ML20135E413

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp of License SNM-639.Corrective Actions:Application to Amend License Reflecting Operational Requirements of Licensee Submitted on 970220
ML20135E413
Person / Time
Site: 07000687
Issue date: 03/03/1997
From: Mcgovern J
CINTICHEM, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9703070034
Download: ML20135E413 (4)


Text

.

.h CINT4 CHEM, INC.

P.ClBOX81G TUXEDO, NEW YORK 10987 (914) 351-2131 March 3, 1997 US Nuclear Regulatory Commission Att: Document Control Desk Washington, DC 20555 g

Gentlemen:

Subj.- Reply to a Notice of Violation (Docket 70-687, SNM639), dated Feb. 6 1997 Ref.-

(a) NRC Notice of Violation dated Feb.

6, 1997 (b) Cintichem letter, JJM/kfs, dated Feb. 20, 1997 (c) NRC letter, JW Hickey, dated Dec.

6, 1996 (d) Cintichem letter, JA/bjc, dated Nov. 21, 1996 (e) Cintichem letter, JJM/64.96, dated Nov. 14, 1996 (f) Cintichem letter, JA/bjc, dated Jul.

3, 1996 (g) Cintichem letter, JJMcG/bjc, dated Apr. 19, 1996 (h) Cintichem letter, JJMcG/bjc, dated Mar. 26, 1996(supplemented May 10, 1996)

The subject Notice of Violation (ref.(a)) was issued because Cintichem neither completed the decommissioning by the scheduled completion date stipulated in SNM639 license condition H nor requested an amendment to extend the schedule for completing the project.

Per the subject Notice we are required to respond; providing information as to the cause or, if contested, any basis for dispute (1), corrective measures addressing the immediate(2) and root (3) causes and a specified date when full compliance will be achieved (4).

Our response per this requirement follows:

1.

The fact that decommissioning operations extended beyond the planned completion date stipulated in license condition H is acknowledged and our failure to apply for a

new scheduled completion date is attributed to our failure to maintain a distinction between the scheduled date of completion in license r

9703070034 970303 PDR ADOCK 07000607 l)/

j C

PDR 4

'i195EF5.EP.E.M

.z_.--

.-n

, -, ~ --

4 d

1 condition H (Jan.'96) and the license termination or expiration date(Dec.'96).

Our ultimate objective of the decommissioning project has always been the termination of the licenses. The i

predominant effort on this project since about Jan.'96 has been the performance of final surveys and remediation of areas requiring final cleanup as a result of the performance of these surveys. This has been a developmental and iterative process. Factual evidence of a

this effort is manifested in our final survey reports to the NRC i

listed as references (e) through (h) above. In addition to these survey reports we have made many status reports via telephone and in meetings with the NRC and other regulatory agencies over the past year. Our commitment to completing this project has been obvious. Our application for license amendment (Ref.(d)) to extend

)

the termination date of thn license beyond Dec. '96 is evidence of

{

our attention to the administrative requirements and in this application, we expressed the inherent difficulty in predicting a time for completion of this final phase of the decommissioning. The i

NRC response to this application (Ref,(c)) approved the extension

)

of the license for an indefinite period provided the termination of the decommissioning was actively pursued within the controls established in the Decommissioning Plan. Cintichem doesn't contest that literal (in the sense of formal) compliance with license l

condition H was not achieved; however, in view of the original reason for having a completion date stipulated in the license amendment that authorized the commencement of decommissioning, 2

Cintichem has surely complied with the intent of this condition. We have been in the final-survey phase of the projecu since Jan.

'96.

2. The immediate corrective action to amend license condition I

l H was taken.

Application to the NRC for license amendment i

reflecting the operational requirements of Cintichem and regulatory agencies during the final-survey phase of the

project, was submitted on Feb. 20, 1997. (ref. b, copy enclosed).

3.

Future occurrences will be avoided according to the final j

form of the revised license condition. We have requested that the project completion date be coincident with the license termination, which is dependant upon actions of the NRC as well as Cintichem.

If a definite date for completion is required to remain in license condition H for this final-survey stage of the project, it will be recognized as a distinctive action point requiring, if necessary, another license amendment due to some delay in achieving license termination by the NRC.

4.

Cintichem is currently in compliance with this license condition, awaiting approval of our latest application for amendment.

In summary, Cintichem acknowledges the cited non-compliance in that application was not made for a formal change to the scheduled completion date in license condition H, however we believe that, in

'O

' addition to the above mentioned considerations and those mention d e

in the Notice as mitigating circumstances for the use of enforcement discretion, the following additional circumstances that are unique to the Cintichem decommissioning should be cause for application of broader enforcement discretion to reverse this notice of violation.

-Cintichem had the understanding from the beginning of the project that the completion date at issue, which'~ was originally estimated and subsequently revised once by Cintichem since the initiation of this project, was established as a license condition in order to assure a diligent effort by the licensee to pursue the project to completion. Cintichem has done that and has been in the final-survey phase of the decommissioning for the past year or more.

-A key aspect of the Cintichem decommissioning that in particularly related to its duration should also be taken into consideration as a strong mitigating circumstance. The acceptance criteria by which the end of the Cintichem decommissioning will be defined are based on a calculated annual dose limit of 10 mrem TEDE to a future resident farmer who will depend on the site for subsistence.

This projected dose must be calculated without factoring in currently-existing municipal water supply systems and institutional controls on land use in the immediate area of the site. There is also no allowance for factoring in the probability that the future hypothetical resident will receive the calculated i

dose. Consequently, the acceptance criteria for this project are extremely conservative.

The dose limit in the currently proposed NRC regulations for decommissicning acceptance criteria is 15 mrem /yr and recent 1

statements by the Commission on this proposed limit indicate that it may bc set at 30 mrem /yr with allowances for institutional controls and for assessing probable risk of exposure to future occupants of decommissioned sites. If either of these recently proposed limits were adopted by the NRC and applied to the Cintichem project in lieu of the current license-specific criteria, significantly less final remediation and survey work would have been required and the project would have been finished much earlier.

Based on our experience in the final phase of the decommissioning, if the 30 mrem limit were the basis for the acceptance criteria for the Cintichem decommissioning we can confidently state that the decommissioning would have been finished much earlier than Jan.

'96.

-The Cintichem decommissioning project bus been conducted diligently, effectively and safely since Jan.

'92.

It involved the expenditure of over 725 person-years of labor as one measure of the project scope. There have been no citations to date for non-compliance with license or regulatory requirements. We have taken some pride in this record and believe that this citation that essentially arises from a formality should not be cause to spoil it.

In view of all of the above considerations, we believe that more discretion should be allowed in this instance for not i

declaring this incident a violation or,at least, reducing the matter to the class of a non-cited violation.

i Very truly yours l

PL/

ames

. Mc overn March 3, 1997 j

STATE OF NEW YORK l

COUNTY OF OPANGE Before me, a Notary Public for the County of Orange, personally appeared James J.

Mc Govern who, being duly swarn, 4

stated that he is President of Cintichem, Inc., that he has read the forgoing " Reply to a Notice of Violation",

and that the information and statements contained therein are true and correct to the best of his knowledge and belief.

v NOTARY PUBLIC ELYSE J.KOUCH Notary Public. State of New%et cc No.5003808 i

NYS-DOL, R. Aldrich County Of Orange

ORISE, E. Abelquist Commission Empires / / - e2 - 9 Er' USNRC-Region I, T. Dragoun USNRC-NRR, T. Michaels USNRC-NMSS, D. Orlando NYSDEC, B. Youngberg Robinson,Silverman,Pearce,Ahronson And Berman, C. Warren Tuxedo Town, K. Magar JJM77

wr 7

s.

t y e..

CINT1 CHEM, INC.

.fi P.O.' BOX B1B TUXEhO, NEW YORK 10987 (914) 351-2131 1

February 20, 1997 Mr. Dominick Orlando U.S. Nuclear Regulatory. Commission Office.of Nuclear Material Safety and Safeguards Division of Waste and Decommissioning Projects Branch 1 White Flint North 11555 Rockville Pike

/

Rockvil1e. MD 20852 Dear Mr. Orlando.

Reference:

(a) Docket 70-6S7. License SN.\\l639. Amendment 4: 7 Dated January 18. 1995 (b) USSRC letter (J.W. Hickey) dated December 6.

1996 The duration of. t he,Cint ichem decommissioning project has ex t ended be' yond t he scheduled compl e t ion da t e that is specified in-the last amendment to Condition H of the license (Ref. (all.

It has been necessary'to extend the project schedule for completion because:

- additional ~ work scope was discovered in the performance of.

final surveys in areas of the site that were not part of the original decommissioning plan and,

- the very low levels that were established for the acceptance criteria for surface contamination has required an iterative process of alternating survey work with final remediation work in order to establish confidence that the criteria have been satisfied. Consequent ly, the duration of the fina1 surveys had to be extended beyond what was anticipated in the last revision to license Condition H.

Currently, all remediation and survey work is scheduled to be finished by April 30, 1997 It is not known for certain when the confirmation survey

' report will be issued by ORISE.

NRC's contractor, and subsequently, when the license will be terminated by the NRC. Your letter of December 6, 1996 (Ref. (b)) concerning ths extension of the SNM 639 license expiration date, allowed an indefinite termination date provided decommissioning efforts were actively pursued. In view of - the developmental nature of the final i

work described above and the fact that the final decision about

)-

declaring the project completion will be made by the NRC, we believe that this rationale is very appropriate for this stage of s

the project and that Condition"H of the license should be amended

.to be less definite.

('u l

1 i())

0M

})5, w

r

F t

--L--g M

l -

However. if there is still a requirement

)

["

date'~by which the decommissioning will to specify a definite be completed. we recommend that an ample contingency period be provided to allow for the l

developmental nature of the final survey process and for the need to obtain NRC's concurrence t hrough t he confirmat ion survey process l

before t he decommissioning projec t can be complet ed. In t his event,

we propose that December 31, 1997 be the new termination date specified in license Condition H.

1 Very Truly Yours, M

Jame[J. McGovern President JJM/kfs CC:

USNRC/RegionI/Mr. T.

Dragoun ORISE/Mr. E. Abelquist NYDOL/Ms. R. Aldrich NYDEC/Ms.

B.

Youngberg USNRC/ORR/Mr. T. Michaels USNRC/NMSS/Mr.

D. Orlando Mr. C. Warren Town of Tuxedo /Mr. K. Magar f

+

d

,s I