_
/D ; Commonwealth Edison.
) One First Nttional Plaza. Clucago, Illinois C-C ") Address Reply to. Post Office Box 767 q,.
j Chicago, Illinois 60690 November 18, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S.' Nuclear Regulatory Commission Washington, DC. 20555
Subject:
Revision to the Expected Fuel Lnad Dates
-For Byron Station Unit 2 and Braidwood Station Units 1 and 2 NRC Docket Nos.-50-455; 50-456/457 Reference (a):
Cordell Reed letter to H.
R. Denton dated December 24, 1984
Dear Mr. Denton:
Reference -(a) provided you with Commonwealth Edison Company's best estimates of the fuel load schedules for the subject units.
The most recent budget review of the schedule of engineering and' construction activities and preoperational testioq has resulted inia change in the estimate of the fuel load catec or Byran Station Unit 2 and Braidwood Station Units 1 and 2 to later dates.
The current estimate is that fuel can be loaded'in '3yron Unit 2 by not later than October 15, 1986, and~1n Braidwooo tinits 1 end 2 by September 30, 1986, and January 31, 1988, respec t iv ely.
There are, of' course, contingencies which could cause fuel load to occur later
.than the above dates.
I will continue to keep you advised er any changes in the scheduled fuel load date for these units.
Very truly yours, 8511220196 851118 PDR ADOCK 050 5
C~';
O h4j Cordell Reed Vice President
/klj cc:-
J. G. Keppler (RIII)
\\
0903K 1