Monthly Operating Rept for Oct 1985
ML20136G688
Person / Time
Site: Ginna Constellation icon.png
Issue date: 10/31/1985
From: Mcnamara A, Spector S
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC
References
NUDOCS 8601080399
Download: ML20136G688 (6)


Text

b 1-OPERATING DATA REPORT DOCKET NO.

50-244 DATE November 11. 9185 b D%

COMPLETED BY Andrew E. McNamara TELEPilONE 1(315) 524-4446 Ext. 301 OPERATING STATUS Ginna Station

1. Unit Name:

R.E. GINNA NUCLEAR POWER PLANT

Note, October, 1985
2. Reporting Period:

1520 Reactor power level esenin-

3. Licensed Thermal. Power (MW ):

tion proceeded fran approx.

490

4. Nameplate Rating (Gross MWe):

45% on 10/1/85 to 100%

470

5. Design Electrical Rating (Net MWe):

achieved on 10/4/85. A re-490

6. Maximum Dependable Capacity (Gross MWe):

duction to 86% on 10/2/85 is 470 detailed on caoe 4.

7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
9. Power Level to Thich Restricted, If Any (Net MWe):
10. Reasons For Restrictions, if Any:

9601000399 8s1031 PDR ADOCK 05000244 R

PDR This Month Yr. to-Date Cumulative

11. Ilours In Reporting Period 745**

7.296.00 139.656.00 745**

6,391.03 106.839.74

12. Number of Ilours Reactor Tas Critical 0

0 1,687.55*

13. Reactor Reserve Shutdown flours 745 6.291.25 104.583.63
14. Ilours Generator On.Line 0

0 8.5*

15. Unit Reserve Shutdown llours
16. Gross Thermal Energy Generated (MTil) 1,116,312 9,275,208 145,560,969
17. Gross Electrical Energy Generated (MTil) 372,753 3,081,784 47,567,191 __
18. Net Electr al Energy Generated (MWil) 354.630

'2.929.920 45.112.941 100%

86.23%

74.89%

19. Unit Service Factor 100%

86.23%

74.89%

20. Unit Availability Factor 101.28%

85.44%

70.35%

21. Unit Capacity Factor (Using MDC Net)
22. Unit Capacity Factor (Using DER Net) 101.28%

85.44%

70.353 0%

1.91%

7.41%

23. Unit Forced Outage Rate
24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

Annual Refueling and Maintenance - February 8.1986 nmmrimarnly 49 diwat-inn

25. If Shut Down At End Of Report Period, Estimated Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION l

  • Cimriulative Total Comencing January 1,1975
    • Eastern Daylight Savings Time to Eastern Standard Time arv. a n m e

_Eay L

'4

.. AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-244 UNIT R.E. Ginna Nuclear Power Plant DATE November 11. 1985 COMPLETED BY 6 % r~ f N'r1,h Andrew L.

McNamara TELEPHONE 1 (315) 524-4446 Ext. 301 at Ginna MONTH October. 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL

.(MWe-Net)

(MWe-Net) 1.

405 17.

479 2.

431 18.

478 3.

458 19.

480 4.

475 20.

479 5.

479 21.

480 6.

480 22.

482 7.

480 23.

484 8.

480 24.

484 9.

480 25.

482 10.

481 26.

480 11.

480 27.

482 12.

480 28.

483 13.

481 29.

484 14.

481 30.

484 15.

481 31.

484 16.

479 INSTRUCTIONS On this format,. list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

t l

DOCKET NO.

50 244 UNIT NAME R.E. GINNA NUCLEAR POWER PLANT' UNIT SHUTDOWN AND POWER REDUCTIONS DATE -

II 1985 A

COMPLETED IlY I

REPORT MONTil October, 1985

'I El.EPliONE If 315) 524-4446 FM. 301 Ginna Station io Eq oI Licensee e,

e a

Cause & Corrective

  • I Event 2=

1 -3 Action to

'?, $ $

No.

Date 1

T, 3 3

,B $

j T

Report #

du

!0 Prevent Recurrence 2

g u

o P.R.

10/2/85 F

50 HA INSTRU

  • High Pressure E.H. Fluid was contmunated with water frun a cooler leak causing high pressure contro11nrs to malfunction. Power reduction to correct problem.

NOIE: See unit outage 85-6 Septernber,1985 report.

1 2

3 4

F: Forced Reason:

Method:

Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 14fanual for Preparation of Data B-Maintenance or Test 2-Manual Scram.

Entry Sheets for Licensee C-Refueling 3-Automatic Scram.

Event Report (LER) File (NUREG-D-Regulatory Restriction 4-Other (Explain) 0161)

,E-Operator Training & License Examination F-Administrative G-Operational Error (Explain) w nev.was

,,4, II-Other (Explain)

Exhibit 1 - Same Source

.. NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.

50-244 UNIT R.E. Ginna Nuclear Power Plant DATE November 11, 1985 COMPLETED BY

// ~ A - f. M 'r1< %

Andrew E. McNamara TELEPHONE 1 (315) 524-4446 EXT. 301 at Ginna MONTH October. 1985 i

Unit startup, which commenced on 9/30/85 at 0330 hours0.00382 days <br />0.0917 hours <br />5.456349e-4 weeks <br />1.25565e-4 months <br /> was reflected in reactor power level escalation on 10/1/85 from a low of - 45% to a high of - 97% on that date.

Further corrective action associated with components within the turbine E.H. System necessitated a reactor power level reduction to - 86% on 10/2/85.

When the problems were resolved the reactor power level was escalated to - 100% on 10/4/85 where it remained for the rest of the report period.

4

... _. _. _ ~. _. _ - _.,,

e-GINNA STATION MAINTENANCE REPORT

SUMMARY

OCTOBER, 1985 During the month of October, routine maintenance and inspections were completed.

Major safety related work included:

Diesel Fire Pump - PM Inspection

. Rebuild Spare Snubbers

. Repair Plug and Cage for V-110A

. Repacked V-5702 Primary / Secondary Snubbers Inspection T

1

'O d

=.,

=

R -[';" -

.f____

m" y

ROCHESTER GAS AND ELECTRIC CORPORATION

  • 89 EAST AVENUE, ROCHESTER, N.Y.14649

_ws e ma4

,3g

.p 6 4 y. 2 7 (,\\()

V(cf'et W at a

,a GINNA STATION November 11, 1985 Director, Office of Management Information and Program Analysis U.S. NUCLEAR REGULATORY COMMISSION Washington, DC 20555 4

Subject:

Monthly Report for October, 1985 Operating Status Information R. E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Sir:

Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of October, 1985.

Very truly yours, Stanley M. Spector Superintendent of Ginna Production l

SMS/eeg i

Attachments cc:

Dr. Thomas E. Murley NRC (1)