Advises of Planned Insp Effort Resulting from Plant Semiannual Plant Performance Review Which Was Completed on 961029.Detailed Insp Plan for Next 8 Months Encl
ML20135A366
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/27/1996
From: Dyer J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Schnell D
UNION ELECTRIC CO.
References
NUDOCS 9612030193
Download: ML20135A366 (6)


Text

.

  1. 8"%q uNITEo STATES

.It NUCLEAR REGULATORY COMM;SSION REGloN IV E MW f

611 RYAN PL AZA DRIVE, SulTE 400 3,3....

.8 AR LINGToN, T E XAS 76011 8064 NOV 2 T 1996 Donald F. Schnell, Senior Vice President - Nuclear Union Electric Company P.O. Box 149 St. Louis, Missouri 63166

SUBJECT:

SEMIANNUAL PLANT PERFORMANCE REVIEW - CALLAWAY PLANT Oh O' tober 29,1996, the NRC' staff completed the Semiannual Plant Performance c

. Review (SPPR) of Callaway Plant. The staff conducts these reviews for all operating nuclear power plants to develop an integrated understanding of safety performance. The results are used by NRC management to facilitate planning and allocation of inspection resources. The SPPR for Callaway Plant involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period March l

1996 through September 1996. SPPRs provide NRC management with a current summary I

of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and Senior Management Meeting (SMM) reviews, l

i 1

i This letter advises you of our planned inspection effort resulting from the Callaway Plant l

SPPR review. It is provided to minimize the resource impact on your staff and to allow for j

l scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. The enclosure details our inspection plan for the next 8 months. The rationale or i

basis for each inspection outside the core inspection program is provided so that you are I

L aware of the reason for emphasis in these program areas. Resident inspections are not l

listed due to their ongoing and continuous nature.

We willinform you of any changes to the inspection plan if you have any questions, please contact W. D Johnson at (817) 860-8148.

Sincerely, 0

M J. E.

yer, Director i Division of Reactor Projects l

Docket Nos.: 50-483 License Nos.* NPF-30

Enclosure:

Inspection Plan l

9612030193 961127 PDR ADOCK 05000483 G

PDR

Union Electric Company cc w/ enclosure:

Professional Nuclear Consulting, Inc.

19041 Raines Drive Derwood, Maryland 20855 Gerald Charnoff, Esq.

Thomas A. Baxter, Esq.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, N.W.

Washington, D.C. 20037 H. D. Bono, Supervising Engineer Site Licensing Union Electric Company P.O. Box 620 Fulton, Missouri 65251 G. L. Randolph, Vice President Nuclear Operations Union Electric Company P.O.' Box 620 l

Fulton, Missouri 65251

)

Manager - Electric Department Missouri Public Service Commission 301 W. High P.O. Box 360 Jefferson City, Missouri 65102 Ronald A. Kucera, Deputy Director Department of Natural Resources P.O. Box 176 Jefferson City, Missouri 65102 Neil S. Carns, President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, Kansas 66839

l l

Union Electric Company l Dan I. Bolef, President Kay Drey, Representative Board of Directors Coalition for the Environment 6267 Delmar Boulevard University City, Missouri 63130 Lee Fritz, Presiding Commissioner Callaway County Court House 10 East Fifth Street Fulton, Missouri 65151 Alan C. Passwater, Manager l

Licensing and Fuels Union Electric Company P.O. Box 149 St. Louis, Missouri 63166 J. V. Laux, Manager Quality Assurance Union Electric Company P.O. Box 620 Fulton, Missouri 65251 k

I l

Union Electric Company ~ bec to DMB (IE01) _

bec distrib. by RIV:

L. J. Callan Resident Inspector DRP Director DRS-PSB Branch Chief (DRP/B)

MIS System Project Engineer (DRP/B)

RIV File Branch Chief (DRP/TSS)

Leah Tremper (OC/LFDCB, MS: TWFN 9E10)

Project Engineer (TSS) i l

DOCUMENT NAME: G:\\drpdir\\sppr\\cw.ltr To receive copy of document, indicate in box: "C" = Copy wthout enclosures "E" = Copy with enclosures "N" = No copy PE:DRP/B l

C:DRP/B l D:DRS lp D:DRP Af)l, l

DNGraves;cm b WDJohnsonW TPGwynnGy V JEDyeot/L @

11/ gg /96 11/g3 /96 11[,Z'l /96 '

11/q9/96 i

OFFICIAL RECORD COPY 030037

1 Union Electric Company gg@

bec to DMB (IE01) bec distrib. by RIV:

L. J. Callan Resident Inspector DRP Director DRS-PSB Branch Chief (DRP/B)

MIS System Project Engineer (DRP/B)

RIV File Branch Chief (DRP/TSS)

Leah Tremper (OC/LFDCB, MS: TWFN 9E10)

Project Engineer (TSS) l 4

i DOCUMENT NAME: G:\\drpdir\\sppr\\cw.ltr To receive copy of document. Indicate in box: "C" = Copy without enctosures "E" = Copy with enclosures "N" m No copy PE:DRP/B l

C:DRP/B l D:DRS l [J D:DRP Ml, l

DNGraves;cm e WDJohnsonp\\- TPGwynnGY JEDyeCt/L $

11/ n /96 11/ g1, /96 11/,Z~l /96 '

11/q9/96 OFFICIAL RECORD COPY

ENCLOSURE CALLAWAY PLANT l

lNSPECTION PLAN IP - Inspection Procedure Tl - Temporary Instruction Core inspection - Minimum NRC Inspection Program (mandatory all plants)

INSPECTION TITLE /

NUMBER OF DATES TYPE OF INSPECTION / COMMENTS PROGRAM AREA INSPECTORS IP 50002 Steam Generators 2

11/18-22/96 To complete baseline inspections for all Region IV plants IP 37001 10 CFR 50.59 Safety 1

12/9-13/96 To review the 10 CFR 50.59 program Evaluation Program IP 37550 Engineering 3

12/9-13/96 Core Inspection 1/6-10/96 IP 81700 Physical Security Program for 1

1/6-10/97 Core inspection Power Reactors Ti 2515/132 Malevolent Use of Vehicles at 2

1/6-10/97 Temporary Instruction Nuclear Power Plants IP 83750 Occupational Radiation 2

1/27-31/97 Core Inspection Exposure IP 40500 Effectiveness of Licensee 3

3/3-7/97 Core inspection Controls in Identifying, 3/17-21/97 Resolving, and Preventing Problems IP 71001 Licensed Operator 3

5/19-23/97 Core inspection Requalification Program Evaluation IP 62706 Maintenance Rule 6

6/2-6/97 To establish initial baseline for Callaway Plant implementation of maintenance rule requirements.