Summary of 851105-06 Meetings W/Util in Granbury,Tx Re Activities Described in Program Plan.Areas Discussed Include Const Adequacy Review & S&W Piping & Pipe Support Activities.Transcript Encl
ML20136C153
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/02/1985
From: Vietticook A
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
To:
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
Shared Package
ML20136C157 List:
References
NUDOCS 8601030157
Download: ML20136C153 (4)


Text

'

PDR DEC 0 2 585 (,M2[

Docket Nos.: 50 445 M and 50-446 ,.-?

/

FACILITY: Comanche Peak Steam Electric APPLICANT: Texas Utilities Electric Company

SUBJECT:

SUMMARY

OF MEETING HELD ON NOVEMBER 5-6, 1985 -

FIRST MONTHLY STATUS MEETING TO DISCUSS THE ACTIVITIES DESCRIBED IN THE APPLICANTS' PROGRAM PLAN On November 5 and 6,1985, a public meeting was held in Granbury, Texas with representatives from the NRC and Texas Utilities. This was the first monthly status meeting regarding the activities described in the Applicants' Program Plan. The meeting was transcribed and the transcript is provided as an enclosure. The list of attendees at the meeting and all handouts provided at the meeting are included in the transcript.

I The NRC staff presented the status their review of the Program Plan. The following areas of NRC staff review were discussed: 1) the Construction Adequacy review, 2) the Construction Inspection activities being performed by Region IV, 3) the Design Adequacy review being performed by IE, 4) the Stone and Webster piping and pipe support activities, and 5) the Ebasco cable tray and conduit support activities.

J Representatives from Texas Utilities then provided the NRC staff with the status of their Program Plan activities. The following areas of the Program Plan were discussed: 1) the Design Adequacy program, 2) the Quality of Construction Inspection program, 3) the Technical Review Team (TRT) issues, 4) the Stone and Webster pipe and pipe support activities, and 5) the Ebasco cable tray and conduit support activities.

The NRC staff will review in more detail the following items: 1) the safety significant evaluation process, 2) the Construction Adequacy program homogeneous construction activities and how SSER 11, Appendix P, is being addressed, and 3) the Design Adequacy program homogeneous design activities.

Annette Vietti-Cook, Project Manager Comanche Peak Project Division of Licensing

Enclosure:

Transcript cc: See next page OFC :CPP :CPP :CPd  :  :  :

f(P . ______:____________:..____...___:.....______

_____:,__ ________:_____ ...... ..) , .....:__%

NAME : >

CT mell :VN n  :  ::

_____:_ ____ N_ .

C DATE:u/24/A5  : R/2v/85 :9/d//85  : /8  : -

0FFICIAL RECORD COP 1 e60103015/ B51202 PDR ADOCK 050 g 5 N

[ ""%, UNITED STATES

. 3 "^ ,

NUCLEAR REGULATORY COMMISSION j

42 g WASHINGTON, D. C. 20555 _

,...~ jeg '

V %4j DEC 0 21985 Docket Nos.: 50-445 and 50-446 FACILITY: Comancha Peak Steam Electric APPLICANT: Texas Utilities Electric Company

SUBJECT:

SUMMARY

OF MEETING HELD ON NOVEMBER 5-6, 1985 -

FIRST MONTHLY STATUS MEETING TO DISCUSS THE ACTIVITIES DESCRIBED IN THE APPLICANTS' PROGRAM 2

PLAN On November 5 and 6,1985, a public meeting was held in Granbury, Texas with representatives from the NRC and Texas Utilities. This was the first monthly status meeting regarding the activities described in the Applicants' Program Plan. The meeting was transcribed and the transcript is provided as an enclosure. The list of attendees at the meeting and all handouts provided at the meeting are included in the transcript.

The NRC staff presented the status their review of the Program Plan. The folicwing areas of NRC staff review were discussed: 1) the Construction Adequacy review, 2) the Construction Inspection activities being perfomed by Region IV, 3) the Design Adequacy review being performed by IE, 4) the Stone and Webster piping and pipe support activities, and 5) the Ebasco cable tray and conduit support activities.

Representatives from Texas Utilities then provided the NRC staff with the status of their Program Plan activities. The following areas of the Program Plan were dis:ussed: 1) the Design Adequacy program, 2) the Quality of Construction Inspection program, 3) the Technical Review Team (TRT) issues, 4) the Stone and Webster pipe and pipe support activities, and 5) the Ebasco cable tray and conduit support activities.

The NRC staff will review in more detail the following items: 1) the safety significant evaluation process, 2) the Constr;ction Adequacy program homogeneous construction activities and how SSER 11, Appendix P, is being addressed, and 3) the Design Adequacy program homogeneous design activities, f wm $U Annette Vietti-Cook, Project Manager Comanche Peak Project Division of Licensing

Enclosure:

Transcript cc: See next page u

W. G. Counsil Comanche Peak Steam Electric Station Texas Utilities Generating Company Units 1 and 2

, cc:

  • Nicholas S. Reynolds, Esq. Resident Inspector / Comanche Peak

, Bishop. Liberman, Cook, Nuclear Power Station Purcell & Reynolds e/o U.S. Nuclear Regulatory Commission 1200 Seventeenth Street, NW P. O. Box 38

Washington, D.C. 20036 Glen Rose, Texas 70043

! Robert A. Wooldridge, Esq. Regional Administrator, Region IV

} Worsham Forsythe, Sampels a U.S. Nuclear Regulatory Commission Wooldridge 611 Ryan Plaza Drive Suite 1000

2001 Bryan Tower, Suite 2500 . Arlington, Texas 76011
Dallas, Texas 75201

! Mr. Namer C. Schmidt Larry A. Sinkin Manager - Nuclear Services 3022 Porter Street, NW #304 .

Texas Utilities Generating Company Washington, D.C. 20008

Skyway Tower 400 North Olive Street, L.B. 81 Dallas, Texas 75201 -

4 Mr. Robert E. Ballard, Jr. Ms. Billie Pirner Garde Director of Projects Citizens Clinic Director Gibbs and Hill, Inc. Government Accountability Project

11 Pen Plaza 1901 Que Street, NW j New York, New York 10001 Washington, D.C. 20009 i

David R. Pigott, Esq.

Mr. A. T. Parker Orrick Herrington & Sutcliffe j Westinghouse Electric Corporation 600 Montgomery Street

! P. O. Box 355 San Francisco, California 94111

Pittsburgh, Pennsylvania 15230 Anthony Z. Roissan. Esq.

i Renea Hicks. Esq. Trial Lawyers for Public Justice l Assistant Attorney General 2000 P. Street, NW j .e. Environmental Protection Division Suite 611 l P. O. Box 12548, Capitol Station Washington, D.C. 20036 Austin, Texas 78711 Nancy E. Wiegers Mrs. Juanita Ellis, President Spiegel & McDiarmed l

Citizens Association for Sound Energy 1350 New York Avenue, NW -

1426 South Polk Washington, D.C. 20005-4798 Dallas, Texas 75224 .

~

Ms. Nancy H. Williams CYGNA 101 California Street San Francisco, California 94111 t

I Texas Utilities Electric Company Comanche Peak Electric Station Units 1 and 2 - . .

cc:

Resident Inspector - Comanche Peak c/o U.S. Nuclear Regulatory Commission P. O. Box 1029 Granbury Texas 76048 Mr. John W. Beck Vice President Texas Utilities Electric Company Skyway Tower 400 N. Olive Street, LB#81 Dallas, Texas 75201 Mr. Jack Redding Licensing -

Texas-Utilities Generating Company 4901 Fairmont Avenue Bethesda, Maryland 20814 William A. Burchette. Esq.

' Heron, Burchette, Ruckert & Rothwell Suite 700 1025 Thomas Jefferson Street, NW Washington, D.C. 20007

' Mr. James McGaughy Southern Engineering Company of Georgia 1800 Peachtree, Street, NW Atlanta, Georgia 30367-8301 Administrative Judge Peter B. Bloch U.S. Nuclear Regulatory Commission Washington, DC 20555 4

m Berbert Grossman Alternate Chairman ASLB Panel U.S. Nuclear Regulatory Commission i

Washington, DC 20555 Dr. Kenneth A. McCollom Dean Division of Engineering, Architecture i l

and Technology -

Oklahoma State University Stillwater, Oklahoma 74074

[

Dr. Walter H. Jordan 881 W. Outer Drive Oak Ridge, Tennessee 37830 '

I

_ _ . . _ _ . _ . _ _ _ . . _ _ , . _ _ . _ . _ . . _ _ _ _ _ _ . _ _ _ _ _ _ . _ . _ . . _ . , _ . . . _ . . _ . . _ . . . _ . . , _ . . . _ _ . .