Monthly Operating Rept for Aug 1985
ML20136B078
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 08/31/1985
From: Mcdonald R, Woodard J
ALABAMA POWER CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
NUDOCS 8511200125
Download: ML20136B078 (5)


Text

,

',s t

OPERATING DATA REPORT DOCKET NO. 50-348 DATE 9-5-85 COMPLETED BY

t. n. Mondard TELEPHONE /969T Roo-5156 OPERATING STATUS
1. Unit Name:'

T~rh

Wrla" - '

  • 4 '- 1
2. Reportas Penod: Au u u s t.1985
1) Cumulative data aince 2652 12-1-77, date of
3. I le===ad Thermal Power (MWt):

860 commercial operation.

4.' Namepiste Rating (Gross MWe):

5. Dengs Electncal Rating (Net MWe):

829 860.9

6. Maximma Dependable Capacity (Grom MWe):

816.5

7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:

v/A

9. Power Level To Which Restncted.lf Any (Net MWe):

M/^

10. Reasons For Restrictions,if Any:

N/A

~

This Month Yr to-Date Cudiulative 744 5,831 67.943

!!. Hours In Reportag Period

12. Number Of Hours Reactor Was Critical 76A o 4.575.1 46,704.I
13. Reactor Reserve Shutdown Hours 0.0 0.0

,cyn n

14. Hours Generator On-Line 144 0 4.452.2

&s L76_6

15. Unit Reserve Shutdown Hours 0.0 0.0 o,o
16. Gross Thermal Energy Generated (MWH) 1,958,242 11.336.453 115,237,028 36,776,244
17. Gross Electrical Energy Generated (MWH) 6A1 AAn

, nn, o,n

18. Net Electncal Energy Generated (MWH) 610.732

, Ano von

,,. n o n ' n,.,.

19. Unit Service Factor 100.0 76.4' 66.9 100.0 76.4 66.9
20. Unit Availability Factor
21. Unit Capnewy Factor (Using MDC Net) 100.5 72.9 63.7
22. Unit Capacity Factor (Using DER Net) on n 71.8 61,4
23. Unic Forced Outage Rate 0.0 1n 17.1 24.' Shutdowns Scheduled Over Next 6 Months (Type. Date, and Duration of Esch):

N/A

25. If Shur Down At End Of Report Period, Estimated Date of Startup:

N/A

26. Units In Test Status tPrior to Commercial Operation):

Forecast Achieved 8-6-77 8-9-77 INITIAL CRITICALITY INITIAL ELECTRICITY 8-20-77 8-18-77

.gf L

COMMERCIAL OPERATION 12-01-77 12-01-77 851 25 850531 N'/

P"120 asaapijp g-34

^

g,,,

r DOCKET NO.

so-un I

UNIT s.

DATE 9-5-85 dard COMPLETED BY (205) 899-5156 TELEPHONE

~ 510NT11 An on" - 1999 DAY AVERACE DAILY POWER LEVEL DAY AVERACE DAILY POWER LEVEL (alWe-Net)

(31We Net) 817 1,

17 815 2

819 gg pio Y ~'

a

~ ~ ' - --" - - -

819 3

818 20 822 4

823 3

971 21 825 825 6

g 819 7

23 R'A 825 821 g

24 825 9

gig 10 825 26 817 816 3g 820 27 822 12 2s gj7 13 826 3

g,,,

OI9 14 Al?

30 15 999 33 819 16 822 INSTRUCTIONS On this form:t. list the aversge daily unit power levelin MWe-Net for e:ch d:y in the reporting month. Compute io -

, the neare:t whole me;swatt.

(9/77)

~

O

y UNIT SilU1 DOWNS AND POWER REIME'HONS DOCKET NO. _5b-348 UNIT NAME J.M. Farley - Unit 1 DATE 9-5-85 COMPLETED gy J. D. Woodard REPORT MONTil.iagne - 1985 TELEPilONE (205) 899-5156 E

  • E' Licensec Ev, j*L u

.$ g

}

] ii,j Cause & Corrective N...

mie Lt gj h

jiji g Repms #

Pacvent Hecurrence eveni n

,3 Aai.ni i.

6 mu a_

d T HERE WERE P O UN IT SHU'I DOWN: ; OR S1 GNIFICANT PO WER Hl l DUCTIONS DURING THE MONTH'OF AUGUST.

I 2

3 4

F: ForceJ Reason:

Meshod:

Ealiibit G - Insieuctions S: Sclieduled A-Equipinent Failure (Explain) 1 Manual for Preparati<m of Data B. Maintenance of Test 2 Manual Scrasn.

Entry Sheets for 1.icensee C-Refueleng 3 Automatic Scram.

Event Rep.x (l.ER) FileINUREG-D Regulasiuy Resinicti<m 4-Oslies (Explain) 0161)

E-Opesaior Training A license Exandnation F Adadaisitative 5

G Opciati.wial Escor (Explain)

Exhibis ! Same Somce l's/77) ll Ollici (Eaplain)

Mailing Address

.,'pj-Atabima Power Company 600 North 18th Street Post Office Box 2641 Birmingham. Alabama 35291 Telephone 205 783-6090 R. P. Mcdonald Senior Vice Pre.*ident Flintridge Building

/Maf)allla POWCf

..gw.,,,,.,.

September 11, 1985 Docket No. 50-348 Director, Office of Resource Management U. S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Sir:

RE: Joseph M. Farley Nuclear Plant Unit 1 Monthly Operating Data Report Attached are two (2) copies of the August 1985 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 1, required by Section 6.9.1.10 of Appendix A of the Technical Specifications.

If you have any questions, please advise.

)

Yours very ily,

fJ R. P.

Donald i

l RPM /SNK:nac/F-2L i

' Enclosures t

xc: Director, IE (10 copies)

Director, RII (1 copy)

I t

1 V

i.

JOSEPR M.

FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE

SUMMARY

OF OPERATIONS AUGUST, 1985 There were no unit shutdowns or significant power reductions during the month of August.

The following major safety-related maintenance was performed in the month of August.

1.

Annual maintenance was performed on the 1-2A diesel generator.

2.

Miscellaneous corrective and preventive maintenance was performed on other-diesel generators.