Forwards Annual Operating Rept,1984. Design Changes Reflected as Being Completed Will Be Completed Prior to Startup from Current Outage
ML20134P680
Person / Time
Site: Cooper Entergy icon.png
Issue date: 02/28/1985
From: Pilant J
NEBRASKA PUBLIC POWER DISTRICT
To: Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20134P685 List:
References
CNSS853519, NUDOCS 8509090018
Download: ML20134P680 (1)


Text

,

e U T)MB COOPER NUCLEAR STATION P.O. BOX 98. BROWNVILLE, NE8RASKA 68321

Nebraska Pubh.c Power Distu.c t TELEP o~E i4o2> .23 3.i >

CNSS853519 February 28, 1985 Mr. Robert D. Martin Regional Administrator _

U. S. Nuclear Regulatory Commission Region IV g g {c )

611 Ryan Plaza Drive Suite 1000 g-4@

Arlington, TX 76011

N

Subject:

Annual Operating Report Cooper Nuclear Station NRC Docket No. 50-298, DPR-46

Dear Mr. Martin:

In accordance witn Paragraph 6.5.1 of the Cooper Nuclear Station Technical Specifications, the Nebraska Public Power District submits the Cooper Nuclear Station Annual Operating Report for the period of January 1, 1984 through December 31, 1984 We are enclosing one signed original for your use and, in accordance with Regulatory Guide 10.1 Revision 4, are transmitting one copy to the Director, Office of Inspection and Enforcement.

It should be noted that some of the design changes reflected as being completed in the enclosed will be completed prior to startup from the current outage.

Should you have any questions or corments regarding this report, please contact me.

Sincerely, M

. Pilant Technical Staff Manager Nuclear Power Group JMP:ss Enclosure cc: Director Oftice of Inspection & Enforcement w/1 encl.