OPSEG
~
~
Public Service Electric and Gas Cornpany P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit NOV 211996 LR-N96387 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
-1 RETRACTION OF A 50.72 FOUR HOUR REPORT 5
FACILITY OPERATING LICENSE NPF-57 HOPE CREEK GENERATING STATION DOCKET NO. 50-354 On October 18, 1996, Public Service Electric and Gas Company (PSE&G) made a four hour report pursuant to the provisions of 10CFR50.72 (b) (2) (iii).
The report documented a concern about the capability of the Standby Liquid Control (SLC) System to perform its safety function when the system is operated at elevated temperatures during chemical additions.
Specifically, net positive suction head (NPSH) calculations at these elevated temperatures were not available to ensure that the NPSH requirements for these pumps were satisfied.
On November 14, 1996, Engineering had completed NPSH analyses fcr the SLC pumps and concluded that NPSH requirements could be satisfied at the maximum temperature rating of the SLC storage tank heater (150 degrees F).
The SLC pump NPSH requirements could be satisfied for all postulated storage tank temperatures (including elevated temperatures during chemical additions).
Since the safety function of SLC could be fulfilled, the associated four hour report was retracted on November 15, 1996.
Should you have any questions concerning this submittal, please contact us.
Sincerely, l
j f
Mark Be$ Illa General Manager -
Hope Creek Operations t
9612O20040 961121
\\
1 b
PDR ADOCK 05000354
- bsh P
PDR TkgwerisinwurhanA
.,o nn em
I NOV 211996 Document Control Desk LR-I96387 C
Mr. H. Miller, Administrator - Region I U.
S.
Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr.
D.
Jaffe, Licensing Project Manager - Hope Creek U.
S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Mr.
R.
Summers USNRC Senior Resident Inspector (X24)
Mr.
K. Tosch, Manager IV Bureau of Nuclear Engineering 33 Arctic Parkway CN 415 Trenton, NJ 08625
i NOV 211996 I
Document Control Desk LR-N96387 JPP BC Senior Vice President - Nuclear Operations (X04)
(
General Manager - Hope _ Creek Operations (H07) i Director - QA/NSR (X01) l Director - Nuclear Design Engineering and Projects (N25) l Director - Nuclear System Engineering (XO7)
Operations Manager - Hope Creek (H01) l Manager - Nuclear Safety Review (N38)
Manager - Hope Creek System Engineering (H18)
Manager - Hope Creek Engineering Design (N51)
Manager - Nuclear Business & Co-Owner Affairs (N28)
Onsite Safety Review Engineer - Hope Creek (H11)
Station Licensing Engineer - Hope Creek (X09)
General Solicitor, R.
E.
Selover (Newark, SG)
Perry Robinson, Esq.
Records Management (N21)
Microfilm Copy File Nos.
1.2.1, 1.2.2 i
l l
l i
1