Requests Relief from Requirements of 10CFR50.55a(g)(4)(v) for Period of One Yr Retroactive to Effective Date of Rulemaking
ML20134P477
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/17/1997
From: Mccoy C
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LCV-0968, LCV-968, NUDOCS 9702250483
Download: ML20134P477 (3)


Text

E

. s.

Georgb Power Company 4^ Inv rness CIntir Ptrkway Et Office Box 1295 Birmingham, Alabama 35201 Telephone 205 992 7122 Georgia Power C.K.McCoy me sourten elecacsprom Vice President. Nuclear Vogtte Project February 17, 1997 LCV-0968 Docket Nos.: 50-424, 50-425 U. S. Nuclear Regulatory Commission ATTN: Public Document Room Washington, D. C. 20555 Ladies and Gentlemen:

VOGTLE ELECTRIC GENERATING PLANT IMPLEMENTATION OF CONTAINMENT INSPECTION RULE REOUEST FOR ALTERNATIVE RULES By Federal Register Notice 154 (Volume 61) dated August 8,1996, the Nuclear Regulatory Commission (NRC) amended 10 CFR 50.55a to incorporate by reference the 1992 edition with 1992 addenda of Subsections IWE and IWL of Section XI, Division 1, of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code. The effective date for the amended rule was September 9,1996. An expedited implementation schedule required licensees to incorporate the new requirements into their inservice inspection plans and to complete the first containment inspections within five years (September 9,2001) of the effective date of the rule.

Georgia Power Company (GPC) interpreted the September 9,2001 implementation date to include the IWE/lWL repair / replacement provisions into the existing ASME Class 1,2, and 3 repair / replacement program for Vogtle Electric Generating Plant (VEGP), Units 1 and 2. Our intent was to include this work as part of the 10-year update of the inservice inspection (ISI) and inservice testing (IST) programs which are due May 31,1997. As result of an NRC letter dated November 6,1996 to the Nuclear Energy Institute (NEI),

we were made aware of the NRC position that the repair / replacement rules of ASME Section XI, Subsections IWE and IWL were to be implemented on September 9,1996 rather than in conjunction with the first set of containment inspections.

In its November 6,1996 letter to NEI, the NRC recognized the impracticality of requiring immediate compliance with the new rules and thus recognized the need for a period of-e Q

9702250483 970217

{DR ADOCK 05000424

[.

PDR W

o.-

~ L

.g UcorgiaPOWer

-U. S.' Nuclear Regulatory Commission

- LCV-0968 Page Two time for licensees to develop and implement procedures for repairs and replacements which meet the requirements of ASME Section XI, Subsections IWE and IWL. In accordance with the provisions of 10 CFR 50.55a(a)(3)(i), GPC hereby requests relief from the requirements of 10 CFR 50.55a(gX4)(v) (as identified in 61 Federa/ Register 41303) for a period of one (1) year retroactive to the effective date of the rulemaking.

GPC requests that the 'NRC grant relief until September 9,1997 to approximately coincide with the beginning of VEGP-1 Maintenance / Refueling Outage 1R7 for compliance with the rule as it is related to the implementation of repair and replacement activities which-comply with the 1992 Edition of ASME Section XI, with Addenda through 1992, for Class MC (metal containments) and CC (concrete containments) for Subsections IWE and IWL, respectively.

The containment structures for the two VEGP units are subjected to the testing of 10 CFR 50, Appendix J, and are included in the scope of the NRC Maintenance Rule. There have been no significant events which would indicate any safety concern over their structural

. integrity or their ability to perform their intended safety function. As a result, the proposed alternative discussed herein provides an acceptable level of quality and safety for VEGP.

A Should there be any questions in this regard, please contact this office.

t-Sincerely, q

C. K; McCoy l

CKM/JAE/jae xc: - (see next page for distribution) y i

. I y

A deorgiaPowerd

~

U. S. Nuclear Regulatory Commission LCV-0968 Page Three xc: Georgia Power Company-Mr. J. B. Beasley, Jr.

Mr. W. L. Burmeister Mr. M. Sheibani NORMS U. S. Nuclear Regulatory Commission Mr. C. R. Ogle, Senior Resident Inspector, Vogtle Mr. L. A. Reyes, Regional Administrator Mr. L. L. Wheeler, Licensing Project Manager, NRR

.