEL TO LJO

'FPT SERVICE it.it; DJS ER ft.r.lCR CO 'lTLE HISTORf SU % %Y 02^C 10/31/05 02-DA -MISC-ta OA222 fiTJfiT CONistr@T 50+

FE WJE C@ TIMG FCA CLEANING AND l

IN5TALLED 2223 10/31/05 02 -< -T!

-2 CIA 0 W' a " FUc M I M HJJJ m & # O' T Kis)ED FL%#4ITE FtVG AND INSTALLE r

4 4

RIP VLV ACTUATOR ARM HOUSING 15 D SET 50KG IN HOUSING. CEM0'/ED FtC LEAKING NING GLAND AND 'ADDED 2 RINGS OF PAC KING TO EACH SIIE OF VALVE ACTUATOR IM.3/8 FACKIM USED SHOP SPAFI i 020 10/31/C5 02-MG +TV -2010 0.::,991 TV Ie'Er?JLC At Me Pr 14.2 CALLED J. 5IWSON FT 14.2 CO*ftETED i

SAT 0 1000 10/27/85 NO FROI4.EM j

EXI5TS 0229 10/31/95 02-EU -r.J. -2042 c 512 ??? IS CRACMI @ AND LEANI%

REFLACED EXPAN510N JOINT WITH NEW DIMSION JOINT l220 10/31/05 02-VS -F

-12 Ody17 INSfiCTICes IX5' ON I15C. SITE INWSTIGATED JOB FOUND NO FROBLEM cF FAN BLOWN IN. HINGES BROKEN WITH DOOR. NO WORK OR ELIdNG ICT HAD OPS INVE5TIGATE THEY FOUND j

JOB TO BE SAT AS FER A WFEELER j 020? 10/2145 02-CW -M0'1 -200D 0513 PIYET TL59)E 4 WITCH IN EWR B5 EhP-C-NC-152 AND EMP-C-MOV-63 IONE

' 0229 10/21/25 ~ 02-SI

'0V -2290A

0. :,10v (ISET TOF9)E 94 ITCH IAW EWR 85 'vAUvE CYCLED SAT j

i 0227 10/22/85 1

02-EI -MOV -20$ B o.::N35 MISSING IcAIN FtL9 OtACED MIS 5ING FtUG i

~

t

! 0229 10/23/85 02-PC -MOV -NA 07.,524 0.SSIST Oct?Ai!0N3 IN NJING LO-ASSI59 075 IN VALVES OFF PACH-SEA op STOP VALVES OFF BACKSEAT T 10/19/85 2229 10/23/05 02 c.H -P

~1A+:B 02S25 CuEcr. OIL LE'cl S IN RHR Nr0R5 ADD OIL TO IB RHR MOTOR 0229 10/23/85 02-SI -MOV -28908 02:110 REEET TOF9X SWITCu IAW EWR 65 EEFLACED THE THERMAL OVERLOADS AND CYCLED WLVE SAT 1

0229 '10/25/85 02-SI -M0') -2042 025839 FEEET T0cOJE SL'I'CH TO ORIGIr4-FESET TOCQUE SWITCH TO OFEN 2 CLOSE 2

toy.

3 TESTED SATISFACTORY COMFLETED PR OCEICFE 0229 10/25/95 02-SW -rOJ -205B 025118 FfEET TOC 9)E SWITCu IN EwR is5 COMFtuu FROCEICRE EMP-C-NCC-152 0221 *0/26/95 02-CH -50V -204 0'.'WO2 PFtwfN FtEX CONIt!IT FEPAIRED I49'EN FLEX ON 2-CH-SOV-2204 0229 10/26/95 02-DA -SOV -200B 025879 TIGHTEN FLEX C0dl8JIT TIGHTEN FLEX CONDUIT ON 2-DA-50V-2 200B 10/26/85 f 0227 10/06/25 02-RO -MOV -2536 025877 FE!ET TOF9)E 997Teu TO 3 0 FEN /3 cLosE r. TEST VALVE WITH MOVATk" 25 CLOSE 25 - SETTINGS CORRECT AS

'ER EMP-C-t@/-063 0229 10/26/05 02-RC -FLY 4',8 01.'030 IC-2-409AIX Pc]_aY IS IE-DER-EELAf AFPADENTLY HAS ALFEADY BEEN GIZED.

REFLACED.IT AFFEARS TO BE NEW AND I5 ENERGIZED. DID NOT REFtACE j

10/26/05

! 0229 10/20/25 02-CH -M7J -2115". 02J936 t'.!SSI*d3 ICAIN PJ13 IN MENING LID U!SUAL IN5FECTION FOUND NO OF THE LIMITORQUE' OPERATOR p(ggg MIggIpg l

l l

L

TT

~N T i f.-~.!,TE. I.Z.?? ' G Juc h.lLU " Tc5 P L*'" r.*'y DU ART >ENT FROGR r3 L7T0;860 11/04/E5 11:2a pt,0E 27 FF.2M 10/1?/E5 TMNU IV/31/t:5 UsIT 02 $URRY RETure'Er T0 v)

WT

~

t'/.*:K RMC tie.1:ER u0 TITLE HISTORY

SUMMARY

& JICE I229 10/22/E5 C-U O.

-2J1-1 0.:345' FD/0;- T* DIP C4WE5 C%GED TF5 FRCe TF 1 TO TAP 2 TC60)E Tte LOLT 3/8 TG 31 FT LBS

~1/4"3TUD AND NUT TD 8 FT LFS ON MAI N IdJs BAR 10/22/85 022' 10/20/05 D AM

~J. -2 W 0259W TIGHTEa' LOCSE 0"D!'IT SLEFORT TIGHTEN LOO 3E CONDUIT SUFftRT ON 2-Kn-57J-200410/26/85 0229 10/29/85 02-12 { 3",-IA c.'5237 A?'.*2IATec P+-5 !S LOCEED IN CrP GED GATE ON RIS CARD. TO SHOW D

WESTIGATE FE&CLC5E TO AL/AM 0229 10/29/85 02-CH -!CJ -2702B 025879 SW DOE 9 **Ti D1T.P F03.ND FRGBLEM WITH COMrEN VIRE AND FID LIGnT WIRE BOTH WIFIS WERE WHIT E. SWFFED RED LIGHT & CCMMON VALVE CYCLED FINE.

C29 10/29/85 02-CS -M~tJ -201A 025627 INTEc*EDIATE INDICATION ONLY FUF04ED HOVATS 2000 TEST AND ADJU STED CLOSE CH LIMIT TO SHORTEN TE i

STROKE IY.2 SEC 0229 10/29/C5 02JP -TX -2H1-1 029356 f9FCA*1 TF SETTD6 CHANGES TMi CHANGED FROM NUMBER NO 1 TAP T 0 N0 2 TAT. 3/8 BOLTS TGROUED TO 31 FT LBS 1/4 INCH STUD TORQUED TO 8 FT LP3 2 BOLTS MISSING FROM COVER.

CLIFS FOR NUT 3 ON ORDER.

022? 10/09/E5 02-CFL.100 W, 0.:WW FIMLFE WCIN? FY ITS E1ECTRI-143iALLED FIXTURE AND LAMFS CAL WIRES 022? 10/29/95 02 ~W

.~.?> -251A OW540

.-Ca.' CONTROL 190LATION SWITCH FILLACED COIL ON LATCHING RELAY OLD COIL blJRNT UP.

0229 10/29/25 02-G2 -TV -204 0.!3911 C'.MI8JIT IS LLME & UN7JFf-3RTED FGAIRED CONICIT S:JPORT ON 2-GW-TV

-204 0229 10/27/95 02-MS -M7) -201A 0253S5 f?! - ON DEMAG FERFCAhiD FM-M3-MOV E/A1 0229 10/29/85 02-M5 J.JJ -209 023933 WEIN FLEX CD'C8]IT REPAIRED I4 GIN FLEr DN 2-MS-SOV-20 9

0229 10/20/85 02-RC -FOJ -2455C 03301 EEM0iE LIMITS r0R PECH. AND RE NO ELECTEICAL DISCONNECTION OF LIMI PLACE LIMITS T5 CF SUV WAS IOE NO LIMIT ADJUSTM ENT WAS NECESSARY 0229 10/29/E5 02-RS --MOV -256A 025133 ASSIST Mai%TS IN TESTING UALVE FEEFORMCD MOVATS TEST REFLACED OVEFLOAD HEATERS 0229 80/29/85 02-RS -M0') -256B 03127 ASSIST MOVATS !N TESTING VALVE FU LACED DVERLOAD HEATERS

~ 0229 10/29/95 02-SU -M2V -204D 025847 8.W_'.'E 10ROJES 0"7 DGTFAD Or ADJUSTED LIMIT SWITCH CYCLE VALVE O LIMIT CLOSE AD1UST LIMITS K

- 0229 10/30/35 02-CH -HT -2A138 025922 REPAIR /REFLAFE HEAT TAPE EEFAIRED HEAT STRIPPERS EVERYTHING SAT. FERFORMED EMP-C-HT-37 0229 80/30/85 02-CH f.09 -2267A 025093 RESET TODOUE SWITCu IAW EWR-85 FUf0F11 EWR-85-2244 0229 10/30/25 02+.2 NH') -201 A. 025709 P!YCCwNECT/ REM 0i'E M0f0R AND

' RECONNECTED MOTOR LEADS INSTALLED L LIMITS / REINSTALL G RECONNECT IMIT SWITCH /TOROUE SWITCH. DID NOT TERMINATE THEM.

0229 10/30/05 02-MS -NRV -201B 025703 DISCONNECF/PEMOVE a0 TOR AND riOTOR RECONNECTED MOTOR NOT MMD 1

LIMITS / REINSTALL G RECONNECT BECAUSE OF PAINT COVERING TEM.

' C229 10/30/95 02-M0 -mV 2010 0.6 /10 DIP.t**ECT/PEM MOTOP AND FEh0iED rt0 TOR AND LIMITS FOR MECHAN LIMITS / REINSTALL G RECONNECT ICS NEEDS GAKET FOR THE MOTOR INSTALLE0 AS PER CM->#4P-C-HSS-130 10-25-85

.~,-,

ItCC St. EP Fi.ATZD D$.ING REKGD P'NEP S0elED Pi LW A@ UEF4TrIENT FRO: % i W TC0360 11/04/05 11:28 FAGE 2f4 Fr:;3 :)/19/g5 itea 10/31n5 UNIT 02 St.iRY FCTlD ED TO V3

.UT E 21!C2 hG NDMICT.

t v.11R L'O T!rLE HISTORY

SUMMARY

r37 10/20/C5 02-FM -kR -200 02:220 Firi LEC%1'Lf: C4N Be&:LY READ FIFLACED INNPAPS CK SAT

~-

I237 10/20/25 02-3U -RM -220 ca376 A:.e SETP01m TOO HIGH ADJJSTED STTPONTS TO DESIRED VALVIS OT 10/22/05 0 ~ -C RM3 -259 0253:9 LOW FLOW 4.5 SCFr* AFTER CH4CUALREFtACED PCTAt1ETER C0FSECTED FLOW I REPLACEMENTS AS PER PT 26.,

S NOW eSCFh. PETUMED MONITOR TO SE tWICE K37 10/24/55 02-n.' -Li 2473 0Jr./4A 14 55f!CA'E TL*IUC r F D'.nAGE/ INVESTIGATED A W FOUND THAT REPAIR AS NECESSARY LINE WAS INTACT WITH NO CRIhPING C FLATING AND NO SCARS. EQUIPMENT IS SAT O'37 10/05/E! 02-00 -FI ~210?.

0.4C:6 it'1CATIT 10.@ GL/ MIN FLOW CiECED TO MAKE SLET ZERO HAD NOT SHIFTED BY ISOLATING TL'NSMITTER AND EQUALIZING. TRANSMITTER READ 1.0 06 VDC CECNED TO MAE SURE BOTH LO A4 HI SIIC SENSING LINES HAD 6:37 10/23/E5 02-CC -FT -208 02463: FEF5LM 19 MONTH CALIBAATION COMFtETED 15 MONTH CALIBRATION MADE ADJUSTMENTS ON FT-CC-208 4

CHECED SAT.

2237 10/28/25 02-CC -PI -3006 0a316 FIED TO IHTAr,L ru!S 5tf4EGE INSTALLED A NEW CAL GAGE GAUGE FOR THE PUMP TEST STOCK #1410977 2227 10/20/55 02-C0 -PI -3XB C24344 NEED TO INSTALL THIS PRERSLEE INSTALLED A NEW Ctt GAGE STOCA i 1410977 r37 10/29/35 02-CC -PI -301A 024331 "EE TO INSTAL'. Tu!S PEE;SURE INSTALLED A NEW CAL GAGE. STOCK (1410575 0237 10/29/85 02-CC -FI -301B 024345 eel' TO ICf 4LL THIS PRESSlfiE INSTELED A NEW CALIBRATED GAGE STOCK #1410975 2237 10/2S/25 (2-F'J -FI -200B 0223Yo I*2'ICATLo OSCII LAT!rr3 CALIBRATED FT-FW-200B AS FER CAL NO FLOW, INVESTIGATE 61 CK SAT 0237 1C/2C/05 02-IC -DETR-B 024683 IETECTCH l'C.NING EXCESSIVE FIFLACED INC0FE ICTECTOR AS FER CURRENT IMP-C-IFM-20 r37 10/23/05 02-RI -RP -H6

,02'A37 Ik+1 EEADS H7C4!. CALIBRATE CtiECKED SIGNAL CONDITIONING MOIdE.N0 ADJJSTMENTS MAIE M37 10/28/85 02-it -RI -219 025675 fil'S 0 HAS NO NEEI'LE DFFECTION PIFi. ACED REh0TE MONITORING METER IT WAS CAUSING THE PROCESS MONITCR TO INDICATE ERR 0NIOUSLY, AFTER r'FTER REFtACEMENT C E CK SAT.

' 2 37 10/22/95 02-EM -RI -220 025676 SE1PCINT HI FOR HI FixDJJSTED THE ALERT AND ALARM SETPOINTS. SETPOINTS DRIFTED HIGH.

0237 10/29/05 M-FfI--ROD -r3 02it23 CMi' IN IRoI-W C2MI't CCvc0T CEI~ CRATED ROD POSITION INDICATOR COMPUTER ALARMS & 000 ANPAJNCIATOR 0237 10/30/05 02-RC -SCM -T0057 023805 TFTC ON

'A' COPE C00LI M MnN-FOUND LOOSE F0WER CONNECTION FETIGH ITORING REA0!NG LOW

.._. ~ _ _ _ _ _ _ _ _ _ _,,. _, _ _ _. _, _, _, _

'"")

EA Cf RELAC CRINC. LJCO c/S c'o'rn u N'T ^'JD iWT9 en0CAAM W:iO?360 11/04/S5 11:28 FAGE 29 Frr. ;3/10 25 reK! I?/;;/r5

/

UNIl 02 bLtm RC'JFNED TO WO

'EPT CEF?!!CE n.%K MER M,?.s WO TITLE HISTORY SUMrb%Y 4 ~

I 1

~237 10/31/05 02-CH E

~2 c.:453: *EE F99a.'EL TO 595tVM VT NTE FERSCdEL PERF#ED VT.MT.AND c ut INSPECTION OF 36 BOLTS UT IWSFECTION3 07 E AT EXCHANGER BOLTI4 (FEMOVED) j ?237 10/31/95 0.%. IC -DE*T.-C 024tS' 8r6* Yr IETECTOR FF LACED CLUTCH AND SET FOR 73LPS.

AND REFtACED IETECTOR

237 10/31/E5 02-IC -ICTR-E C245::: FfLtACE Ir5ECTIVE OLUTCH MD EU LACED CLUTCH AND SET FOR 72LPS.

DETECTOR FiFtACED IETECTM

237 10/31/05 02-Mi -P: -2400P 02t?W D19.WSE Fff9CE GAC# INACCU* REMOVED OLD GAIX{ FROM FLOOR AND RATE READS DI5FOSED Or AFFROPCIATLY. INSTALLG A NEW CALIBFATED CMI. OFENED ISOLATIGH VALVE.

4 F#.TS: 1) GAUGE 14111270 J

4 I

i 1

6 f

4 3

1 I

i f

1 I

I I

i l

_...-_,-.,.,..-.,..~..--...._m

s &

e q

7 00 ESI N RC_A"T!: DLC2 T11UCEv PwER RmE1: ?? ""1T tMi IUwaTMDo m 00RM IfT00560 11/04/85 11:29 PAGE

'y FR0a 10/19/t:5 THR9 1091/95 LPCT 02 StfRY RET'JPJNED TO.

WO J.PT CERV!CE MATf. if#2 G teJf.PER Wu Tl'LE HISTORY SUhNRY 2220 10/20/C= C2-At -hiSC '.CNT e2t-;94 Ir6 ! v_L M9 'E 97 RD.-

INSTt> f PU STMD PIFE MD VENT RIG r20 10/21/25 22-EE -E20 --2 0.:0469 nD2 01'. TC nEWoA".* AIR NOT EEIED AS FER G. hARSHALL.

FILTERS 2220 10/22/05 02-12 MPJ -255A C/:,713 it'YESTIGA'E p' STROKE VALE AND CHECK FOR TOTAL ST EM Ti& VEL IN DEGT<EES. 85 DEG. TOTAL TRAVEL 04 THIS VAU/E.

7.:22 10/22/S5 02-2I.a?! -2 hCF 0.c691 CUT Phlr6 STEa I!L31CATOR SO VERIFIED VALUE WAS IN CLOSED IT IS FLUSH WHEN VALVE IS SHUT POSITIOr4 AND CUT AND ADJUSTED STEM FOSITION INDICATOR TO RERECT

'SAME 2229 10/23/95 02_rg 4tv.24?5 021td #L"E S!!CES'Ir6 TAI.L B6TTCri R! M JED OLD PACKING AND REFLACED WI TH NEW GARLOCK 90. 8 RINGS

220 10/23/85 C2-R2 -M3V '-2'59 0 4 714 Ir#ESTIGATE WJ STROKE E VE AND CHECK FOR TOTAL ST EM TEAVEL IN [EGREES. 105 DEG. TOTA L TT4 VEL ON THIS VALVE
223 10/24/05 02-SU 9 0 -t4A 02:c LC'.9.N rLv'GE TO ALLOW MAIN RErtNED BLANK FLANGES 0228 10/05/05 02-F.H -MOV -2701 03 ?/3 PA'J.1% LEAK AS DETTAMINED M FOUND FACKING GLAND NUTS LOOSE HOT SHUTDOWN WALKOOWN ADJJSTED PACKING STILL HAVE 1" 0F ADJJSTMENT LEFT
223 10/25/05 0~;-2: -

-15?

025064 PA'.*.1% LEtA RDv"!VED OLD PACKING IN SMALL PIECES AND DUST APPROX TREE RINGS REFAChE D WITH 1/4" GAF1.0CK 98 3 RINGS 2225 10/26/95 02-MS -

-77 05617 PPCo.ING LEAh.

VALW IS ON BACKSEAT. REPACKED VALVE IAW FROCE18SE 6 RINGS PACKING 2225 10/26/05 02-RC 4CV -2455C 025909 AIR LEAN DOLWTEAM Or REGULAT FEFLACE ELBOW WITH NEW ONE OR 1223 10/26/95 02-S'J -P

-10A 025519 f t* 1p_pa,qy ptc To f.0W DEL-CHANGED OUT DEFECTIVE F1JMP WITH SHO

~

TA P SPARE FtJMP. TESTED SAT AT 40 PSI WG SUIMITTED TO REPUILD DEFECTIVE FtiMP REMOVED *208016

229 10/27/25 02-CH -Wi> -2229A. e21909 ft2V-2290A HAS A PACKING LEAK FEM")VED THREE (3) RINGS OF PACKING.

COULD NOT REMOVE LANTERN RING WITH-GUT FEh0VING VALVE. REPACKED WITH T THREE (3) RINGS ORGARLOK 98 3/8" AS PER ED BRENPW4 AND JIM CLAY.

2229 10/27/E5 02-DA -TV -200A 022623 VALE WILL NOT 0 9 DISASSEMBLE VALVE AND REPLACE SEAT, Ftt% STEM AND GASKET SET.

223 10/23/95 02-CH -

-305 021809 2-C4-305 (FCV-2122 FYPA35 FEh0VED OLD PACK *NG 2 RINGS OF VALVE HAS A LEAK ON PACKING C#: LOCK 99 AND 2 202. 6 RINGS HOUSING) LEAVAGE REDUCTION OF C# FOIL. PEPAChED WITH 8 RINGS GARLOCK 98 1/4" T'23 10/20/05 02-CH 4CY -2303B 04816 Rt7t^CE DictRtSM ADJJSTED STRONE OF VALVE TO 1" AS FER TECH hANUAL. HAD OFS CYCLE VALVE SEVERAL TIMES TO VERIFY STROK E SAT. CHECK FOR AIR LEAKS ON DIAFt!RAGM FOUND HONE 220 10/20/C5 02-CV -

-4 00:333 Ire ECT LW %

FA5i<ICATED NEW SPOOL PIECE WITH CHECK VALVE USING ALL NEW MATERIAL

o....

-~0':

SATE'Y TI.aTO I'JRING RE2E PPc c sm t, e r amp pga pi,.qNT p p g:T0 E 0 11/04/e5 11:2a AGE 3i FRC:i 10/19/00 THRU 1041'Y5 UNIT 02 SUfJ:'

RET'JR.C TO Li' OT EERVICE MTc N'J.PEr:

Nuta.5CR 90 TITLE HISTORY

SUMMARY

0229 10/29/25 02-CV -

5 e01:04 VER!rY M TwtR CHECN VauiE INT 3EEID OLD SM)0L PIECE WITH 02 ERNALS ARE INSTALLED 5 INSTALLED. REPLACED GAStiT WITH R EL Rt!EiER GASkIT AND INSTALLED NEW SPOOL PIECE WITH NEW 02-CV-5 S~.23 10/OS/S5 0*-DA -TV -200A OME.;'l IW7nLL 997. P!ECE ~

SDOCi PIECE INSTALLED.

5F07. FIECE PEMENED.

022G 10/03/Si 02-DG -

-14 OL%15 F9_ ACE DIAMM FiftACED ICWT ASSY ICE TO WATER AND D05E CON 3IDEFiATION3.

C'23 10/20/E5 02 re icy.2495 024417 AIN LFp. m. vaut sistrIONER FIFAIFED AIR LEAN IN FOSITIONER 2220 13/23/05 02-M3 -

-?6 02:616 G*_ ACE PACMNG Att B/B FACh.ING VALVE IS ON BACKSEAT.FIFACKED VALVE 6 RINGS 1/4" NOTE., GLAND FOLLOWER STEAM CUT

^28 10/29/85 02-RC -

-17 US?ed FiACK W.t8E REMNED FACKING GLAND AND SFtIT. FE n0VE EXISTING FACKING. CLEANED GLAN D MD KEFACKED UALVE.

222 10/20/25 02 :f' TO.' -f456 039 9 VE'E 9PEtY AM LI*ti HAS AIR EN005 TEST AIR COINECTIONS FROM FtV LEAK AT FIRST CONNECTION UP.

BACM TO SOLENDID UALtE. NO LEAKS l

STREAM b2 N'

?"20 10/22/05 02-Rd. -F

-257 0 5247 F W wA5 LOM rLOW FOUND BELT LOOSE AND DAMAGED.

INSTALLED WW BELT.#-T' ADJUSTED TO COLFECT TENSION.kAD OFS TEST R'JN TESTED SAT. ALSO FOUND FtLLY ON MOTOR DAMAGED. ELEC TO REFLACE 0"23 10/23/25 02-T<3 -GG -N/A 02574 INST 4_L/FT*?S P.NE FLA%E FLiWCE3 HAVE BEED INSTALLED 10/22/.

55 iME BEEN EEr40'ED AND CRATIr4G IN3 TALL 10/23/85. GLEN MOORE CALLED 4

j GC Oil r4IGHT SHIFT TO SEE IF GC NEEDED TO LOON AT SUMP BEF0FE GRATI 0223 10/23/85 02-RS - rt3 N/A 03706 INSTN L#i&?E BLMK FiMGE BL44ks HAVE BEEN INSTALLED AND FISED. Ch'N h00ri CALLED OC ON NI GHT SHIM TO SEE IF GC NEEIED TO LOOK AT SUMP BEFORE GRATING WAS INSTALLED. OC TOLD HIM NO.

0229 10/29/05 02-5U

-41 01W65 Ff91R VALVE M HECESSARY.

REKNE OLD VALVE AND CLEANED GASKET SUEFACE. INSTALLED NEW VALVE (W)

NEW STUDS, NUTS.AND GASKET. INSTALL BLANK ON VALVE OUTLET

]0229 10/22/05 02-0U 4+ -CL151 02S781 PIN 5#.?_E LEAK IN MAIN PIFE FiftACE WITH FIECE OF PIPE 0228 10/29/95 02.".3 -TV -201B 03V90 EXCEED 9.X STET E TIME CALLED J. STMFSON PT 14.2 COMFtETED SAT G 1000 10/29/85. NO FROBLEM E(I5TS 0228 10/09/85 02-T.0 -FfV -2455C Chm VALVE HAS ShetL DI6PHP@ LEAK TIGHTENED DIA:tiRAM BOLTING TO STOP AIR LEAK 0223' 10/31/85 02-B3 -DR -HATCH 025937

.W.E WCESSARY REPAIRS NO FIFAIRS NECE33ARY HATCH PASSED FT 16.5/16 7 0228 10/31/95 02-Q: -

.',75 0257P.G FEMUVE BLANK FNG, INSTALL TEST IU4JK FLAWE INSTALLED add REMOVED

, 0228 10/31/95 02-Oi -FE -2150 025895' PIPINf3 OC 2-C9-141 IS 100SE TIGHTENED FIFE. LEAK STOPFED WHERE IT SCREWS INTO FE 2150 i

n.-..

_..m_..

__,.__-___y

-, ~

F 0'

VIHU INI A ELucTunc Axn Pownu Costi Axy Hiennoxn,Vinoisir unuut W.L.STEWAMT vara Pumminews Noctuam opunattosn November 14, 1985 Mr. Maurice R. Beebe Serial No.85-795 Office of Resource Management N0/ETS:acm U. S. Nuclear Regulatory Commission Docket Nos. 50-280 Washington, D. C. 20555 50-281 License Nos. DPR-32

Dear Mr. Beebe:

DPR-37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNIT NOS. 1 AND 2 MONTHLY OPERATING REPORT Enclosed is the Monthly Operating Report for Surry Power Station Unit Ncs. I and 2 for the month of October, 1985.

'ry trul" ours,

(

,0 h o y-W. L.

tewaA Enclosure (3 copies) cc:

Mr. J. Taylor, Director (12 copies)

Office of Inspection and Enforcement Dr. J. Nelson Grace (1 copy)

Regional Administrator Region II Mr. D. J. Burke NRC Resident Inspector Surry Power Station i

)